Turning variances into risks and issues
A variance is a number. It says the project is off plan, but not why, and not what will happen next. This chapter shows how to turn a variance into something you can act on: a risk, an issue, or both. It also covers how to keep a register that stays useful.
This chapter assumes you can compute schedule variance (SV) and cost variance (CV), and that you know what a baseline is. If you need a refresher, review the chapters on baselines and variance analysis first.
Why a variance is not yet a risk or an issue
A variance is evidence. Risks and issues are the project's responses to that evidence.
- A risk is an uncertain event that, if it happens, affects an objective. It has a probability and an impact. It has not happened yet.
- An issue is something that has already happened or is certain to happen, and it needs management now. It has no probability, only an impact and an owner.
A variance can point in either direction:
- A variance can be the symptom of an issue. SV of -10,000 because a vendor delivered two weeks late is an event that already occurred.
- A variance can be the trigger for a risk. A CPI of 0.89 that has dropped for three periods suggests the budget may be exhausted before the work is done. That outcome has not happened, so it is a risk.
- A variance can be noise. A small, one-period dip caused by invoice timing may need no entry at all.
The skill in this chapter is classifying the variance correctly and recording it in the right place.
From variance to register entry
Use a short, repeatable sequence each time a variance crosses your threshold.
- Confirm the number. Check that the data is right. A bad percent-complete figure or a late timesheet produces false variances.
- Find the cause. Ask which work package drives the variance. Drill down the work breakdown structure (WBS) until you reach the task or the cost account that moved.
- Classify it. Decide whether the cause is an event that has occurred (issue), a possible future event (risk), or a measurement artifact (no entry).
- Record it. Write an entry with an owner, a due date, and a link back to the variance.
- Decide the response. Hand the entry to the corrective action process.
Notice the link from issue back to risk. One event often creates follow-on uncertainty. A late delivery (issue) can raise the chance that testing is squeezed (risk).
Setting thresholds
You cannot investigate every variance. A threshold decides which ones get attention. Common forms are:
- Percentage bands. For example, green within 5% of plan, amber from 5% to 10%, red above 10%.
- Index bands. For example, a CPI or SPI between 0.95 and 1.05 is green, between 0.90 and 0.95 is amber, and below 0.90 is red.
- Trend rules. For example, an index that declines for three periods in a row is amber even if each value is still inside the band.
- Absolute limits. For example, any variance above a fixed sum, or any slip on a critical-path task.
Agree on thresholds in the plan, before the first variance appears. Thresholds set after the fact tend to match whatever number you already have.
A table of one possible scheme:
| Status | CPI or SPI | Trend rule | Required action |
|---|---|---|---|
| Green | 0.95 to 1.05 | Stable | Report only |
| Amber | 0.90 to 0.95 | Falling for 3 periods | Find cause, log a risk if the cause is uncertain |
| Red | Below 0.90 | Any | Log an issue or risk, assign an owner, propose a corrective action |
A worked example
Take the project from the earned value chapter: BAC 100,000, PV 50,000, EV 40,000, AC 45,000. The code below computes the metrics and applies the threshold scheme above to draft register candidates.
def evm(bac, pv, ev, ac):
cpi = ev / ac
spi = ev / pv
return {
"CV": ev - ac,
"SV": ev - pv,
"CPI": round(cpi, 2),
"SPI": round(spi, 2),
}
def rag(index):
if index >= 0.95:
return "green"
if index >= 0.90:
return "amber"
return "red"
def candidates(metrics):
found = []
for name in ("CPI", "SPI"):
status = rag(metrics[name])
if status != "green":
found.append((name, metrics[name], status))
return found
metrics = evm(bac=100000, pv=50000, ev=40000, ac=45000)
print(metrics)
for name, value, status in candidates(metrics):
print(f"{name}={value} is {status}: investigate and classify")
# {'CV': -5000, 'SV': -10000, 'CPI': 0.89, 'SPI': 0.8}
# CPI=0.89 is red: investigate and classify
# SPI=0.8 is red: investigate and classifyBoth indices are red. The code cannot decide whether each is a risk or an issue. A person must look at the cause. Suppose the investigation finds these facts:
- The schedule gap comes from the database team, which started three weeks late because a contractor was not onboarded. That has happened, so it is an issue.
- The cost gap comes mainly from the same contractor rate being higher than estimated. The rate is already fixed, so the overrun to date is an issue. However, the remaining work uses the same contractor, so the overrun will probably continue. That continuing overrun is a risk.
The register entries might read:
| ID | Type | Description | Link to variance | Owner | Response |
|---|---|---|---|---|---|
| I-07 | Issue | Database team started 3 weeks late | SV -10,000 | Delivery lead | Add a second engineer for 4 weeks |
| I-08 | Issue | Contractor rate 18% above estimate | CV -5,000 | Procurement | Renegotiate or substitute |
| R-12 | Risk | Rate overrun continues on remaining work, adding about 12,500 to the final cost | CPI 0.89, VAC -12,500 | Project manager | Mitigate by capping hours |
Notice that each entry cites the variance it came from. That link lets a reader audit the entry later and lets you close it when the variance recovers.
