Sub topic 4
The Six Phases at a Glance
This chapter gives you the map of an SAP Activate project. It assumes you know what an ERP system is, understand phases, deliverables and milestones, and know how SAP S/4HANA differs from SAP ECC. Later chapters cover each phase in detail.
The working model
SAP Activate divides an S/4HANA implementation into six phases: Discover, Prepare, Explore, Realize, Deploy and Run. Each phase has a purpose, a set of deliverables, and a quality gate that marks its end. The phases run in order, but work inside a phase is often iterative. Realize, for example, is built from short build-and-test cycles.
| Phase | Main question | Typical outputs |
|---|---|---|
| Discover | Is S/4HANA right for us, and which path do we take? | Business case, solution trial, high-level scope |
| Prepare | Is the project ready to start? | Charter, plan, team, governance, system access |
| Explore | What does the standard solution cover, and what is missing? | Fit-to-Standard results, backlog of gaps and requirements |
| Realize | Can we build and prove the solution? | Configured and extended system, tested processes, migrated data |
| Deploy | Are we ready to switch to the new system? | Cutover plan, trained users, productive system |
| Run | Is the system stable and improving? | Hypercare exit, operations handover, improvement backlog |
How the phases connect
Each phase produces the input for the next one. Discover yields a decision and an approach. Prepare turns that decision into a staffed project. Explore turns the scope into a validated list of requirements. Realize builds that list. Deploy moves the result into production. Run keeps it healthy.
Reading the roadmap
An SAP Activate roadmap lists each phase with its deliverables and tasks. To place an activity in a phase, ask what it produces and who needs that output next.
- Evaluating a trial system or drafting a business case belongs in Discover.
- Appointing the project manager and setting up governance belongs in Prepare.
- Running workshops that compare business processes to standard SAP Best Practices belongs in Explore.
- Configuring, building extensions, running integration tests and loading test data belongs in Realize.
- Rehearsing cutover, training users and going live belongs in Deploy.
- Resolving post-go-live incidents and planning upgrades belongs in Run.
Common errors
- Treating the phases as a strict waterfall. Explore and Realize overlap in practice, because gaps found in Explore feed iterations in Realize.
- Skipping Discover because the decision seems made. Without it, scope and approach are usually unclear when Prepare starts.
- Placing user training late in Realize or ignoring it until Deploy begins. Training material depends on the final solution, so plan it as a Deploy deliverable that is prepared earlier.
- Closing a phase without its gate review, which pushes open risks into the next phase.
Exercise
A team has finished running workshops that compare their order-to-cash process with the standard solution. They now have a list of gaps. Which phase are they in, and which phase comes next?
Show answer
They are in Explore, because the workshops validate the standard solution with the business and produce the gap list. Realize comes next, where the gaps are configured or extended and tested in iterations.
Exercise
Name the phase that ends with hypercare exit and an improvement backlog, and give the phase before it.
Show answer
Run ends with hypercare exit and an improvement backlog. Deploy comes before it.