Sub topic 7
Prepare: Mobilizing the Project
This chapter assumes you know what the Discover phase produces, can read a basic project plan, and understand the difference between SAP ECC and SAP S/4HANA. Prepare is the second of the six SAP Activate phases. Its purpose is to turn an approved business case into a project that can start work.
What Prepare is for
Discover ends with a decision to proceed. Prepare answers the practical questions that follow. Who is on the team? What is the scope? Which systems will be used? How will the project be run and governed?
The phase is short compared with Realize, but weak decisions made here cause delays later.
Main activities
The work in Prepare falls into five groups.
- Project planning. The team selects and tailors the roadmap, sets the schedule, and defines scope boundaries. A first version of the project plan and a budget baseline are created.
- Governance and organization. The team sets up a steering committee, names a project manager, and assigns roles. Each role has a clear owner on both the customer side and the partner side.
- Project standards. These are the rules the project follows. They cover the change request process, issue and risk handling, documentation conventions, and the test strategy.
- Team enablement. Team members learn the Fit-to-Standard approach, the chosen SAP solution scope, and the project tools.
- System setup. The team requests and prepares the first systems. For a cloud project, this usually means getting access to the starter system with preconfigured SAP Best Practices content.
Key deliverables
| Deliverable | What it contains | Why it matters |
|---|---|---|
| Project charter | Goals, scope, roles, assumptions | Gives everyone one shared definition of the project |
| Project plan | Timeline, milestones, resources | Sets the baseline for tracking progress |
| Governance model | Steering committee, escalation path | Decides who can approve changes |
| Standards and procedures | Change, risk, issue, test rules | Keeps the team consistent |
| Initial system access | Starter or sandbox system | Lets the Explore phase begin with a working system |
How Prepare connects to the other phases
Prepare takes the business case from Discover as its input. Its output is a mobilized team and a project plan, which feed the Explore phase. The quality gate at the end of Prepare checks that these items exist and are approved before the project moves on.
Common errors
- Starting Explore without a baseline scope. Workshops then drift, and scope grows without any control.
- Skipping team enablement. If the team does not understand Fit-to-Standard, it tends to collect custom requirements instead of reviewing standard processes.
- Leaving governance vague. Without a named decision maker, change requests wait for weeks.
- Treating the plan as fixed. The plan is a baseline. Activate expects it to be refined as the team learns more.
Exercise
A project team finishes Discover and wants to begin Fit-to-Standard workshops next week. Name two Prepare deliverables that should already be in place, and explain why each is needed.
Show answer
The project plan and the governance model are two examples. The plan gives the workshops a defined scope and schedule, so they do not drift. The governance model names who can approve scope changes that come out of the workshops. Initial system access is also a valid answer, because participants need a system to see the standard processes.