Sub topic 6
Discover: Evaluating S/4HANA and Building the Case
This chapter assumes you know what SAP S/4HANA is, how it differs from SAP ECC, and basic project terms such as phase, deliverable and milestone. Discover is the first of the six SAP Activate phases. It comes before any project exists. Its job is to help an organization decide whether and how to adopt S/4HANA.
Purpose of the phase
Discover answers three questions. Does S/4HANA fit our business goals? Which deployment model and implementation scenario suit us? Is the investment justified?
The phase ends with a decision, not a configured system. A "no" or "not yet" is a valid result. It is cheaper than a failed project.
Main activities
Teams usually work through these activities. The order varies.
- Explore the solution. Business and IT leaders look at what S/4HANA offers for their industry. They use trial systems, demos and the SAP Best Practices content. A trial system is a pre-configured sandbox that people can log in to and click through.
- Assess the current landscape. The team lists existing systems, custom code, interfaces and data volumes. For an ECC customer, this shows how large a conversion would be.
- Choose a direction. The team compares deployment models (cloud or on premise) and implementation scenarios (new implementation, system conversion, selective data transition). The next chapters in this tutorial's plan treat these in detail, but Discover is where the first choice is made.
- Build the business case. The team estimates costs, benefits, risks and timing.
- Draft a roadmap. A rough plan shows phases, effort and a likely start date.
Building the business case
A business case turns a technical idea into a decision a sponsor can approve. It usually contains the items below.
| Element | What it covers | Example |
|---|---|---|
| Drivers | Why change now | ECC end of maintenance, slow financial close |
| Benefits | Expected gains | Faster close, fewer manual reconciliations |
| Costs | One-time and running | Licenses or subscription, partner effort, training |
| Risks | What could go wrong | Heavy custom code, poor data quality |
| Timeline | Rough duration | 12 to 18 months |
Be careful with benefits. A claim such as "better reporting" cannot be checked later. A claim such as "reduce month-end close from eight days to five" can be.
Typical deliverables
- Business case and a high-level cost and benefit estimate
- Selected deployment model and implementation scenario
- Landscape and custom code assessment summary
- Draft roadmap with rough timeline
- Go or no-go decision from the sponsors
Common errors
- Starting from technology instead of outcomes. A case built on "we need S/4HANA" has no measurable goals. Start from business problems.
- Skipping the landscape assessment. Hidden custom code and poor master data often raise cost late in the project.
- Treating the estimate as final. Discover estimates are rough. Refine them in Prepare and Explore.
- Leaving business stakeholders out. IT-only cases lose support when budget is requested.
Exercise
A company on SAP ECC wants to move to S/4HANA. Its IT team has written a case that says "S/4HANA is the future of SAP." Name two things missing from this case and one Discover activity that would supply them.
Show answer
Missing items include measurable business benefits (for example a shorter financial close), cost estimates, and risks. A landscape and custom code assessment would supply cost and risk inputs. Drafting the business case with business stakeholders would supply the measurable benefits.