Sub topic 10
Realize: configuring, extending and testing in iterations
This chapter covers the Realize phase of SAP Activate. It assumes you know the Discover, Prepare and Explore phases, including what a Fit-to-Standard workshop produces. It also assumes you are familiar with iterative delivery ideas such as sprints and backlogs, and with basic SAP configuration terms such as the implementation guide and client.
Purpose of the phase
Realize turns the requirements agreed in Explore into a working, tested system. The project team builds the solution in the development system and verifies it step by step. The business confirms the result through acceptance testing. When the phase ends, the solution is ready to be moved to production in Deploy.
Explore ends with a prioritized backlog of requirements, fit-gap results and a defined scope. Realize consumes that backlog. Anything the Fit-to-Standard analysis classed as "fit" is handled by configuration. Anything classed as a gap goes through a decision: adapt the process, configure differently, or extend.
Baseline and delta
Realize is usually split into two kinds of work.
- Baseline build. The team activates the SAP Best Practices content that matches the agreed scope. This gives a working starting point that follows the standard process. In a cloud deployment this baseline is often already prepared by SAP, and the team confirms it. In other scenarios the team activates the content using the guided configuration tools.
- Delta build. The team then handles the differences between the baseline and what the business needs. These differences come from the Explore backlog. They include extra configuration, organizational structure changes, reports, interfaces, forms and extensions.
Keeping the two apart makes it easy to see how far the solution has moved from standard. Every delta item adds build effort, test effort and upgrade risk, so each one should be justified.
Working in iterations
SAP Activate recommends an agile, iterative approach for Realize. The team works in sprints, which are short, fixed-length cycles of build and review. Each sprint draws items from the backlog, builds them, tests them and shows the result to business representatives.
A typical sprint follows this pattern.
Key points about the sprint rhythm:
- Each sprint ends with a demonstration of working functionality, not a status report. Business users see the real system and can correct misunderstandings early.
- Rejected or incomplete items return to the backlog and are re-prioritized. They are not silently carried forward.
- Retrospectives adjust how the team works, for example how it handles transports or test data.
- The number and length of sprints depend on scope. Large programs often run several sprint cycles per release, with a stabilization period before formal testing.
What gets built
Several workstreams contribute to Realize at the same time. The table lists the main activities and what each produces.
| Area | Activity in Realize | Typical output |
|---|---|---|
| Application | Configure processes, organizational units and master data settings | Configured development system, configuration documentation |
| Extensibility | Build in-app and side-by-side extensions | Custom fields, logic, apps and services |
| Integration | Build and test interfaces to other systems | Working interfaces, integration test results |
| Data | Build and rehearse migration of business data | Migration objects, mapping rules, trial load results |
| Security | Design roles and authorizations | Role concept and tested roles |
| Testing | Plan and run test cycles | Test plans, test cases, defect log, test reports |
| Change management | Prepare training and communication | Training material, end-user readiness plan |
| Technical | Prepare quality and production systems, transport routes | Landscape ready for later phases |
| Cutover | Draft the cutover plan | Cutover plan and runbook draft |
Extending while keeping the core clean
Not every requirement fits standard. SAP Activate guides teams to keep the core standard and put differences into extensions that do not modify SAP code. This keeps upgrades simple. There are two main kinds.
- In-app extensibility. Changes made inside the S/4HANA system through released, supported means. Key users can add custom fields, change forms and set up simple business logic with tools inside the application. Developers can build custom logic using the developer extensibility model, which works only against released interfaces.
- Side-by-side extensibility. Separate applications that run outside the S/4HANA system, usually on SAP Business Technology Platform (SAP BTP). They connect to S/4HANA through released APIs and events. This suits requirements with their own user interface, a different release cycle, or a need to combine data from several systems.
Choose by asking where the logic belongs. If it enhances an existing S/4HANA process and needs close access to its data, use in-app. If it is a separate application or serves multiple systems, use side-by-side.
Testing in Realize
Testing is layered. Each layer widens the scope and involves more people.
- Unit tests. The consultant or developer checks a single configuration or extension. These happen inside the sprint.
- Scenario or string tests. A short chain of steps within one area, such as creating a sales order and checking pricing and delivery.
- Integration tests. End-to-end business processes across modules and connected systems, for example order-to-cash including finance postings and external interfaces. They run in a separate test system with realistic master data.
- User acceptance testing (UAT). Business users run their own scenarios and confirm the system meets requirements. Their sign-off is a key exit criterion.
- Non-functional and regression testing. Performance and security checks, and repeat runs of earlier tests to confirm that later changes did not break existing behavior.
Test cases should trace back to the process steps and backlog items from Explore. That traceability shows that every agreed requirement has been checked. Test automation pays off most for regression tests, since the same scenarios run in every cycle.
Defects need a clear lifecycle: logged, prioritized, fixed, retested and closed. Define severity levels early, and agree which must be fixed before go-live.
Data migration and cutover preparation
Data migration is built and rehearsed during Realize, not left to Deploy. The team defines migration objects and mapping rules, cleanses source data, and runs trial loads. Each trial reveals data quality problems and timing. Business data owners must take part, because only they can decide what is correct. The standard tool for S/4HANA is the SAP S/4HANA migration cockpit. System conversions use different tools and approaches, as covered in the scenarios chapter.
The cutover plan is also drafted here. It lists the tasks, owners, durations and dependencies for the move to production, and later trial runs refine it.
Exit criteria and the quality gate
Realize closes with a quality gate before Deploy. The exact checklist depends on the project, but typical questions are:
- Is all in-scope functionality built and demonstrated?
- Have integration tests and UAT been completed, with open defects accepted or resolved?
- Have the migration trial loads reached an acceptable quality?
- Are roles and authorizations tested?
- Are end users trained, or is the training plan ready?
- Is the cutover plan approved?
- Are production systems prepared?
If the answers are not yes, the project should extend Realize instead of passing the gate with known risk.
Common errors
- Treating Realize as a waterfall build. The team configures for months, then shows results once. Business feedback arrives too late and rework is costly.
- Letting the backlog grow without control. New requests appear after the Explore sign-off. Use a change process that weighs each request against scope, time and the standard-first principle.
- Testing too late. Integration defects found just before go-live are hard to fix. Start integration tests as soon as enough sprints have delivered connected functionality.
- Unrealistic test data. Tests on thin sample data miss real-world problems. Use migrated, representative data where possible.
- Skipping documentation of decisions. Without records of why a gap was solved a certain way, later support and upgrades suffer.
Exercise
During a sprint review, business users reject a custom approval step built as an extension because it does not match what they described. What should happen to the item, and why is this better than waiting until UAT?
Show answer
The item goes back to the prioritized backlog, is re-clarified with the business and is rebuilt in a later sprint. Finding the mismatch in the sprint review costs a small amount of rework. Finding it in UAT, after integration testing and training material have been built around it, causes much more rework and puts the Realize quality gate at risk.
Exercise
A requirement calls for a new self-service app for suppliers, with its own interface, which also needs data from two other systems. Should the team use in-app or side-by-side extensibility, and why?
Show answer
Side-by-side extensibility on SAP BTP. The app has its own user interface, serves external users and combines data from several systems, so it should run outside the S/4HANA core and connect through released APIs and events.