The six phases at a glance
This chapter gives you the working model of SAP Activate's six phases. It assumes you know what an ERP system is, you are familiar with project phases, deliverables and milestones, and you know how SAP S/4HANA differs from SAP ECC. Later chapters cover each phase in detail. Here you learn how the phases fit together, what each one produces, and where projects commonly go wrong.
The phase model
SAP Activate splits an S/4HANA project into six phases: Discover, Prepare, Explore, Realize, Deploy and Run. Each phase has a purpose, a set of deliverables, and a quality gate that marks its end. The phases are sequential at the level of the roadmap. Inside them, the work is iterative, especially in Explore and Realize.
Two points about this model are easy to miss.
- Discover is optional in many projects. It is about evaluating S/4HANA and building the business case. A customer who has already decided to move starts at Prepare.
- Run is not the end of the project. It is the phase in which the solution is operated and improved, and it starts when the system is live.
What each phase is for
The table gives a one-line purpose and the typical main outputs for each phase.
| Phase | Purpose | Typical main outputs |
|---|---|---|
| Discover | Evaluate the solution and build the case for change | Business case, solution scope outline, trial system experience, roadmap choice |
| Prepare | Mobilize the project | Project plan, governance, team and roles, system landscape, project standards |
| Explore | Validate the solution against business processes | Fit-to-Standard results, backlog of gaps and requirements, scope confirmation |
| Realize | Build and test the solution in iterations | Configured and extended system, data migration objects, tested integrations, end-user training material |
| Deploy | Move to production | Cutover plan, completed cutover, production go-live, user readiness |
| Run | Operate and improve | Hypercare outcome, stable operations, improvement backlog |
Discover
Discover answers the question "should we do this, and what would it look like?" The team looks at what S/4HANA offers, often with a trial or demonstration system, and compares it with business goals. The result is a business case and a first view of scope, so a sponsor can decide whether to fund the project.
Prepare
Prepare answers "how will we run this project?" The team sets up governance, assigns roles, plans the work and prepares the technical landscape. Projects that rush this phase tend to pay for it later through unclear ownership and missing environments.
Explore
Explore answers "what does the business need that standard does not already give us?" Business process owners see the standard solution, usually in a prepared system, and compare it with how they work. This comparison is the Fit-to-Standard analysis. Its output is a list of what fits as delivered, what needs configuration, and what is a real gap.
Realize
Realize answers "can we build and prove it?" The team configures the system in iterations, builds the agreed extensions, prepares data migration, and tests. Testing includes integration tests and user acceptance tests.
Deploy
Deploy answers "are we ready to switch?" The team finishes final preparation, rehearses and runs cutover, which is the controlled transition from the old system to the new one, and then goes live.
Run
Run answers "does it work in daily operation, and how do we improve it?" The first period is hypercare, an intensive support window right after go-live. After that the solution moves into normal operations and continuous improvement.
How the phases connect
The phases are linked by what they hand over to each other. Each output becomes the input of the next phase.
This chain explains why a weak phase causes damage downstream. If Explore produces vague fit-gap results, Realize builds the wrong things or builds too much. If Realize leaves defects open, Deploy inherits them at the worst possible moment.
Iteration inside the phases
Explore and Realize are not single passes. The Realize phase is organized into sprints or iterations, and the team demonstrates working results to the business repeatedly rather than once at the end. This is a common point of confusion for people who expect a waterfall plan. SAP Activate is best described as a phase-based roadmap with agile practices inside the phases.
A practical consequence: the phase boundaries stay firm, but the content inside Explore and Realize changes as the backlog changes. Plan the phase end dates and quality gates firmly, and keep the backlog flexible.
Phase gates and exit criteria
Every phase ends with a quality gate. A gate is a checkpoint where the project confirms that the phase deliverables are complete and of sufficient quality before the next phase begins. Gates are covered in their own chapter. For now, remember two rules.
- A gate is a decision, not a meeting date. The project can pass, pass with conditions, or fail and repeat work.
- The exit criteria should be written before the phase starts, so that nobody negotiates them after the fact.
Phases and workstreams
The phases describe time. Workstreams describe topics. A workstream is a group of related activities that runs through several phases, such as project management, solution adoption, data management, testing, and technical architecture. Each phase contains tasks from many workstreams.
You can picture a roadmap as a grid. The columns are phases and the rows are workstreams. A task such as "define the data migration approach" sits in the data workstream and belongs to a particular phase. When you read a roadmap, ask two questions about any task: which phase is it in, and which workstream owns it?
Common errors
- Treating Run as an afterthought. Teams plan until go-live and then lose the people. Hypercare then fails for lack of staff who know the system.
- Skipping Prepare detail. Missing environments or unclear decision rights block Explore.
- Using Explore to collect a wish list. The purpose is to validate against standard. If workshops start with requirements instead of a demonstration of standard, the project drifts toward heavy customization.
- Treating gates as paperwork. A gate passed without evidence moves the risk into the next phase.
- Assuming one roadmap fits all. The phases are the same in name, but the tasks differ by scenario and deployment model. This is covered in the chapters on scenarios and on tailoring a roadmap.
Reading a roadmap with this model
When you open a roadmap, work through it in this order.
- Identify the phase and its purpose.
- Find the deliverables the phase must produce.
- Find the quality gate and its exit criteria.
- Check which workstream each task belongs to.
- Look at what the next phase takes as input.
This habit lets you place any activity, even an unfamiliar one, in the correct phase.
Exercise
A project team has finished configuring the system and has passed integration testing, but the business has not yet accepted the process design. In which phase did the process design validation belong, and what does this situation say about the earlier phase?
Show answer
Process design validation belongs to Explore, through the Fit-to-Standard workshops. The situation shows that Explore did not produce confirmed fit-gap results with the business before Realize began. The gate at the end of Explore should have caught this, and the team now risks rework in Realize.
Exercise
Name the phase that produces each of these outputs: business case, cutover plan execution, project governance setup, hypercare outcome.
Show answer
Business case: Discover. Cutover plan execution: Deploy. Project governance setup: Prepare. Hypercare outcome: Run.