Selecting and Tailoring a Roadmap for Your Project
This chapter assumes you know the six SAP Activate phases (Discover, Prepare, Explore, Realize, Deploy, Run), the main S/4HANA implementation scenarios, and the role of workstreams and quality gates. Here you will learn how to pick a starting roadmap and adapt it to your project.
Why a roadmap needs tailoring
SAP Activate provides several roadmaps. Each is a template of phases, deliverables, tasks and accelerators. No template fits a real project unchanged. A roadmap that is too heavy wastes effort on deliverables nobody needs. One that is too light skips controls the project depends on.
Tailoring means choosing the right roadmap first, then adding, removing or reshaping content within it.
Step 1: Select the roadmap
Two inputs drive the choice: the deployment model and the implementation scenario.
| Input | Typical options | What it changes |
|---|---|---|
| Deployment model | Public cloud, private cloud, on premise | How much configuration and extension is allowed, and who runs upgrades |
| Implementation scenario | New implementation, system conversion, selective data transition | How much existing data, custom code and process design carries over |
For example, a new implementation on public cloud leans on standard SAP Best Practices and guided configuration. A system conversion of a heavily customized ECC system needs more time for custom code analysis, data migration and testing of existing processes.
Use the roadmap viewer to find the roadmap that matches your combination. Read its phase descriptions before you commit.
Step 2: Tailor the content
Work through the roadmap phase by phase and ask the same questions each time.
- Which deliverables does this project actually need? Remove the rest, and record why.
- Which deliverables are missing? Add them, for example regulatory validation in a regulated industry.
- Which workstreams matter most? A project with heavy integration needs more depth in the technical and integration workstreams.
- Which quality gates apply? Keep the gates, and adjust their exit criteria to your risk level.
- How many iterations will Realize need? Base this on the number of fit-gap results and extensions.
The tailoring flow is easier to see as a diagram.
Common errors
- Choosing a roadmap by habit. A team that always used one roadmap may apply an on-premise approach to a public cloud project and fight the standard.
- Deleting quality gates to save time. Gates are the points where the sponsor sees real status. Shorten the criteria if needed, but keep the gate.
- Tailoring once and never again. Revisit the plan at each phase exit, because Explore results often change the Realize plan.
- Copying every deliverable. Unused deliverables create work and hide the ones that matter.
Summary checklist
- Identify the deployment model and the scenario.
- Select the matching roadmap in the roadmap viewer.
- Review deliverables, workstreams and gate criteria phase by phase.
- Document and agree the changes.
- Review the tailoring at each phase exit.
Exercise
A company is converting a heavily customized ECC system to S/4HANA on premise. Name two areas of the roadmap you would likely expand, and one thing you would not remove.
Show answer
Expand custom code analysis and data migration (or testing of existing processes). Do not remove the quality gates. You may adjust their exit criteria, but the gates give the sponsor a checkpoint at each phase.