Run: hypercare, operations and continuous improvement
This chapter assumes you know the earlier phases (Discover through Deploy), what cutover is, and the basics of support organizations such as a service desk. It covers the sixth and last SAP Activate phase.
What the Run phase is for
Run starts after go-live. Its purpose is to stabilize the productive system, hand responsibility to the operations organization, and keep improving the solution. In a cloud deployment, the Run phase also includes taking in the regular upgrades the vendor delivers.
The phase has three parts that overlap in practice:
- Hypercare: a short, intensive support period right after go-live.
- Operations: steady-state support of the system and its processes.
- Continuous improvement: planned changes that add value after stabilization.
Hypercare
Hypercare is usually a fixed period of a few weeks, agreed before go-live. The project team stays close to the business and fixes problems quickly, because users meet real data and real volumes for the first time.
Typical activities:
- Monitoring critical processes such as order-to-cash or period-end close.
- Triaging incidents by priority and fixing defects found after go-live.
- Answering user questions and giving extra training.
- Checking interfaces, batch jobs and performance against expectations.
- Recording lessons learned for the project.
Set exit criteria for hypercare in advance. Examples are no open incidents of the highest priority, incident volume at an agreed level, and a successful first period-end close.
Handover to operations
The project team transfers knowledge to the support organization. This covers documentation, support procedures, known issues and the process for requesting changes. Handover must be explicit. Without it, the project team keeps answering tickets informally long after the project budget ends.
Operations
In steady state, the support organization runs a tiered model. Level 1 handles user questions, level 2 handles functional and technical analysis, and level 3 handles complex defects, often with SAP. Common operations tasks include:
- Monitoring system health, jobs and interfaces.
- Managing users, roles and authorizations.
- Handling incidents, problems and change requests.
- Applying updates. In cloud editions SAP delivers them on a fixed schedule, so you must plan regression testing for each release.
Continuous improvement
After the system is stable, the business collects ideas for better use of the solution. Sources include user feedback, incident trends, new releases that add functions, and process KPIs. The team evaluates each idea, prioritizes it, and delivers it in small increments. Preferring standard functions and clean extensions keeps this work cheap and keeps upgrades safe. This follows the same principle as the Fit-to-Standard approach in Explore.
| Aspect | Hypercare | Operations | Continuous improvement |
|---|---|---|---|
| Timing | Weeks after go-live | Ongoing | Ongoing, in increments |
| Main people | Project team and support | Support organization | Business and IT together |
| Goal | Stabilize | Keep running | Add value |
Common errors
- Ending hypercare by date only, without checking exit criteria.
- Skipping handover, so support knowledge stays with a few consultants.
- Treating go-live as the end of change management, so adoption stays low.
- Not testing cloud releases, which then break custom processes.
Exercise
Your hypercare period is scheduled to end tomorrow, but several highest-priority incidents are still open. What should you do, and why?
Show answer
Do not close hypercare on the date alone. Compare the situation with the agreed exit criteria, which usually require no open highest-priority incidents. Extend hypercare or agree a documented plan with named owners, so the support organization can take over without losing the project team's knowledge.