Prepare: Mobilizing the Project
This chapter covers the second SAP Activate phase. It assumes you know what SAP S/4HANA is, how ERP processes are organized, and basic project management terms such as deliverable, milestone and steering committee. You should also have read the chapters on the phase overview and the Discover phase.
What the Prepare phase is for
Discover ends with a decision: the organization has chosen to adopt S/4HANA and has a rough scope, a business case and a preferred deployment model. Prepare turns that decision into a project that can start working. By the end of the phase, the team should be staffed, the governance should be running, the landscape should exist, and the plan should be detailed enough to guide Explore.
Prepare is short compared with Realize, but its mistakes are expensive. An unclear scope, a missing decision-maker or a late system provision shows up months later as delay, rework or disputes over change requests.
Main activities
Prepare is usually organized around five groups of work.
- Project initiation and planning. The team writes the project charter, the scope statement, and the initial project plan. The plan is based on the SAP Activate roadmap selected for the scenario and deployment model, then tailored to the project.
- Governance and organization. The team sets up the steering committee, the project management office (PMO), and the roles of the project team. Decision rights and escalation paths are written down.
- Team mobilization and enablement. Internal staff, SAP specialists and partner consultants are assigned. Core team members are trained on S/4HANA concepts, on the Activate approach and on the tools they will use.
- System and environment preparation. The team requests the systems it needs. In a cloud model, SAP provisions the tenants. In an on-premise or private cloud model, the customer or hosting partner builds the landscape.
- Initial plans for later phases. Early plans are drafted for testing, data migration, change management and training. They are refined as the project learns more.
Typical deliverables
| Deliverable | Purpose |
|---|---|
| Project charter | States objectives, scope, constraints and success criteria |
| Project plan and schedule | Sequences activities, owners and milestones across the phases |
| Governance model | Defines the steering committee, PMO, roles and escalation |
| Resource plan | Names people and their availability for each workstream |
| Risk and issue log | Records risks with owners and responses |
| Initial landscape | Provides the starter system for Explore |
| Quality plan | Describes the reviews and the quality gate criteria |
| Draft plans for test, data and change | Gives early direction for later workstreams |
Exact deliverable names differ between roadmaps. The roadmap viewer lists the ones that apply to your scenario.
Governance in practice
Governance is the structure that lets the project make and record decisions. A common model has three levels.
- Steering committee. Senior business and IT sponsors. It approves scope, budget and major changes, and it resolves escalations.
- Project management. The project manager and PMO. They run the plan, track risks and report status.
- Workstream leads. They own the work in areas such as data, testing or integration, and they raise issues upward.
Decide in Prepare how scope changes will be handled. A simple rule helps: a change that affects budget, timeline or the standard-first principle goes to the steering committee. Smaller changes are decided by the project manager.
Planning from the roadmap
SAP Activate provides a roadmap with tasks, deliverables and accelerators for each phase. You do not copy it as it is. You select the roadmap that matches your scenario (for example new implementation or system conversion) and deployment model, and then remove, add or reorder tasks.
Two choices affect planning most:
- Deployment model. A cloud tenant is provisioned by SAP and arrives with SAP Best Practices content already active. On-premise and private cloud projects need installation, sizing and configuration work, which the plan must show.
- Scenario. A system conversion needs readiness checks and custom code analysis. A new implementation needs a plan for how to load data from legacy systems.
The diagram shows how the inputs from Discover and the tailoring choices lead to the Prepare outputs.
Preparing the landscape
The landscape is the set of systems the project uses. What you need depends on the deployment model.
- SAP S/4HANA Cloud Public Edition. SAP provisions the tenants. The team needs to confirm the tenant setup, create users and assign roles. The customer cannot change the code of the core, so extension planning focuses on in-app and side-by-side options.
- SAP S/4HANA Cloud Private Edition or on-premise. The team sizes the hardware or hosting, installs the software, and plans the transport route between development, quality and production systems. A starter system with SAP Best Practices content can be activated, which gives the Explore workshops something to demonstrate.
In either case, the Explore phase needs a system the business can see. If the landscape is late, Fit-to-Standard workshops fall back to slides, and the standard process is much harder to judge.
Change management and training start here
Many projects begin change management in Realize or Deploy. That is too late. In Prepare, the team should:
- Identify stakeholder groups and how the change affects each.
- Name change champions in the business.
- Agree on a communication plan with regular messages.
- Plan how end users will be trained and when.
Early planning matters because Explore asks business people to commit time. They only do so when they understand why the project is happening.
Prepare quality gate
The phase ends with a quality gate, a formal review that checks readiness for Explore. Typical checks are:
- Is the scope agreed and documented?
- Are the governance roles filled and the steering committee active?
- Is the plan approved, with owners for the main milestones?
- Is the initial landscape available and accessible?
- Are the key risks recorded with responses?
- Is the team trained well enough to run workshops?
A gate is not a ceremony. If a criterion fails, the project should fix it or decide explicitly to accept the risk. Quality gates are covered in detail in a later chapter.
Common errors
- Treating the roadmap as a fixed plan. The roadmap is a template. A plan without tailoring includes tasks that do not apply and omits ones that do.
- Staffing the project with people who have no time. Business process owners who are assigned part time to a full-time job often miss workshops. State the expected availability in the resource plan and have the sponsor confirm it.
- Skipping team enablement. If consultants and key users do not share an understanding of the standard, Fit-to-Standard turns into a debate about terminology.
- Unclear scope boundaries. Vague phrases such as "finance processes" invite scope creep. List the processes, organizational units and countries that are in scope.
- Late environment readiness. Request systems at the start of Prepare, not at the end. Lead times for hosting and licenses are often longer than expected.
- No decision on the standard-first principle. If the steering committee does not endorse using standard processes, every gap becomes a custom development request later.
A short worked example
A manufacturer has chosen a system conversion to S/4HANA on a private cloud. Discover produced a business case and a target of go-live in 14 months. In Prepare, the team does the following:
- Selects the system conversion roadmap and adds a task for custom code analysis, because the ECC system has about 3,000 custom objects.
- Forms a steering committee with the CFO, the head of operations and the CIO, and sets a monthly meeting.
- Assigns a project manager and five workstream leads, and confirms with each business lead that they have two days per week for the project.
- Asks the hosting partner for sandbox, development and quality systems, with a delivery date four weeks before Explore.
- Drafts a data migration plan that names the legacy data owners.
- Writes a quality plan that defines the exit criteria for the Prepare gate.
At the gate, the steering committee notes that the sandbox is two weeks late. It accepts the delay, records it as a risk, and moves the first Explore workshops to the schedule's second week.
Exercise
A project team is preparing for Explore, but the initial landscape will not be ready for another month. Name two consequences for Fit-to-Standard workshops and one action the team could take at the Prepare quality gate.
Show answer
Without a system, workshops must rely on slides or recorded demos, so business users cannot see standard processes working, and gaps are harder to judge, which raises the risk of wrong fit-gap results. The workshop schedule may also slip. At the gate, the team can either hold the gate until the landscape is available, or conditionally pass it by recording the risk, setting a firm delivery date, and rescheduling the workshops to start after that date. The decision belongs to the steering committee.
Exercise
Why does the Prepare phase include early plans for change management and training, even though end-user training happens much later?
Show answer
Explore requires business people to spend time in workshops and to make decisions about their processes. They commit more readily when they understand the purpose and impact of the project. Early stakeholder analysis, champions and communication plans create that understanding, and they give the later training plan a base to refine.