Sub topic 7
What happens next: suspension, extension of time and termination rights
This chapter assumes that you understand breach of contract, express terms, and the basic distinction between force majeure and frustration. The key point is that a force majeure clause gives only the relief stated in its wording. An event does not automatically suspend every obligation or give an automatic right to terminate.
Suspension of obligations
A clause may suspend performance while the force majeure event continues. Suspension temporarily pauses specified obligations. It does not usually cancel the contract.
The clause should identify:
- which obligations are suspended;
- when suspension begins;
- whether the affected party remains liable for other obligations;
- what happens to obligations that became due before the event; and
- whether interest, storage costs, or other charges continue.
Payment obligations need careful attention. A clause may suspend delivery but still require payment for goods already delivered. Some clauses expressly exclude payment obligations from suspension. Others do not. The wording and the commercial context therefore matter.
A party relying on suspension must normally prove that the event satisfies the clause and caused the relevant failure. A general statement that performance became difficult is not enough.
Extension of time
Instead of suspending an obligation, a clause may extend the time for performance. For example, a supplier may receive additional days for delivery when transport restrictions delay shipment.
An extension can operate in different ways:
- the deadline moves by the length of the delay;
- the parties agree a revised date;
- performance is excused until the event ends; or
- the affected party receives a reasonable period after the event to resume performance.
The clause may require notice before the extension is available. It may also require evidence of the delay, an estimate of its duration, and regular updates. A party that misses a notice condition may lose the contractual relief, depending on the construction of the clause.
| Contract wording | Likely effect |
|---|---|
| “The delivery date shall be extended by the period of delay” | The deadline moves by the proven period of force majeure delay. |
| “The affected party may suspend performance” | Performance may pause, but only within the clause’s conditions. |
| “Either party may terminate after 90 days” | Termination becomes available after the stated period and required notice. |
Termination rights
A long-lasting event may give either party a right to terminate. This is usually a contractual termination right, not frustration. The clause may require:
- a specified duration, such as 60 or 90 days;
- written notice;
- notice after the period has elapsed; and
- compliance with any continuing mitigation or reporting duties.
Termination normally ends future performance. It does not necessarily erase rights and liabilities that arose before termination. Accrued payment claims, confidentiality duties, dispute clauses, and provisions intended to survive may remain effective.
A termination right is different from an automatic termination provision. If the clause says a party “may terminate,” notice is generally required. If it says the agreement “shall terminate,” the contract may end automatically, subject to the precise wording and applicable law.
Exercise
Exercise
A contract permits termination if a force majeure event continues for 90 days. The buyer sends a termination notice on day 60 because delivery is already impossible. Is the notice necessarily effective?
Show answer
No. Unless another clause or legal rule applies, the contractual termination right has not yet arisen. The buyer must wait until the stated period has elapsed and follow any notice requirements.