Sub topic 4
Trims, Labels and Packaging
Assume you know basic garment construction, can calculate percentages, and have seen a style’s tech pack. This chapter focuses on the non-fabric materials that make a garment complete and saleable.
What belongs in this part of the BOM?
A bill of materials (BOM) lists every material required for one garment. Trims are components attached to or used in constructing the garment. Labels identify the product and provide information. Packaging protects the product and prepares it for shipment or sale.
Typical items include:
| Category | Examples | Common unit |
|---|---|---|
| Trims | Zippers, buttons, snaps, elastic, drawcords | piece, metre |
| Labels | Main label, size label, care label, fibre-content label | piece |
| Packaging | Hangtag, polybag, carton, tissue, sticker | piece, carton |
| Support materials | Interfacing, thread, seam tape | metre, cone, piece |
The BOM should describe each item precisely. “Button” is not enough. Record the diameter, material, finish, colour, supplier reference, and placement. A matte black 18-line polyester button may have a different price and appearance from a glossy metal button.
Trims and construction requirements
Start with the tech pack and construction details. Count the components required by the design:
- A shirt may need seven buttons, one spare button, sewing thread, and fusible interfacing.
- A trouser may need one zipper, one hook and bar, four pocket buttons, and waistband fusing.
- A hoodie may need a drawcord, two eyelets, two cord ends, and rib fabric.
- A lined jacket may need sleeve lining, shoulder pads, labels, and several types of interlining.
Separate the consumption per garment from the purchase unit. A garment might use 1.2 metres of thread, but the factory buys thread by the cone. The cost sheet should convert the cone price into a usable unit cost.
Some trims also affect production time. A metal snap may cost more to apply than a sewn button. A complicated cord end may require a separate operation. Include that effect in the cut-make-trim (CMT) discussion, rather than hiding it inside the trim price.
Labels and packaging
Labels must match the market and the product. A label set can include:
- Brand or main label
- Size label
- Care and fibre-content label
- Country-of-origin label
- Compliance or safety label, where required
Check whether one label combines several requirements. Combining labels can reduce cost, but it may make the label crowded or difficult to read.
Packaging should be specified at the level used in production. Record whether a polybag is individual or shared by several garments, whether it has a suffocation warning, and how many garments fit in a carton. Carton cost is often allocated across its pack quantity.
Costing quantities and allowances
Use the actual required quantity, then add a justified allowance. For example, a style requiring eight buttons may need eight buttons in production and a small percentage for defects or loss. A spare button sewn into the garment may be a separate required quantity, not wastage.
For a trim line, calculate:
gross quantity = required quantity × (1 + allowance)
line cost = gross quantity × unit priceSuppose a jacket needs five buttons per garment. The supplier sells them for $0.18 each, and the allowance is 3%:
required_buttons = 5
allowance = 0.03
unit_price = 0.18
gross_buttons = required_buttons * (1 + allowance)
line_cost = gross_buttons * unit_price
print(f"Buttons to buy per garment: {gross_buttons:.2f}")
print(f"Button cost per garment: ${line_cost:.2f}")The production order may still be rounded to whole cartons or supplier minimums. Keep the per-garment calculation separate from the purchase-order quantity so the costing remains understandable.
Common errors
A BOM becomes unreliable when it:
- Omits spare buttons, labels, or packaging components.
- Uses a sample quantity for a graded size range.
- Confuses a supplier pack price with a per-piece price.
- Lists a trim without colour, finish, size, or supplier reference.
- Adds the same allowance twice, once in the BOM and again in the supplier quote.
- Ignores minimum order quantities (MOQs), leaving unused stock unpriced.
- Changes a trim in the sample without updating the BOM revision.
Exercise
A sweatshirt uses two drawcord ends at $0.12 each. The allowance is 5%. What is the drawcord-end cost per garment before rounding?
Show answer
Gross quantity is 2 × 1.05 = 2.10 pieces. Cost is 2.10 × $0.12 = $0.252, or $0.25 when rounded to cents.