Sub topic 12
Deploy: Cutover and Go-Live
This chapter assumes you know the Explore and Realize phases. You should also know what a quality gate is and have a basic idea of how data migration and testing work in an ERP project.
What the Deploy phase is for
Deploy moves the tested solution from the project environment into production. It ends when the business runs live on the new system and the project hands over to support. The phase has a fixed target: the go-live date agreed at the Realize exit gate.
Typical deliverables:
- An approved cutover plan with owners, durations and a rollback decision point.
- Completed end-user training and a confirmed support organization.
- Final data loads, reconciled against the source.
- A signed go-live decision.
- A transition into hypercare, the stabilization period at the start of the Run phase.
Cutover
Cutover is the controlled switch from the old system to the new one. It is a sequence of timed tasks, each with an owner. It is not a single event.
A cutover plan usually covers these areas:
- Freeze: stop changes in the source system and in the transport landscape.
- Final data migration: load master data, open items and balances.
- Reconciliation: compare totals and record counts between source and target.
- Technical tasks: activate interfaces, jobs and authorizations.
- Business sign-off: key users confirm the system is ready.
- Go/no-go decision.
Rehearsals
Run at least one full cutover rehearsal, often called a dress rehearsal, in a production-like system. Measure how long each task takes. The real cutover window, often a weekend, must fit those timings with some buffer.
Rehearsals expose problems early. Common findings are data load errors, missing authorizations and interfaces that were not switched over.
Common errors
| Error | Effect | Prevention |
|---|---|---|
| Skipping a rehearsal | Unknown durations, overrun of the window | Rehearse and time every task |
| No rollback criteria | Disputes during the go/no-go decision | Define rollback conditions in advance |
| Late user training | Posting errors after go-live | Finish training before cutover |
| Unreconciled data | Wrong balances in production | Set reconciliation checks with finance owners |
| Interfaces forgotten | Orders or payments stop flowing | List every interface in the plan |
Go-live readiness
The project team usually runs a readiness check before the go/no-go decision. It covers open critical defects, test results, data quality, user readiness, and support staffing. The steering committee then makes the decision based on evidence rather than on the calendar.
Handover to Run
After go-live, the team enters hypercare. Project members stay close to users and fix issues quickly. When incident volumes fall to agreed levels, support moves to the normal operations team. The next chapter covers this part of Run.
Exercise
Your cutover rehearsal took 38 hours, but the planned window is 30 hours. What should you do before the go/no-go decision?
Show answer
Do not proceed on the current plan. Find which tasks ran longest, then optimize them, for example with parallel loads, smaller data volumes or earlier preloads. Alternatively, extend the window. Then repeat the rehearsal to confirm the new timing fits.