Sub topic 16
Putting it together: a step-by-step method for a disrupted contract
This chapter assumes that you understand contract terms, breach, damages, and basic case and statute citations. It uses English contract law. The central method is simple: read the contract first, then test frustration, then calculate the consequences.
Start with the contract
English law normally requires strict performance of contractual promises. A party cannot usually avoid liability because performance has become difficult or expensive. A force majeure clause changes that position only if the contract contains one and the event falls within its wording.
Record the governing law, the relevant obligation, and the event that caused the disruption. Then ask these questions in order:
- Does the contract contain a force majeure clause or another risk-allocation term?
- Does the event fall within the clause?
- Did the event cause the required failure or delay?
- Were notice and mitigation requirements satisfied?
- What remedy does the clause provide?
- If the clause does not apply, has the contract been frustrated?
Test a force majeure clause
Interpret the clause using ordinary principles of contractual construction. Consider the words used, the contract as a whole, and the commercial context known when the parties contracted.
Separate the clause into its working parts:
| Part of clause | Question to ask |
|---|---|
| Event definition | Is the event listed, covered by general wording, or excluded? |
| Causation | Did the event prevent, hinder, or merely make performance more expensive? |
| Notice | Was notice given in the required form and time? |
| Mitigation | Did the affected party take reasonable steps to reduce the effect? |
| Relief | Does the clause suspend duties, extend time, excuse liability, or permit termination? |
A listed event is not enough by itself. A party usually must prove that the event produced the contractual failure. A notice condition may be especially important if the clause makes timely notice a condition of relief. Check the precise language rather than assuming that late notice has no effect.
Test frustration only when necessary
Frustration is a narrow common law doctrine. It applies when a supervening event, without the affected party’s fault, makes performance impossible, illegal, or radically different from what the parties agreed.
Ask whether the contract or force majeure clause already allocates the risk. Frustration normally cannot be used to rewrite that allocation. It also does not apply merely because performance is less profitable, more burdensome, or more costly. Foreseeable events and self-induced problems usually defeat the argument.
If frustration is established, the contract ends automatically from the frustrating event. Under the Law Reform (Frustrated Contracts) Act 1943, money paid may generally be recovered, while money due ceases to be payable. The court may allow a party to retain or recover expenses, and may account for a valuable benefit received.
Apply the method to evidence
Collect the contract, amendments, notices, correspondence, delivery records, government orders, and mitigation evidence. Build a timeline. Then state a conclusion that addresses both possible arguments: why the clause applies or fails, and why frustration does or does not follow.
Exercise
A supplier cannot deliver because a port closure increases its transport costs by 80%. The contract has no force majeure clause. Is the contract frustrated?
Show answer
Probably not. A cost increase alone normally makes performance more burdensome, not radically different or impossible. The supplier must perform or face the ordinary contractual consequences.