Sub topic 6
Mitigation and Reasonable Endeavours Obligations
Why mitigation matters
A force majeure clause often protects a party only if it takes steps to reduce the event's effect. These steps are called mitigation. Mitigation means limiting the loss or disruption that the event causes.
The duty may require the affected party to find another supplier, use an alternative route, move production, or continue performing any part of the contract that remains possible. The exact duty depends on the clause.
Mitigation is different from the general common law rule on damages. A party claiming damages must usually take reasonable steps to avoid unnecessary loss after a breach. A force majeure clause may impose a separate contractual duty before or during the failure. Breaching that duty can prevent the party from relying on the clause.
Reasonable endeavours
A clause may say that the affected party must use “reasonable endeavours” to overcome or reduce the event. This is an objective standard. The question is what a reasonable party in that position would have done, considering the contract and the surrounding circumstances.
Relevant factors can include:
- the cost of the proposed step;
- how likely the step is to work;
- how quickly it can be taken;
- whether it creates serious safety or legal risks;
- the affected party's contractual and commercial interests; and
- whether the step changes the obligation into something substantially different.
Reasonable endeavours do not normally require a party to accept unlimited expense or abandon its own commercial interests. They also do not permit a party to do nothing merely because performance has become inconvenient.
“Best endeavours” is usually more demanding. It may require significant expense or commercial sacrifice, although it is not an absolute guarantee of success. “All reasonable endeavours” falls between the two in some cases, but its meaning still depends on the wording and context.
A structured assessment
| Question | Evidence to examine |
|---|---|
| What step could have reduced the effect? | Alternative suppliers, routes, sites, or methods |
| Was the step reasonably available? | Cost, timing, capacity, legality, and safety |
| Did the party investigate it promptly? | Emails, quotations, search records, and decision logs |
| Did the step preserve the original bargain? | Whether performance remained substantially the same |
The obligation may be limited by the event itself. A party cannot be required to take an unlawful step, and it need not guarantee that mitigation will succeed. However, it should normally investigate realistic options and act promptly.
Worked analysis
Assume a contract excuses delay caused by an epidemic if the affected party uses reasonable endeavours to continue delivery. A factory closes, but a second factory can produce the goods within three weeks at a 20% higher cost.
The affected party should investigate the second factory and compare the cost, capacity, quality, and delivery time. Refusing the option solely because it is more expensive may breach the clause. The result could differ if using the factory would require a large, unrecoverable loss or would produce goods that do not meet the contract.
Exercise
A supplier is delayed by a flood. The buyer can obtain replacement goods at twice the contract price. Must the supplier always buy them?
Show answer
No. The supplier must assess the option under the clause. A large additional cost may make it unreasonable, but the supplier should investigate promptly, consider other options, and record its reasons.