Sub topic 9
The Test: Radical Difference, Not Merely Harder or Costlier Performance
This chapter assumes you understand express and implied terms, breach, damages, and basic case citation. It focuses on English law and the common law doctrine of frustration. A force majeure clause is considered first because its wording may allocate the risk before frustration is relevant.
The basic test
Frustration applies when a supervening event makes performance:
- impossible;
- illegal; or
- radically different from the performance promised.
The event must occur after the contract was made and without the fault of either party. The question is not whether performance has become inconvenient or expensive. The question is whether the obligation has changed into something fundamentally different.
In Davis Contractors Ltd v Fareham Urban District Council [1956], a building contract took much longer and cost more because of labour and material shortages. The House of Lords held that the contract was not frustrated. The work remained the same work. It had become more burdensome, but not radically different.
| Situation | Likely result |
|---|---|
| Performance is prohibited by a new law | Possible frustration through illegality |
| The required subject matter is destroyed | Possible frustration through impossibility |
| Performance costs substantially more | Usually no frustration |
| The event removes the contract's central purpose | Possible frustration of purpose |
Impossibility, illegality, and purpose
Impossibility
A contract may be frustrated if the thing essential to performance no longer exists. For example, a contract to hire a particular hall may be frustrated if the hall burns down before the event.
Temporary impossibility can also qualify, but only if the delay destroys the contract's commercial purpose or leaves too little time for meaningful performance. A short interruption will not automatically end a long-term agreement.
Illegality
A later statute, court order, or government restriction may make performance unlawful. A party cannot normally be required to perform an illegal obligation. The legal prohibition must affect the contractual performance itself, not merely make it less profitable.
Frustration of purpose
Performance may remain physically possible but cease to provide the agreed foundation of the bargain. In Krell v Henry [1903], a room was hired to watch a royal procession. The procession was cancelled, so the room hire was frustrated even though the room still existed.
The purpose must be objectively central to the contract. A private disappointment or a weaker commercial benefit is insufficient.
Limits on the doctrine
Ask these questions before concluding that frustration applies:
- Did the contract expressly allocate the risk through a force majeure clause, cancellation term, or other provision?
- Was the event reasonably foreseeable when the parties contracted?
- Did the party claiming frustration cause or contribute to the event?
- Has performance become radically different, rather than merely more difficult or costly?
- Would applying frustration rewrite the parties' bargain?
A party cannot usually rely on frustration after choosing to enter a contract despite a known risk. Frustration is also unavailable where the alleged impossibility results from that party's own conduct.
The distinction can be shown as follows:
Exercise
A supplier's costs double after an unexpected shortage, but the supplier can still deliver the same goods. Is the contract likely frustrated?
Show answer
No. The performance is more expensive, but it has not become impossible, illegal, or radically different. Check the contract for a price-adjustment or force majeure clause instead.