Sub topic 3
Anatomy of a Force Majeure Clause
This chapter assumes you understand express contract terms, breach, damages, and basic case citations. It focuses on how to read a force majeure clause under English law.
What the clause does
English common law has no general doctrine called force majeure. A party can rely on force majeure only if the contract contains a suitable clause. The clause allocates the risk of specified disruptive events and states what relief follows.
A typical clause answers five questions:
| Question | Function |
|---|---|
| What event qualifies? | Defines the relevant disruption |
| What must the event cause? | Links the event to non-performance |
| What must the affected party do? | Sets notice and mitigation duties |
| What relief is available? | Provides suspension or an extension |
| When can the contract end? | Creates a termination right |
The court interprets the wording using ordinary principles of contractual construction. It considers the words used, the contract as a whole, and the commercial context. It does not rewrite an unclear clause simply because performance has become difficult.
Events and catch-all wording
A clause may list events such as fire, flood, war, epidemic, strikes, or government action. It may then add general words such as “any event beyond the reasonable control” of the affected party.
The listed events help explain the scope of the general wording. The general phrase does not automatically cover every event that causes loss. For example, a rise in operating costs may not be an event beyond reasonable control in the required sense, especially if the clause also requires impossibility or prevention.
The clause should therefore be read as a complete sequence:
"Force Majeure Event" means any event or circumstance beyond the reasonable control of the affected party, including fire, flood, earthquake, war, act of terrorism, epidemic, or act of government, which prevents that party from performing its obligations under this Agreement.
A party affected by a Force Majeure Event shall (a) give written notice to the other party within 7 days of becoming aware of it, describing the event and its expected duration; (b) use reasonable endeavours to mitigate its effect; and (c) resume performance as soon as reasonably practicable.
While the Force Majeure Event continues, the affected party's obligations (other than payment obligations already due) are suspended and it is not liable for failure or delay in performance. If the event continues for more than 90 days, either party may terminate this Agreement by written notice.Causation, notice, and mitigation
The event usually must cause the contractual failure. A party cannot rely on a qualifying event if it would have failed anyway. “Prevents” is stronger than “delays” or “makes more expensive.” “Hinders” or “impedes” may create a broader obligation, but the exact wording controls.
The affected party normally bears the burden of showing:
- the event falls within the clause;
- the event caused the failure or delay;
- the required notice was given; and
- any mitigation or reasonable-endeavours duty was met.
Notice conditions matter. A clause may require notice within a fixed period, details of the event, and an estimate of its duration. Missing a condition may remove the right to relief, depending on the clause’s wording and the court’s construction.
Consequences
Relief may include suspension of duties, extra time, exemption from damages, or termination after a stated period. Payment obligations already due are often excluded from suspension. A party should also check whether the clause preserves other rights, such as termination for prolonged delay.
Exercise
A contract covers government action that “prevents” performance. A new regulation makes performance 30% more expensive but still legally possible. Does the clause automatically apply?
Show answer
No. The regulation may be government action, but the party must also show that it prevented performance. A mere increase in cost normally does not satisfy that causal requirement.