Force Majeure Versus Frustration: Which Applies and When
The starting point
This chapter assumes you understand basic contract terms, breach, damages, and the difference between express and implied terms. It focuses on English law.
A force majeure clause is an express contractual term. It gives a party relief when a specified event prevents or delays performance. Its effect depends on the clause's exact wording.
Frustration is a common law doctrine. It may end a contract when a later event makes performance impossible, illegal, or radically different from what the parties agreed. English law has no general rule that automatically excuses performance merely because an exceptional event occurs.
| Question | Force majeure | Frustration |
|---|---|---|
| Source | The contract | Common law |
| Main test | Does the event satisfy the clause? | Has performance become radically different? |
| Effect | Whatever the clause provides | Automatic discharge |
| Proof focus | Wording, causation, notice and mitigation | Impossibility, illegality or radical change |
| Financial rules | Contract terms and ordinary remedies | Law Reform (Frustrated Contracts) Act 1943 |
Apply the contract first
When disruption occurs, read the contract before relying on frustration. Look for:
- A force majeure definition listing events such as war, epidemic, government action or supply failure.
- A catch-all phrase, such as “any event beyond the reasonable control” of the affected party.
- A requirement that the event “prevents,” “delays” or “ materially affects” performance.
- Notice deadlines and information requirements.
- Duties to mitigate the effect or use reasonable endeavours.
- Relief such as suspension, an extension of time or termination after a stated period.
A party cannot rely on a general idea of force majeure if the contract contains no applicable term. It must show that the event falls within the clause and caused the relevant failure. A rise in cost may be insufficient where the clause requires performance to be prevented.
When frustration becomes relevant
If no force majeure clause applies, ask whether the contract allocated the risk in another way. Express terms may show that the parties accepted the possibility of delay, price changes or government restrictions. That allocation usually makes frustration unavailable.
If the risk was not allocated, ask whether the supervening event produces a radical change in the obligation. The event must do more than make performance inconvenient, slower or less profitable.
Typical examples include:
- A change in law makes the promised performance illegal.
- The subject matter needed for performance is destroyed.
- The event removes the contract's central purpose, such as the cancellation of a specific event for which premises were hired.
Frustration is narrow. It does not normally apply where the event was foreseeable, the party caused the problem, or performance remains possible at substantially greater expense.
A structured analysis
Use this sequence:
- Identify the event and the obligation affected.
- Read the force majeure clause and test its wording.
- Check causation, notice and mitigation requirements.
- Identify the relief the clause gives.
- If the clause fails, check other risk-allocation terms.
- Apply the narrow frustration test.
- If frustration applies, assess the financial consequences under the 1943 Act.
Exercise
A government order temporarily closes a venue. The contract covers government restrictions, requires prompt notice, and permits suspension. The venue owner gives notice two days late. What should you analyse first?
Show answer
Analyse the force majeure clause first. Determine whether the notice deadline is a condition of relief, whether the delay caused prejudice, and what remedy follows. Frustration is a later question only if the clause does not resolve the disruption.