Sub topic 9
Fit-to-Standard Workshops and Fit-Gap Results
Prerequisites
This chapter assumes you know the six SAP Activate phases and the purpose of the Explore phase. It also assumes you know the difference between SAP Best Practices (preconfigured process content) and custom development. You should be comfortable with project terms such as scope, backlog and deliverable.
What Fit-to-Standard Is
Fit-to-Standard is the analysis technique used in the Explore phase. The project team shows the business a working system that already contains SAP Best Practices content. The business then confirms which processes it can adopt as delivered and which need a change.
This reverses the older blueprint approach. In a blueprint project, the team collected requirements first and then built a solution to match them. In Fit-to-Standard, the standard solution comes first. Requirements are judged against it. A requirement that the standard covers is a fit. A requirement the standard does not cover is a gap.
The aim is to keep the core standard. Every gap must be justified, because each one adds build, test and upgrade cost.
Inputs and Preparation
Workshops go badly when they start cold. The Prepare phase and the start of Explore should produce these inputs:
- A fit-to-standard system. For a new implementation this is usually a preconfigured SAP Best Practices system, such as a cloud trial or a starter system. For a system conversion it is often a sandbox copy of the existing system after the conversion.
- A scope list of the in-scope processes, taken from the scope items of the chosen SAP Best Practices package.
- The process documentation for each scope item, including test scripts and process flow diagrams.
- Named business process owners who can decide, not only attend.
- A workshop agenda and a logistics plan, including who records results.
Prepare the fit-gap tool or backlog in advance. Teams often use SAP Cloud ALM, SAP Solution Manager or a backlog tool such as Jira. Whatever the tool, every finding needs an ID, an owner and a status.
Running a Workshop
A typical workshop covers one process area, such as order to cash, for one to three days. The flow below applies to each scope item.
- The facilitator states the scope item and the business outcome it supports.
- A consultant demonstrates the process in the system, using the delivered data and configuration.
- Business participants compare the demonstration with how they work today and with how they want to work.
- The group records each deviation as a finding.
- The group classifies each finding and assigns an owner and a next step.
- The business process owner confirms or rejects the classification.
Run the demonstration in the system, not in slides. Participants react to what they see, and this exposes differences that a written requirement would hide.
Classifying Findings
A finding is not always a plain fit or gap. Teams usually sort findings into a few categories. The names vary by project, but the logic is consistent.
| Result | Meaning | Typical action |
|---|---|---|
| Fit | The standard process meets the need as delivered. | Confirm and document. |
| Configuration | The need is met by a setting that differs from the delivered default. | Add to the configuration backlog. |
| Gap, in-app extension | The need requires a change inside S/4HANA, such as a custom field or logic. | Add to the extension backlog. |
| Gap, side-by-side extension | The need requires a separate application on SAP Business Technology Platform. | Add to the extension backlog with an architecture note. |
| Process change | The business should change how it works to match the standard. | Record for the organizational change workstream. |
| Out of scope | The need is not part of this project. | Record the decision and the approver. |
Before accepting a gap, challenge it. Ask these questions in order:
- Can the business change its process to fit the standard?
- Can configuration deliver the outcome?
- Can a key-user (in-app) extension deliver it?
- Is the need worth a developer or side-by-side extension, given the cost over the system's lifetime?
Most gaps should disappear at the first or second question. A project where most findings end as gaps usually has a facilitation problem, not a product problem.
Recording Results
The output of the workshops is a set of records, not a document. Keep each record small and traceable. A useful fit-gap record contains:
- A unique ID and the scope item it relates to.
- A short description of the requirement and the business reason.
- The classification from the table above.
- The business owner and the decision date.
- An estimate of effort and a priority.
- The target release or iteration in Realize.
The following Python example shows how a team could check an exported fit-gap list for records that are incomplete. It reads a CSV file and prints a summary of the classifications, then reports the records that lack an owner or an estimate.
import csv
import io
from collections import Counter
SAMPLE = """id,scope_item,classification,owner,effort_days
FG-001,Order to cash,Fit,A. Rossi,0
FG-002,Order to cash,Configuration,A. Rossi,2
FG-003,Procure to pay,Gap in-app,,5
FG-004,Procure to pay,Gap side-by-side,K. Mensah,
FG-005,Record to report,Process change,K. Mensah,0
"""
def check(rows):
counts = Counter(r["classification"] for r in rows)
problems = []
for r in rows:
if not r["owner"].strip():
problems.append((r["id"], "missing owner"))
gap = r["classification"].startswith("Gap")
if gap and not r["effort_days"].strip():
problems.append((r["id"], "gap without estimate"))
return counts, problems
rows = list(csv.DictReader(io.StringIO(SAMPLE)))
counts, problems = check(rows)
for name, n in counts.most_common():
print(f"{name}: {n}")
for rec_id, issue in problems:
print(f"{rec_id}: {issue}")Running it prints the count per classification, then FG-003: missing owner and FG-004: gap without estimate. In a real project you would read the file exported from your tracking tool instead of the sample string.
What Fit-to-Standard Delivers
At the end of the workshops, the Explore phase should have produced:
- A confirmed scope, with fit-gap results for each scope item.
- A prioritized backlog of configuration, extension, data and integration items.
- A list of process changes handed to the organizational change workstream.
- Updated estimates, because the real number of gaps is now known.
- Signed-off decisions from business process owners.
These items feed the Explore quality gate and form the starting backlog for Realize.
Variations by Scenario
The approach changes with the implementation scenario.
- New implementation. The workshops walk through the SAP Best Practices scope items in a clean system. Gaps are measured against the standard.
- System conversion. The team compares the existing custom code and processes with the converted system. Simplification items matter here, because some old functions are replaced or removed. Findings include both gaps and required adaptations of custom code.
- Selective data transition. Workshops cover both the target process design and the data to be moved, such as which history to keep.
For public cloud editions, the options for gaps are narrower, because extensions must use released interfaces. The first two questions in the challenge list carry more weight there.
Common Errors
- Treating the workshop as a requirements-gathering session. The business lists wishes, and no one looks at the system. Keep the demonstration central.
- Wrong attendees. If decision makers are absent, findings return later as reversals. Require process owners.
- Recording gaps without a business reason. Without a reason, no one can later judge whether the gap is worth its cost.
- Skipping the process-change category. Teams then build extensions that a change in working habits would have avoided.
- Closing the workshops without estimates. The backlog cannot be planned for Realize.
- Letting gaps grow silently. Track the gap count over time and review each new gap at a change control point.
Exercises
Exercise
A business owner asks for a custom approval step in purchase requisitions during a workshop. The demonstrated standard process has a different release strategy. List the order of questions the team should ask before recording this as a gap.
Show answer
First, ask whether the business can adopt the standard release strategy (process change). Second, ask whether configuring the release strategy meets the need (configuration). Third, ask whether a key-user in-app extension can add the step. Only if all three fail, and the value justifies the lifetime cost, record a developer or side-by-side extension gap, with a business reason, owner and estimate.
Exercise
In the Python example, what would the output look like if FG-005 also had an empty owner, and why does the check for estimates skip it?
Show answer
The output would also include "FG-005: missing owner". The estimate check skips FG-005 because its classification is "Process change", which does not start with "Gap", so an empty effort value is not reported for it.