Sub topic 5
Causation, Burden of Proof and Notice Conditions
This chapter assumes you know what a contractual term is, what breach means, and how courts use case law to interpret wording. The focus is a force majeure clause under English law. Such a clause gives relief only when its requirements are satisfied.
Causation: did the event cause the failure?
A force majeure event is not enough by itself. The event must have caused the failure, delay, or prevention described in the clause. This is the causation requirement: the party relying on the clause must connect the event to the contractual non-performance.
The wording matters:
- “Prevents” usually requires performance to be legally or physically impossible, not merely more expensive.
- “Hinders” may cover serious obstacles that leave performance possible but difficult.
- “Delays” focuses on timing. The event must cause the delay claimed.
- “Results in” generally requires a factual link between the event and the loss of performance.
A party cannot rely on force majeure if it would have failed for another reason. For example, a factory closure caused by a listed flood may qualify. A failure caused by the party’s earlier decision not to maintain the factory may not.
Burden of proof
The party invoking the clause normally bears the burden of proof. This means it must establish the facts needed to obtain relief, usually on the balance of probabilities. It should be able to show:
- The event falls within the clause.
- The event affected the relevant obligation.
- The event caused the required type of failure.
- The party complied with notice and other conditions.
- It took any required mitigation steps.
Useful evidence may include government orders, transport records, supplier correspondence, production data, staff records, and contemporaneous decisions. A general statement that performance was “impacted by the crisis” is usually too vague.
The other party may challenge causation by showing that performance was possible, an alternative supplier was available, or the failure began before the event.
Notice conditions
A clause may require written notice within a stated period. It may also require details of the event, affected obligations, expected duration, and steps being taken to reduce its effects.
A condition precedent is a requirement that must be satisfied before a party receives the clause’s protection. If the wording clearly makes notice a condition precedent, late or defective notice can prevent reliance on the clause, even where the event genuinely caused the failure.
Check four points:
| Point | Question |
|---|---|
| Timing | Was notice sent within the required period? |
| Content | Did it identify the event and affected obligations? |
| Delivery | Was it sent to the correct person and by the required method? |
| Consequence | Does the clause state what happens if notice is late? |
Courts generally interpret notice provisions according to ordinary contractual principles. They do not automatically excuse non-compliance because the result seems harsh.
Exercise
A contract covers government restrictions and requires notice within seven days. A supplier sends notice after fourteen days, although the restriction clearly prevented delivery. What is the key issue?
Show answer
Whether the notice term is a condition precedent. If it is, the supplier may lose force majeure protection despite proving causation.