Case Studies: Pandemics, War and Sanctions, and Supply Disruption
This chapter assumes that you understand breach, contractual terms, and the basic distinction between force majeure and frustration. The examples use English contract law. Always begin with the wording of the particular contract.
A pandemic and a cancelled event
A company agrees to provide catering for a festival. The contract contains a force majeure clause covering “epidemic, pandemic, government restriction, or any event beyond the parties’ reasonable control.” The clause excuses delay or non-performance caused by such an event, provided that the affected party gives notice and takes reasonable steps to reduce its effects.
A government order prohibits large gatherings. The caterer cannot lawfully provide the service. The prohibition fits the listed event and directly causes the failure. If the caterer gives the required notice, it will probably receive the contractual relief.
The result depends on the clause. It might suspend performance, extend time, or allow either party to terminate after a specified period. It does not automatically cancel every connected obligation. For example, an obligation to return equipment may remain possible.
If the contract contains no applicable clause, frustration might be considered. The government order could make performance illegal for the relevant date. However, a temporary restriction does not necessarily frustrate a long-term contract if performance can resume without changing its fundamental nature.
War, sanctions, and blocked performance
Suppose a seller must deliver machinery to a buyer in a country affected by sanctions. Exporting the machinery becomes unlawful without a licence. A force majeure clause covering “war, sanctions, embargoes, and acts of government” may protect the seller, but only if the sanctions caused the failure in the way the clause requires.
The seller may need to show that it applied for a licence, explored lawful routes, and notified the buyer. A clause that excuses performance only when it is “prevented” may require more than proof that delivery became expensive or inconvenient. A clause referring to performance being “delayed, hindered, or rendered uneconomic” may provide wider protection.
Frustration is less likely where the contract already allocates the risk of sanctions. It may also fail if lawful alternative performance remains available, even if that alternative is substantially more expensive.
Supply disruption
A manufacturer promises to deliver 10,000 units. Its usual supplier suffers a factory fire. The manufacturer cannot obtain the required parts at the contract price, but another supplier can provide them at a higher price.
This is usually not frustration. Increased expense and inconvenience do not normally create a radical difference in performance. A force majeure clause may still apply if it covers supplier failure, fire, or shortages and does not require the event to make performance impossible.
| Event | Key question | Likely issue |
|---|---|---|
| Pandemic restriction | Did the restriction prevent the promised performance? | Clause wording, notice, and duration |
| Sanctions | Was performance unlawful, and were lawful alternatives attempted? | Causation and mitigation |
| Supplier failure | Was performance impossible or merely more expensive? | Risk allocation and cost |
A structured comparison
The same facts can produce different outcomes under different drafting. A pandemic may trigger suspension under one clause, but leave a party in breach under another. A court interprets the words used, the contract as a whole, and the commercial context. It does not rewrite the bargain because performance has become difficult.
Exercise
A supplier’s only overseas factory closes during a government lockdown. The contract covers government restrictions but requires the event to “prevent” delivery. Another supplier could deliver in six months at double the price. What should be analysed first?
Show answer
Analyse the clause’s wording, whether the lockdown prevented this delivery rather than merely making it costly, and whether the supplier gave notice and pursued reasonable alternatives. If the clause does not apply, consider whether the delay creates a radical change or only increased cost before raising frustration.