Discover: evaluating S/4HANA and building the case
Prerequisites and scope
This chapter assumes you know what an ERP system is and how SAP S/4HANA differs from SAP ECC. It also assumes you are familiar with phases, deliverables and milestones in project management. You should have read the chapters on the six phases at a glance and on the implementation scenarios. This chapter covers only the Discover phase. Prepare, the next phase, has its own chapter.
What the Discover phase is for
Discover is the first of the six SAP Activate phases. It starts before any project exists. The question it answers is not "how do we implement S/4HANA?" but "should we, in what form, and with what expected value?"
A customer in this phase is usually in one of three positions:
- An existing SAP ECC customer weighing a move to S/4HANA.
- A customer on another ERP product evaluating SAP for the first time.
- An existing S/4HANA customer considering a new deployment model, a new line of business, or a move to a newer release.
Because the phase happens before a commitment, it is often lighter than later phases. It can run for a few weeks or several months, depending on how much internal alignment is needed. It also tends to involve more people from the business side and fewer from the delivery side.
Typical activities
Discover work falls into four groups.
- Learn what the product offers. The team looks at the scope of S/4HANA, the available deployment models (SAP S/4HANA Cloud Public Edition, SAP S/4HANA Cloud Private Edition, or on-premise) and the industry and line-of-business functions that apply. SAP trial systems and demonstration environments are common here, so stakeholders can see the solution instead of reading slides.
- Assess the current landscape. The team inventories existing systems, custom code, interfaces, data volumes and business processes. For ECC customers this includes checking how much custom development exists and how much of it will still be needed.
- Choose a direction. The team compares the implementation scenarios (new implementation, system conversion, selective data transition) against business goals, timeline and risk tolerance.
- Build the business case. The team estimates costs, benefits and risks, and secures a decision and a budget for the next phase.
Key deliverables
Discover is lighter on formal deliverables than later phases. The roadmap's content varies by solution and scenario, but the following items appear commonly.
| Deliverable | Purpose |
|---|---|
| Business case and value assessment | States expected benefits, costs and the return that justifies the investment |
| Solution and deployment model recommendation | Records which S/4HANA edition and deployment option fits the customer |
| Scenario selection | Records whether the project is a new implementation, a system conversion or a selective data transition, and why |
| High-level scope and roadmap | Gives a first view of processes, countries, organizational units and timeline |
| Initial risk and assumption list | Captures known risks and the assumptions the estimates rest on |
| Readiness findings | Summarizes what the landscape analysis revealed, such as custom code volume or data quality |
None of these is final. They are inputs that the Prepare phase refines when it plans the project properly.
How Discover connects to the rest of the plan
The scenario choice made here shapes everything afterward. A system conversion, for example, brings technical preparation work such as a simplification check and custom code analysis. A new implementation puts more weight on process design and data migration from legacy systems. The choice also affects which Activate roadmap you pick in the Prepare phase.
Building the business case
A business case in Discover usually has to persuade executives who do not follow technical detail. Three questions drive it.
- Why now? Common drivers are the end of mainstream maintenance for SAP ECC, a need for real-time reporting, process standardization after mergers, or a wish to reduce the cost of running many systems.
- What will it cost? Costs include licenses or subscriptions, implementation services, infrastructure, internal staff time, training, and any custom code remediation.
- What do we get? Benefits can be hard savings, such as retired systems, or softer gains such as faster closing cycles. Soft benefits should still carry a named owner and a way to measure them.
SAP offers value-assessment material and benchmarking approaches to help here, and many customers also use partner or consulting support. Whichever source you use, keep your assumptions visible. A business case that shows its inputs is easier to defend and easier to revisit later.
Common errors in business cases
- Counting only license cost. Implementation, data work and change management often cost more than the software.
- Assuming the whole existing process scope carries over. Fit-to-Standard in the Explore phase often shrinks custom requirements, but the case should not promise this before evidence exists.
- No owner for benefits. Benefits without owners tend not to be tracked after go-live.
- Skipping the landscape assessment. Without it, conversion estimates are guesses.
Choosing the deployment model and scenario
Discover is where the customer picks a direction, so it helps to compare the options in terms of the trade-offs that matter.
| Question | Leans toward new implementation | Leans toward system conversion |
|---|---|---|
| Is the current process design worth keeping? | No, the business wants to redesign | Yes, processes are mostly sound |
| How much custom code exists? | A lot of it is unwanted | Much of it is still needed and can be adapted |
| How much historical data must move? | Only selected master data and open items | All of it, in place |
| How fast must the change be? | Can accept a longer program | Wants minimal process disruption |
These are tendencies, not rules. A selective data transition, for example, suits a customer who wants to keep some existing structures while reshaping others, and it is a separate decision from the two above.
The deployment model also constrains the roadmap. A public cloud deployment follows a more standardized route with limited extension options and a fixed upgrade rhythm. An on-premise or private cloud deployment allows more freedom in configuration and extensions, at the cost of more responsibility for the technical landscape.
Edge cases and gotchas
- Discover is not always visible as a project. Some customers do it informally over months and only open a project at Prepare. Treat the outputs as real deliverables anyway, or the later phases will have nothing to start from.
- A "no" is a valid result. If the business case does not hold, stopping is a success of the phase. It saves the cost of a failed program.
- Existing S/4HANA customers still use Discover. They apply it to new lines of business, new countries or a move to a different edition.
- Trials show standard behavior only. A demonstration system uses preconfigured SAP Best Practices content. It does not show how the customer's own data and exceptions will behave, which is why Explore exists.
- Scenario choice can change. If the landscape assessment in Discover is shallow, the team may discover in Prepare or Explore that the chosen scenario does not fit. A deeper assessment now reduces this risk.
Exit from Discover
Discover ends with a decision, not a go-live. The usual evidence is an approved business case, a chosen deployment model and scenario, and a budget and sponsor for the Prepare phase. SAP Activate uses quality gates at phase boundaries, and a gate here checks that the decision has the right backing. Quality gates have their own chapter later in this tutorial.
Exercise
A company runs SAP ECC with heavy custom code and wants to keep its current processes with minimal disruption. During Discover, the landscape assessment shows most of the custom code is still needed. Which scenario does this lean toward, and which Discover activity produced the evidence?
Show answer
It leans toward a system conversion, because the processes are worth keeping and the custom code is still needed. The evidence came from the landscape assessment, which inventoried custom code, interfaces and data. The team should record the choice and its reasons in the scenario selection deliverable.
Exercise
A sponsor asks you to approve a business case that lists only license costs and a total benefit figure with no owners. Name two problems and a fix for each.
Show answer
First, it counts only license cost, so it omits implementation, data work, training and change management. Fix it by adding those cost categories. Second, the benefits have no owners, so nobody will track them after go-live. Fix it by naming an owner and a measure for each benefit.