Writing a good risk entry
A risk entry that says "budget might overrun" cannot be managed. Use a cause, event, effect structure:
- Cause. The condition that exists today.
- Event. The uncertain thing that might happen.
- Effect. What it does to scope, schedule, cost, or quality.
Example: "Because the contractor rate is 18% above estimate (cause), the remaining 400 hours may also be billed at that rate (event), which would add about 12,500 to the final cost (effect)."
Then score it. A simple scale of 1 to 5 for probability and 1 to 5 for impact gives a score from 1 to 25. Multiply for an exposure ranking. Where possible, use money: expected monetary value (EMV) is probability times impact. A 50% chance of a 12,500 overrun has an EMV of 6,250. Comparing that figure with the cost of a mitigation tells you whether mitigation pays.
Writing a good issue entry
An issue entry needs less scoring and more ownership.
- State what happened, in the past tense.
- State the current impact in the project's units: days, money, features.
- Name one owner and one due date.
- State the next action, not a general intention.
- Define what "resolved" means so the entry can be closed.
If an issue has no owner, nobody is working on it. If it has two owners, you have the same problem.
Risks that became issues
A risk register entry should be reviewed every cycle. When the uncertain event occurs, the risk becomes an issue. Do three things:
- Close the risk and note the date it occurred.
- Open an issue and link it to the old risk.
- Check whether the response you planned (the contingency) is now triggered.
Keep these records. They show you how accurate your probability estimates were. If your "20% likely" risks occur half the time, adjust your scoring.
Common errors
- Reporting the variance with no entry. The status report shows red, but nothing in the registers explains it. Readers cannot tell whether anyone is working on it.
- Calling everything an issue. This feels decisive but drops probability and removes the chance to prevent the event.
- Calling everything a risk. Treating an event that already happened as a possibility delays action.
- Recording the symptom instead of the cause. "SPI is low" is not a risk. "The vendor may deliver late again" is.
- Ignoring favorable variances. A project that is far ahead of schedule may have skipped work or mis-measured progress. Investigate it.
- Never closing entries. A register with 80 stale entries hides the five that matter.
- Changing thresholds to avoid red. This hides problems and removes the register's value.
Keeping the registers alive
Treat the registers as working tools with a regular rhythm.
- Each reporting period: recalculate variances, review amber and red items, update probabilities and impacts, and close resolved entries.
- Each milestone: review all open risks for relevance and remove those whose window has passed.
- After a change request or rebaseline: re-check all entries. New baselines change which variances exist and which risks still apply.
A short checklist at each review helps:
- Does every red variance link to at least one entry?
- Does every entry have an owner and a date?
- Has any risk occurred and needs conversion to an issue?
- Has any response been done but not closed?
- Do the top three exposures match what the status report highlights?
Summary
A variance tells you where to look. Classification tells you what to do. Confirm the data, find the cause, decide whether it is an event that happened or one that might, and record it with an owner and a link to the variance. Use thresholds fixed in advance, write risks as cause, event, and effect, and write issues with a clear owner and next action. Then pass the entries to corrective action.
Exercise
A project has CPI = 0.93 for the third reporting period in a row, down from 0.97 and 0.95. Your thresholds are green at 0.95 or above and amber from 0.90 to 0.95, with a three-period falling trend rule. The cause is that a supplier raised prices last month, and two more purchase orders to that supplier are still to come. Is this a risk, an issue, or both? What status applies, and what would you write for the risk?
Show answer
Both. The price increase has already happened, so the overrun to date is an issue with an owner (for example, procurement). The two remaining purchase orders create uncertainty about further overrun, so that is a risk. The status is amber, because CPI is in the 0.90 to 0.95 band and has fallen for three periods. A risk entry could read: "Because the supplier raised prices last month (cause), the two remaining purchase orders may be priced at the higher rate (event), which would increase the cost of materials and lower CPI further (effect)." Add probability, impact in money, an owner, and a response such as negotiating a fixed price.
Exercise
Your status report shows SV = +8,000 (ahead of schedule) with no register entries. A colleague says no action is needed because ahead is good. What would you check, and what could the variance turn out to be?
Show answer
Check that the progress data is correct and that the work counted as complete meets its acceptance criteria. A favorable variance can come from overstated percent complete, work completed early because it was started out of sequence, or deliverables skipped or left incomplete. If the data is wrong, it is a measurement problem to fix. If work was done out of sequence or without quality checks, it may be a risk of rework later. If the schedule is genuinely ahead, note it and consider whether the spare time can absorb other slippage.