Workstreams that run across the phases
SAP Activate splits an S/4HANA project in two directions. The six phases (Discover, Prepare, Explore, Realize, Deploy, Run) cut it by time. Workstreams cut it by subject. This chapter covers the second cut: what a workstream is, which ones you will meet on a typical roadmap, and how their work moves through the phases.
This chapter assumes you know the six phases by name and purpose, and that you have worked on or around a project plan with deliverables and milestones. Later chapters cover each phase in detail.
What a workstream is
A workstream is a group of related tasks, deliverables and responsibilities that continues across several phases. Each workstream has an owner, a set of skills, and its own tasks in the roadmap. The phase decides what is due now. The workstream decides who does the work and what knowledge it needs.
A phase exit question such as "Is the solution ready for cutover?" cannot be answered by one team. Testing, data, integration, security and training each contribute part of the answer. Workstreams make those contributions visible and assign them to people.
The roadmap is organized as a grid. Each phase is a column, and each workstream is a row. A task sits where a phase and a workstream meet. When you open a phase in the roadmap viewer, you see its tasks grouped by workstream.
Common workstreams
Workstream names and groupings differ between roadmaps. The roadmap for SAP S/4HANA Cloud Public Edition is lighter than the one for SAP S/4HANA Cloud Private Edition or on-premise, and SAP revises both over time. Treat the list below as typical, and check the roadmap you actually use.
| Workstream | Main concern | Typical peak phases |
|---|---|---|
| Project management | Planning, budget, risks, governance, status reporting | All phases |
| Solution adoption (organizational change management) | Stakeholder impact, communication, training, readiness of the people | Prepare through Run |
| Application design and configuration | Business processes, fit-to-standard results, configuration of the standard | Explore and Realize |
| Extensibility | Custom fields, custom logic, side-by-side apps, kept outside the standard core | Explore and Realize |
| Data management | Data migration, data quality, cleansing, archiving | Prepare through Deploy |
| Integration | Interfaces to other SAP and non-SAP systems | Explore through Deploy |
| Analytics | Reports, dashboards, embedded analytics | Explore and Realize |
| Testing | Test strategy, test cases, execution, defect handling | Realize and Deploy |
| Technical architecture and infrastructure | Landscape, sizing, system setup, performance | Prepare through Deploy |
| Security and authorizations | Roles, access, compliance controls | Realize and Deploy |
| Operations and support | Support model, monitoring, service processes | Deploy and Run |
Some roadmaps also list a customer team enablement or learning workstream. It builds the project team's own skills early, before the end-user training that solution adoption handles later.
How the grid looks over time
The chart below shows how the emphasis of selected workstreams shifts across a project. The dates and durations are illustrative only. Real projects vary widely.
Three patterns matter more than the exact bars:
- Project management never stops. It covers the whole timeline, including Run.
- Some workstreams start earlier than people expect. Data management starts in Prepare, not in Realize.
- Some workstreams change character instead of ending. Testing begins as strategy, becomes test case design, then execution, then cutover rehearsal.
Workstreams in each phase
The list below shows what each workstream usually does in each phase. It gives examples, not a complete task list.
- Discover. Project management builds the business case. Application design records the processes and pain points that motivate the move. Technical architecture considers deployment options. Most other workstreams exist only as early input.
- Prepare. The project is mobilized. Project management sets governance, plans and the team. Technical architecture provisions the first systems. Data management starts scoping the data sources. Solution adoption starts a stakeholder analysis and a first change plan.
- Explore. Application design leads the fit-to-standard workshops and produces the backlog. Extensibility records the gaps that need an extension. Integration lists the interfaces. Data management refines the migration scope. Testing defines the strategy. Analytics identifies reporting needs.
- Realize. This phase is the busiest. Configuration, extensions, interfaces, migration programs, roles and reports are built in iterations. Testing runs unit, integration and user acceptance tests. Solution adoption builds training material.
- Deploy. Data management runs mock migrations and the final load. Testing covers cutover rehearsals. Security finalizes roles. Operations and support prepare the support organization. End users are trained.
- Run. Operations and support take over, with hypercare first. Solution adoption measures whether people use the new system. Application design handles the improvement backlog.
Dependencies between workstreams
Workstreams are not independent, and most project delays come from the gaps between them. These dependencies are the usual ones:
- Application design to testing. Test cases come from the process definitions and fit-to-standard results. If design decisions arrive late, test preparation stalls.
- Application design to data management. The processes you keep decide which data objects you must migrate. A scope change in design changes the migration scope.
- Integration to testing. End-to-end tests need the connected systems and their test environments. Teams of the other systems must be scheduled early.
- Security to testing. Test users need the final roles. Without them, testers cannot tell a missing authorization from a real defect.
- Solution adoption to everything else. Training content depends on stable process definitions, so adoption has to follow design decisions closely.
A practical habit is to record these dependencies in the plan as explicit links and review them in each iteration. A task that is "finished" in its own workstream but blocks another one is a risk that status reports often hide.
Workstream governance
Each workstream needs a lead, and the leads together form the core of the project's delivery management. Three practices keep this manageable:
- One owner per deliverable. The roadmap assigns tasks to workstreams, but your plan must assign them to named people.
- A shared cadence. Workstreams report on the same rhythm, such as weekly status and per-iteration reviews. That makes cross-workstream blockers visible.
- Quality gates as joint checkpoints. A quality gate reviews all workstreams together, so a gap in one cannot be hidden by progress in another. Quality gates get their own chapter.
Tailoring workstreams
You may merge, rename or drop workstreams. A small cloud project might combine integration and extensibility under one technical lead. A system conversion adds work to data management and technical architecture, because the existing system and its custom code must be assessed. What you should not do is drop a subject area. If you remove a workstream, make sure a named person still owns each of its deliverables.
Exercise
Your project is in Explore. A teammate says data management can wait until Realize, when the configuration is stable. Give two reasons from this chapter why that is risky.
Show answer
First, the data migration scope depends on which processes and data objects remain after the fit-to-standard workshops, so data management needs to take part in Explore to scope correctly. Second, data quality problems take time to find and fix. Finding them in Deploy, during mock migrations, is much more costly than finding them early. Data management typically starts in Prepare and runs through Deploy.
Exercise
Testing cannot start user acceptance tests because testers keep reporting failures that turn out to be missing permissions. Which two workstreams are involved, and what is the dependency?
Show answer
Testing and security and authorizations. Testing depends on the security workstream delivering final roles and test users in time. The fix is to schedule role delivery before test execution and to record that link in the plan.