Sub topic 3
Implementation Scenarios: New Implementation, System Conversion, Selective Data Transition
This chapter assumes you know what SAP S/4HANA is, how it differs from SAP ECC, and the six SAP Activate phases at a basic level. Here you will learn the three main ways to reach S/4HANA and how each one changes the project approach.
Why the scenario matters
SAP Activate gives one set of phases for every project. The scenario decides what you do inside those phases. It affects how much you redesign, how you move data, how long the business is down, and how much of your existing custom code survives. Choose the scenario early, because it shapes the Discover and Prepare outcomes.
The three scenarios
New implementation
You install a fresh S/4HANA system and load the data you need into it. This is often called greenfield. The old system is not upgraded.
- Processes start from SAP Best Practices, and you adopt standard processes where you can.
- You migrate selected master data and open items, not the full history.
- Old custom code is not carried over unless you rebuild it.
- Fit-to-Standard workshops in Explore carry the most weight here, because the business is redesigning its processes.
System conversion
You convert an existing SAP ECC system in place. This is often called brownfield. The system keeps its configuration, data and history.
- You run readiness checks first, such as the simplification item check and the custom code analysis.
- You adapt custom code and fix data that fails the new rules, such as the business partner model.
- Business processes change less, so Explore focuses on what differs from today instead of a full redesign.
- Testing in Realize leans on regression tests of the existing processes.
Selective data transition
You move only part of the landscape. Examples are one company code, one business unit, or a merge of several systems into one. This is sometimes called bluefield. It can start from a copy of the current system, or from a new system with chosen data and configuration.
- You decide which data, history and configuration to take, and which to leave behind.
- Tools and service providers do much of the data selection work, so the data migration workstream grows.
- Cutover needs the most planning, because you must keep the moved and unmoved parts consistent.
Comparing the scenarios
| Aspect | New implementation | System conversion | Selective data transition |
|---|---|---|---|
| Starting point | Empty new system | Existing ECC system | Existing system, or new system with chosen data |
| Process change | High | Low to medium | Varies by scope |
| Data history | Selected data only | Kept | Chosen by scope |
| Custom code | Rebuilt as needed | Adapted | Chosen by scope |
| Main risk | Change management load | Technical debt and data quality | Data consistency across parts |
How the scenario shapes the phases
Common errors
- Choosing system conversion to avoid change, then discovering that data quality and custom code need as much effort as a redesign.
- Choosing new implementation but copying old processes into the new system. This brings back the customizations you wanted to leave.
- Treating selective data transition as a small project. Its scope decisions are the hardest part.
Exercise
A company runs a heavily customized ECC system and wants to keep its full financial history in the new system. Which scenario fits best, and which Realize activity will take extra effort?
Show answer
System conversion fits best, because it keeps the existing data and history. The extra effort goes into analyzing and adapting custom code and fixing data that fails the S/4HANA checks.