Sub topic 8
Explore: validating the solution with the business
This chapter assumes you know the six SAP Activate phases by name, you have read the Prepare chapter, and you understand the difference between SAP Best Practices content and custom development. It covers what the Explore phase is for, how it is run, what it produces, and where it commonly goes wrong. The workshop technique itself, Fit-to-Standard, gets its own chapter. Here it appears only as the main activity inside Explore.
Purpose of the phase
Explore is where the business sees the standard solution and decides what it needs. Prepare mobilized the team, set up governance and provided a first system. Explore uses that system to answer one question: how far does the standard SAP S/4HANA scope cover our processes, and what is left over?
The phase turns an agreed intent ("we will implement finance, procurement and sales") into a validated, prioritized scope. That scope is the input for configuration and extension work in Realize. Mistakes made here are cheap to fix on paper and expensive to fix after build.
Explore has three goals:
- Confirm which standard processes the business will adopt.
- Record every difference between those processes and what the business needs.
- Turn the differences into a managed backlog with owners, priorities and effort estimates.
Inputs from Prepare
Explore depends on what Prepare left behind. Check these before the first workshop:
| Input | Why Explore needs it |
|---|---|
| Project plan, governance and team | Workshop attendees and decision makers must be named and available |
| A system to demonstrate with (for example a starter or trial system preloaded with SAP Best Practices content) | Workshops run against a working system, not slides |
| Initial scope from Discover and Prepare | It defines which process areas are in play |
| Chosen deployment model and implementation scenario | It decides which activities apply. A conversion has system and custom-code analysis work that a new implementation does not. |
| Tooling for the backlog | Fit-gap results must live somewhere traceable |
If the demonstration system is missing or empty, the workshops degrade into requirement-gathering sessions. That is the most common way Explore loses its value.
Main activities
The Explore flow is shown below. The steps overlap in practice, but the order of dependencies holds.
Plan the workshops
Group workshops by business process area, not by organization chart. A typical agenda covers one end-to-end scope item, such as procure-to-pay, per session. Invite process owners who can decide, plus key users who know the details. Send the scope items and the relevant process descriptions in advance so people arrive prepared.
Run the Fit-to-Standard workshops
In each workshop the team demonstrates the standard process in the system and the business reacts to it. The facilitator records, step by step, whether the standard process fits. The next chapter covers how to run these sessions and write down results. What matters here is that the business reviews real system behavior and takes ownership of the outcome.
Classify and record results
Every difference becomes a recorded item. A useful classification separates three kinds of result:
- Fit: the standard process meets the need as delivered.
- Configuration: the need is met by setting options the standard solution already offers.
- Gap: the need requires an extension, an additional solution, or a change to the business process.
The first answer to a gap should be a question: can the business adapt its process to the standard? Extensions cost build effort, test effort and upgrade effort for the life of the system. They are accepted only when the business case justifies them.
Build and prioritize the backlog
All configuration and gap items go into one backlog. A workable item carries the following fields:
id: GAP-014
process_area: Procure-to-pay
scope_item: Purchase order approval
type: gap # fit | configuration | gap
description: Approval required from a second manager above 50,000 EUR
proposed_solution: Standard release strategy with an additional release level
extension_needed: false
priority: high # high | medium | low
effort_estimate_days: 2
owner: P2P workstream lead
status: approvedNotice that this example turned out to be solvable with configuration. Writing proposed_solution early often shows that an apparent gap is not one.
Refine design and plans
The workshop results feed several other artifacts that Explore updates:
- Solution scope and design: the confirmed scope items, organizational structure and key design decisions.
- Data migration approach: which objects migrate, from which sources, and with what cleansing rules. Workshops often reveal data needs that nobody had listed.
- Integration and extension inventory: interfaces to other systems and any extension that survived the gap review.
- Test strategy and authorization concept: both depend on the confirmed processes.
- Organizational change impact: which roles and ways of working change, to prepare training and communication.
- Project plan and estimates: refreshed with real backlog sizes instead of Discover-phase assumptions.
How scenarios change Explore
The activities shift with the implementation scenario:
- New implementation: the workshops cover the full standard scope. Data migration planning is large, because data comes from legacy systems into a clean target.
- System conversion: the business keeps its existing processes, so workshops concentrate on what changes in S/4HANA, such as simplified data models and replaced transactions. Custom code and add-on analysis results feed the backlog.
- Selective data transition: the workshops define which organizational units, time slices or data sets are in scope. This needs more data-focused sessions than the other scenarios.
Deliverables
At the end of Explore you should be able to point to:
- Confirmed solution scope, signed off by business process owners.
- Fit-to-Standard results for every in-scope process.
- A prioritized backlog of configuration and gap items with estimates.
- An updated data migration approach, test strategy and authorization concept.
- A refreshed project plan and budget forecast.
Common errors
- Slides instead of system. Walking through documents lets people agree to things they have not seen. Demonstrate in the system.
- Wrong people in the room. Attendees without decision authority defer every question, and sign-off arrives late or never.
- Gaps accepted without challenge. Each unquestioned gap erodes the standard core. Require a business justification and a standard alternative review.
- Backlog that is only a spreadsheet nobody owns. Without an owner and a status per item, Realize starts with unclear scope.
- Skipping data and integration topics. They surface as late surprises in Deploy. Raise them while workshops are fresh.
- Treating sign-off as a formality. Sign-off means the process owner accepts the scope and its consequences. Unsigned areas should be flagged, not assumed.
Exit criteria and the quality gate
The Explore quality gate checks that the phase delivered what Realize needs. Typical checks include: all in-scope processes were reviewed, results are documented, the backlog is prioritized and estimated, open decisions have owners and dates, and the business has signed off the scope. If the gate finds open issues, the team returns to the relevant workshops rather than carrying uncertainty into Realize. The quality gates chapter covers gates across all phases.
Exercise
In a Fit-to-Standard workshop, a process owner says the standard purchase approval does not match their current three-level approval. Name two things the team should do before logging this as a gap needing an extension.
Show answer
First, check whether configuration, such as release strategy settings, can meet the need, and record it as a configuration item if so. Second, ask whether the business can adapt its process to the standard. Only if both fail, and the business case justifies it, log a gap with an owner, a priority and an effort estimate.
Exercise
Your project is a system conversion. How do the Explore activities differ from a new implementation, and why does data migration planning still matter?
Show answer
Workshops focus on what changes in S/4HANA, such as simplified data models and replaced transactions, and on results from custom code and add-on analysis, rather than on the full standard scope. Data migration planning still matters because existing data must be checked, cleansed and converted, and the workshops often reveal data needs that were not previously listed.