Sub topic 16
Selecting and Tailoring a Roadmap for Your Project
This chapter assumes you know the six SAP Activate phases (Discover, Prepare, Explore, Realize, Deploy, Run), the main implementation scenarios, and the idea of Fit-to-Standard. It shows how to pick a starting roadmap and adapt it to a real project.
Why a roadmap is a starting point
An SAP Activate roadmap is a structured template. It lists phases, deliverables, tasks, accelerators (ready-made documents, templates and guides) and quality gates. SAP publishes several roadmaps, each built for a combination of deployment model and scenario.
No project uses a roadmap unchanged. A roadmap that is too heavy slows a small cloud project. A roadmap that is too light leaves a large conversion without cutover planning or data-migration controls. Tailoring means removing, adding and adjusting content on purpose, and recording why.
Step 1: Choose the roadmap that matches your situation
Selection depends on three questions.
- Deployment model. Is the target SAP S/4HANA Cloud Public Edition, SAP S/4HANA Cloud Private Edition, or an on-premise installation?
- Scenario. Is it a new implementation, a system conversion, or a selective data transition?
- Scope shape. Is it a single-country, single-wave rollout, or a multi-country program with several waves?
The table shows typical pairings. Exact roadmap names change between SAP releases, so confirm them in the roadmap viewer.
| Situation | Typical starting roadmap | What differs from a plain new implementation |
|---|---|---|
| Greenfield, public cloud | Roadmap for new implementation of the public cloud edition | Scope is limited to the delivered best practices. Extensions use in-app and side-by-side options. SAP updates the system on a fixed schedule. |
| Greenfield, private cloud or on-premise | Roadmap for new implementation with more configuration freedom | More configuration and custom development are possible, so Realize carries more build and test effort. |
| Existing ERP system, keep processes and data | Roadmap for system conversion | Technical readiness checks, custom code adaptation, and downtime-optimized cutover dominate. |
| Existing landscape, move only some entities or history | Roadmap for selective data transition | Data selection, harmonization and migration rules take the most planning effort. |
Pick the closest roadmap, even if it is not a perfect match. Adding a missing activity is easier than building a roadmap from nothing.
Step 2: Read what the roadmap gives you
Before changing anything, review the roadmap in the roadmap viewer. For each phase, note:
- the deliverables the phase is expected to produce,
- the tasks that support each deliverable,
- the accelerators attached to each task,
- the quality gate at the end of the phase.
This review gives you a baseline. Without it you cannot tell later whether a change removed something essential.
Step 3: Tailor the roadmap
Tailoring has four kinds of change.
Remove what does not apply
Delete tasks that your scenario never needs. A public cloud project does not need an on-premise sizing task. A conversion with no new modules may not need a full Fit-to-Standard workshop series for every area.
Add what is missing
Add activities the template does not cover. Common additions are:
- local legal reporting for specific countries,
- integration with a non-SAP system your company relies on,
- extra data-quality cleansing for a poor legacy source,
- change management steps for a large user population.
Resize the effort
The same task can take one day in one project and three weeks in another. Adjust effort by the number of countries, business units, interfaces and users. Larger scope usually means more Explore workshops, more test cycles and a longer hypercare period.
Adjust the delivery rhythm
The roadmap describes an iterative Realize phase, but the number and length of iterations is yours to set. A common pattern is two to four sprints for configuration and extension, then integrated testing. If the project uses waves, repeat Prepare-light, Realize, Deploy and Run for each wave while Explore and design decisions stay consistent across waves.
How scenario and deployment model change the emphasis
The six phases stay the same. What changes is where the effort goes.
| Phase | Public cloud new implementation | System conversion |
|---|---|---|
| Discover | Trial system, fit with standard scope | Readiness analysis, business case for moving a running system |
| Prepare | Tenant provisioning, team onboarding | Sandbox conversion, landscape planning |
| Explore | Fit-to-Standard against delivered processes | Fit-to-Standard focused on simplification items and changed processes |
| Realize | Configuration and key-user extensibility | Custom code remediation, regression testing |
| Deploy | Data migration and cutover to a new tenant | Downtime planning for the conversion, cutover rehearsal |
| Run | Adopt quarterly or half-yearly updates | Stabilize, then adopt new functions at your own pace |
Guardrails: what not to cut
Tailoring can go wrong when teams trim without thinking. Treat these as protected unless you have a documented reason:
- Quality gates. Shorten the paperwork if needed, but keep the decision point. A gate is where sponsors confirm that the next phase may start.
- Fit-to-Standard. Skipping it moves design disputes into Realize, where changes cost more.
- Cutover rehearsals. At least one full rehearsal exposes timing and data problems before go-live.
- Testing layers. Unit, integration and user acceptance testing each catch different faults.
- Hypercare. Removing it saves little and raises the risk of unresolved issues after go-live.
A tailoring workflow
The diagram shows the order of decisions.
Worked example
A manufacturer with plants in three countries runs SAP ECC and wants to move to SAP S/4HANA Private Edition. It wants to keep most processes but clean up old master data.
- Selection. The deployment model is private cloud. The scenario is a system conversion with data cleanup. The team picks the conversion roadmap.
- Review. The baseline lists readiness checks, custom code analysis, and a cutover plan with rehearsals.
- Remove. The team drops the task for creating a new organizational structure, because the structure carries over.
- Add. It adds a master data cleansing track in Prepare and Realize, and a local tax reporting task for the third country.
- Resize. Custom code analysis showed many adapted objects, so the team doubles the regression testing effort.
- Rhythm. It plans two rehearsals and a single go-live weekend, with a hypercare period of six weeks.
- Record. Every change goes into a tailoring log with the reason and the approver.
The log is short and useful. Later, when someone asks why there is no organizational-structure workshop, the answer is written down.
Common mistakes
- Picking by name, not by fit. Choosing a roadmap because it sounds familiar, then discovering it assumes a different deployment model.
- Tailoring without a baseline. Teams delete tasks before reading what they were for.
- Treating the roadmap as a fixed plan. The roadmap is generic. The project plan, with dates, names and effort, is separate.
- Never revisiting the tailoring. If scope grows or a new country joins, review the roadmap again at the next quality gate.
- Ignoring the tools. Teams that keep tailoring only in a slide deck lose traceability. Use the roadmap viewer for the baseline and your project tool, such as SAP Cloud ALM or SAP Solution Manager, to carry the tailored plan.
Checking your result
A tailored roadmap is ready when you can answer yes to each question.
- Does it match the deployment model and scenario?
- Is every removed item justified in the log?
- Does every added item have an owner and a phase?
- Are all six phases and their gates still present?
- Do the sponsor and the project office accept it?
Exercise
A company plans to move an existing on-premise ERP system to SAP S/4HANA Private Edition. It will keep its current processes and all data. A team member suggests skipping the cutover rehearsal and the Fit-to-Standard workshops to save time. Which roadmap is the best starting point, and how would you respond to the suggestion?
Show answer
The best starting point is the system conversion roadmap, because the company keeps its processes and data. Do not skip the cutover rehearsal. Conversion projects depend on a tested downtime plan, and a rehearsal exposes timing and data problems before go-live. Fit-to-Standard can be resized rather than removed. Focus the workshops on simplification items and processes that change in S/4HANA, and record the reduced scope in the tailoring log.
Exercise
List the four kinds of tailoring change and give one example of each for a three-country rollout.
Show answer
Remove: drop tasks that do not apply, such as new organizational structure design when the structure carries over. Add: include local legal reporting for each country. Resize: increase workshop and test effort for the added countries. Adjust rhythm: plan waves per country, or set the number and length of Realize sprints to fit the scope.