This chapter assumes you know what SAP S/4HANA is and how it differs from SAP ECC. It also assumes you are familiar with project phases and deliverables, and that you have seen the six SAP Activate phases (Discover, Prepare, Explore, Realize, Deploy, Run) at a high level. Here you will learn the three main S/4HANA implementation scenarios, what separates them, and how each one changes the work inside the phases.
Why the scenario matters
SAP Activate gives one phase structure for every project. The activities inside those phases are not the same for every project. The scenario you pick sets the starting point of the system, the way data reaches S/4HANA, how much of the existing design you keep, and how much of the business must be re-examined.
Pick the scenario early, ideally in Discover and no later than Prepare. It drives the roadmap you select, the team skills you need, the scope of Fit-to-Standard workshops, the testing strategy, and the cutover plan. Changing scenario after Explore usually means redoing planning and design work.
The three scenarios
SAP uses these names for the main paths to S/4HANA. Some sources use other labels, such as "greenfield", "brownfield" and "bluefield". Those labels are informal, so confirm what a colleague means before relying on them.
New implementation
A new implementation sets up a fresh S/4HANA system. You do not carry over the old system. You design processes from SAP's predefined best practice content and migrate only the data you choose, such as master data and open items.
This is the scenario where Activate's Fit-to-Standard approach has the most effect. The team starts from standard processes and asks where the business must differ. Typical reasons to choose it:
- The current landscape is heavily customized and the business wants to simplify.
- The company is moving from a non-SAP system, or from several SAP systems.
- The company is a new organization or a new legal entity.
- Leadership wants to adopt a cloud deployment model and keep the core standard.
Trade-offs: you get a clean design and fewer inherited problems, but you must migrate data deliberately, rebuild interfaces, and retrain users for processes that may look different.
System conversion
A system conversion moves an existing SAP ERP system, usually ECC, to S/4HANA in place. The technical tools are Software Update Manager (SUM) with Database Migration Option (DMO), together with the Maintenance Planner and the readiness checks. The system keeps its configuration, custom code, and business data. SAP's data model changes, for example the Universal Journal and the Business Partner model, and the conversion transforms the data to match.
Typical reasons to choose it:
- The existing processes work and the business wants continuity.
- The data history must be kept in one system.
- The timeline favors a single technical move over a redesign.
Trade-offs: you inherit old customizations and design choices, and the preparation effort is large. You must analyze custom code against the S/4HANA simplification list, resolve incompatible items, and test existing processes after conversion. The conversion is one-way, so you need a tested fallback plan before go-live.
A system conversion still uses Activate phases, but Explore changes in character. Fit-to-Standard workshops focus on the simplifications and new capabilities, not on designing every process from scratch.
Selective data transition
A selective data transition moves chosen parts of an existing landscape to S/4HANA. Two typical cases:
- Moving only some company codes, business units, or legal entities, while others stay on the old system.
- Consolidating several ERP systems into one S/4HANA system, or taking the existing design and applying it to a new system with selected historical data.
This scenario often relies on SAP or partner tooling and services for data transformation, because the data is extracted, filtered, and loaded rather than converted in place. It is also the scenario with the most variation, so the project team should write down its exact scope before planning.
Trade-offs: you can combine a clean target with selected history, and you can phase the rollout, but you take on the highest planning and data complexity. Mapping, reconciliation, and cutover rehearsals need extra time.
Comparing the scenarios
| Aspect | New implementation | System conversion | Selective data transition |
|---|---|---|---|
| Starting point | Empty S/4HANA system | Existing ECC system | Existing system(s) plus a new S/4HANA system |
| Process design | Redesigned from best practices | Mostly kept, adjusted for simplifications | Chosen per scope |
| Data approach | Migrate selected master data and open items | Convert all data in place | Extract, transform, and load selected data |
| Custom code | Rebuilt only if needed, often as extensions | Analyzed and adapted | Selected and adapted |
| Main risk | Change management and data migration | Legacy complexity and downtime | Scope definition and data reconciliation |
| Fit-to-Standard emphasis | High | Moderate, on changes and new features | Varies with scope |
How the scenario shapes each phase
The six phases stay the same. The content changes.
- Discover: For a conversion, run readiness checks and a simplification analysis to size the effort. For a new implementation, build the case around process improvement and the target operating model.
- Prepare: Set up the project, governance, and landscape. A conversion needs a sandbox copy of production to rehearse on. A new implementation needs a new system and, for cloud, the tenant provisioning.
- Explore: Fit-to-Standard workshops cover the full scope in a new implementation. In a conversion they cover the delta between the old and new behavior.
- Realize: A new implementation configures and extends in iterations. A conversion adapts custom code, runs technical conversion cycles, and runs regression tests. A selective transition builds and tests the data transformation rules.
- Deploy: Cutover differs most. A conversion has one downtime window for the technical conversion. A new implementation loads data into an empty system. A selective transition may cut over in waves.
- Run: All scenarios start hypercare, but conversions often see issues in legacy custom code, and new implementations see more user adoption questions.
Common mistakes
- Choosing by habit. Teams pick conversion because it feels faster, then find the custom code and data quality work takes longer than a redesign would have.
- Calling a new implementation a "lift and shift". If the team copies old processes into S/4HANA without Fit-to-Standard analysis, the project gets the cost of a new implementation without the simplification.
- Underestimating selective transition scope. Without a written list of entities, data objects, and history to move, scope grows during Realize.
- Skipping rehearsals. All three scenarios need cutover rehearsals. Conversions need timed dress rehearsals of the downtime. Migration scenarios need data reconciliation rehearsals.
- Ignoring deployment model. The scenario and the deployment model (cloud public edition, cloud private edition, or on premise) are separate decisions. Not every scenario is available in every model. For example, SAP Activate roadmaps for the public cloud assume a new implementation, because the public edition is a standard, SaaS-style system and does not allow the in-place conversion of a customized ECC system. Check current SAP documentation for the combination you plan to use.
Choosing a scenario: decision criteria
Use these questions in Discover and confirm them in Prepare.
- How much do you want to change the business processes? A lot suggests new implementation.
- How much of the custom code and the configuration still has value? A lot suggests conversion.
- Do you need all historical data in the new system, or only open items and master data?
- Are you merging systems or moving only part of the business? That suggests selective data transition.
- What downtime and risk can the business accept at go-live?
- Which deployment model is the target, and does it support the scenario?
Record the answers and the decision in the Discover deliverables, so later phases can trace why the scenario was chosen.
Exercise
A company runs a heavily modified ECC system and wants to move only two of its five company codes to S/4HANA, keeping the other three on ECC for now. Which scenario fits best, and how does this change the Deploy phase compared with a system conversion?
Show answer
Selective data transition fits best, because only part of the landscape moves and the data must be extracted, filtered, and loaded. In Deploy, a system conversion has one technical downtime window for the whole system. A selective transition cuts over only the chosen company codes, possibly in waves, and needs data reconciliation rehearsals and a plan for the company codes that stay on ECC.
Exercise
In which scenario do Fit-to-Standard workshops cover the widest scope, and why?
Show answer
In a new implementation. The team starts from SAP best practice content with no inherited design, so the workshops must review the whole process scope. In a conversion they focus mainly on what changes through simplifications and new capabilities.