Sub topic 11
Limits on Frustration: Risk, Choice and Cost
Assume you know the basic elements of a contract, the difference between express and implied terms, and the meaning of breach and damages. This chapter focuses on when frustration is unavailable, even though performance has become difficult.
Frustration is a narrow doctrine. It does not protect a party from every bad commercial outcome. The event must make performance impossible, illegal, or radically different from what the parties agreed. Several limits prevent parties from using frustration simply to escape an unprofitable bargain.
Foreseeability and assumed risk
Foreseeability is relevant, but it is not an automatic rule that a foreseeable event can never frustrate a contract. The deeper question is whether the contract, properly interpreted, placed the risk of that event on one party.
If the parties could reasonably have considered an event and allocated its consequences, a court is less likely to intervene. A detailed force majeure clause is strong evidence of that allocation. The clause may provide suspension or termination rights, or it may deliberately exclude relief.
The absence of a force majeure clause does not automatically mean that frustration applies. The court still asks whether the event has produced a radical change in the obligation.
Express terms and contractual risk allocation
A party cannot normally rely on frustration to obtain a result that the contract already addresses. For example, a contract might require delivery despite specified transport problems, allow extra time for a government restriction, or permit termination after a defined period.
The wording matters. A force majeure clause may cover an event but require proof that it actually caused the failure, timely notice, and reasonable mitigation. If those conditions are not met, the party may lose the contractual relief. It does not automatically follow that frustration rescues the party.
An exclusion or limitation clause may also allocate the risk. Courts interpret such terms using ordinary principles of construction. They do not rewrite a bad bargain merely because the result is harsh.
Self-induced frustration
Frustration must result from an event for which the claiming party is not responsible. A party cannot create the frustrating situation through its own decision, breach, or voluntary act and then rely on it.
In The Eugenia, a shipowner’s decision to send a vessel through a route that became blocked did not support frustration. The owner had chosen the relevant course of action despite the known risks.
Self-induced frustration can involve more than deliberate misconduct. Choosing one available method of performance, then finding that method impossible, may not suffice if reasonable alternatives remained available.
Mere cost increases
A contract is not frustrated merely because performance has become more expensive, inconvenient, or less profitable. Commercial hardship is different from a radical change in the obligation.
| Situation | Likely result |
|---|---|
| Performance costs more but remains essentially the same | No frustration |
| Performance becomes illegal | Possible frustration |
| The agreed subject matter no longer exists | Possible frustration |
| The contract’s purpose is completely defeated | Possible frustration |
In Davis Contractors v Fareham UDC, unexpected delay and increased expense did not frustrate a building contract. The work remained the same kind of work, so the contractor bore the commercial risk.
Exercise
A supplier must deliver goods at a fixed price. Transport costs triple after an unexpected regional shortage, but delivery remains legally and physically possible. Is the contract frustrated?
Show answer
Usually no. The obligation remains delivery of the same goods, and the higher cost is commercial hardship rather than a radical change.