Revisions and Change Control in a Garment BOM
Assume you know basic garment construction, spreadsheet arithmetic, and the relationship between a style, tech pack, and sample. This chapter focuses on controlling changes after a BOM has been created.
A bill of materials (BOM) is a controlled list of everything needed to make a style. A revision is a recorded version of that list. Change control is the process of proposing, checking, approving, and applying a change without losing the earlier record.
Why BOM revisions matter
A small material change can affect more than the purchase order. Changing a fabric width can alter consumption. Replacing a button can change unit cost, appearance, testing requirements, and supplier lead time. Adding a care label can affect both the BOM and the tech pack.
Without revisions, different teams may use different assumptions:
- Product development may approve a new zipper.
- The factory may still use the old zipper price.
- Purchasing may order the previous item.
- Finance may calculate margin from an outdated cost sheet.
A revision gives every team the same reference point. It should identify what changed, why it changed, who approved it, and when it becomes effective.
What a controlled revision contains
Use a revision code such as BOM-STYLE123-R03. The record should include:
- Style number and product description
- Revision code and date
- Status, such as draft, approved, or superseded
- Changed BOM lines
- Old and new values
- Reason for the change
- Expected cost impact
- Affected sizes, colourways, or production orders
- Approver and effective date
- Links to the related tech pack, sample comment, and supplier quote
Do not overwrite an approved BOM. Copy it into a new revision, make the change there, and preserve the previous version as superseded.
| BOM line | R02 value | R03 value | Reason | Cost effect |
|---|---|---|---|---|
| Main fabric | Cotton twill, $6.00/m | Cotton twill, $6.20/m | Supplier price update | +$0.29 |
| Zipper | Metal, $0.40 | Recycled nylon, $0.48 | Approved sustainability change | +$0.08 |
| Hangtag | 1 per garment | 1 per garment | No change | $0.00 |
A practical change-control workflow
Use this sequence for every material change:
First, describe the requested change precisely. “Use better buttons” is not enough. State the item code, material, size, finish, supplier, and quantity.
Next, check dependencies. A new fabric may require a different needle, seam allowance, wash test, or care instruction. A size-specific change may affect only one grade rule rather than the entire style.
Then calculate the difference. Compare the old and new quantity, unit price, and extended line cost. Recalculate CMT, freight, duty, and margin when the change affects those values.
Approval should happen before the new revision is used for purchasing or production. The released revision needs an effective date and a clear rule, such as “applies to purchase orders issued from 15 March.”
Common errors
A common error is applying a change globally when it affects only one colourway. Another is updating the BOM but not the tech pack, purchase order, or cost sheet. Teams also confuse markup with margin when judging whether a revision is affordable.
For each revision, compare:
- Material cost per garment
- CMT or labour effect
- Freight, duty, and overhead effect
- Wholesale and retail margin
- Quality, compliance, and delivery risk
A cheaper component is not automatically a saving if it causes defects, rework, returns, or delayed delivery. Record those risks beside the numerical cost impact.
Exercise
Exercise
The original BOM uses 1.40 m of fabric at $6.00 per metre. A revised fabric costs $6.20 per metre and requires 1.45 m per garment. What is the material-cost increase before wastage?
Show answer
Original cost = 1.40 × $6.00 = $8.40. Revised cost = 1.45 × $6.20 = $8.99. The increase is $0.59 per garment. Record it in a new revision and recalculate any downstream costs.