Sub topic 7
Earned value: PV, EV, AC, CPI, and SPI
What this chapter assumes
You should already know what a baseline is, how percent complete is measured, and how to compute a simple schedule or cost variance. This chapter builds on those ideas. It combines scope, schedule, and cost into one consistent set of numbers called earned value management (EVM).
The problem EVM solves is easy to see. Suppose a project has spent $45,000 of a $100,000 budget. Is that good or bad? You can't tell from the spend alone. If the team planned to spend $45,000 by now and finished the planned work, the project is on track. If it planned to spend $30,000, the project is overspending. If it has finished only a third of the planned work, it is in worse trouble than the spending suggests. EVM answers the question by measuring all three things in the same unit, money.
The three core quantities
Every EVM calculation starts from three numbers, all taken at the same status date.
| Term | Name | Meaning | Where it comes from |
|---|---|---|---|
| BAC | Budget at completion | Total approved budget for all the work | The cost baseline |
| PV | Planned value | Budgeted cost of the work scheduled to be done by the status date | The baseline schedule and budget |
| EV | Earned value | Budgeted cost of the work actually completed by the status date | Your progress measurement rules |
| AC | Actual cost | What you really spent on that completed work, up to the status date | Accounting or timesheets |
Two of these are budget numbers. PV and EV are both measured in baseline prices, so they can be compared directly. AC is the only number measured in real money spent.
A useful way to remember them:
- PV answers "What should be done by now, and what did the plan say it would cost?"
- EV answers "What is actually done, valued at the plan's prices?"
- AC answers "What did it actually cost us?"
Earned value depends on your progress rule
EV is not a free-standing number. You compute it by multiplying the budget of each work package by its percent complete, then summing:
EV = sum of (work package budget × percent complete)
The percent complete comes from the measurement rule you chose earlier, such as 0/100, weighted milestones, or units completed. This matters because EV is only as honest as that rule. If a team reports "90% done" on a package for weeks, EV overstates progress and every index built on it looks better than reality. Rules like 0/100 are stricter and give lower, more defensible EV.
Here is a small example with three work packages.
| Work package | Budget | Percent complete | EV |
|---|---|---|---|
| Design | $20,000 | 100% | $20,000 |
| Build | $60,000 | 25% | $15,000 |
| Test | $20,000 | 0% | $0 |
| Total | $100,000 | $35,000 |
BAC is $100,000 and EV is $35,000. The project has earned 35% of its budget.
Variances: the differences
Two variances compare the three quantities in dollars.
- Cost variance: CV = EV − AC
- Schedule variance: SV = EV − PV
A negative CV means you spent more than the completed work was worth, so you are over cost. A negative SV means you have completed less work than planned, so you are behind schedule. Positive values mean under cost and ahead of schedule.
Notice that both variances use EV as the starting point. The question for cost is "What did the work we finished cost, compared with what we budgeted for it?" The question for schedule is "How much of the planned work did we finish?"
Indices: the ratios
Variances are in dollars, so a $5,000 overrun looks alarming on a $50,000 project and trivial on a $5 million project. Indices are ratios, so they compare projects of any size.
- Cost performance index: CPI = EV / AC
- Schedule performance index: SPI = EV / PV
Read both against 1.0.
| Value | CPI means | SPI means |
|---|---|---|
| Above 1.0 | Getting more than $1 of planned work per $1 spent | Doing work faster than planned |
| Equal to 1.0 | On budget | On schedule |
| Below 1.0 | Getting less than $1 of work per $1 spent | Doing work more slowly than planned |
A CPI of 0.89 means each dollar spent is producing about 89 cents of planned value. An SPI of 0.80 means the team has completed 80% of the work it planned to have done by now.
A worked calculation in code
The following function computes the standard metrics, including the forecast values that the next chapter covers in detail. The project here has a BAC of $100,000. By the status date the plan called for $50,000 of work, the team has completed $40,000 worth, and it has spent $45,000.
def evm(bac, pv, ev, ac):
cpi = ev / ac
spi = ev / pv
eac = bac / cpi
return {
"CV": ev - ac,
"SV": ev - pv,
"CPI": round(cpi, 2),
"SPI": round(spi, 2),
"EAC": round(eac),
"ETC": round(eac - ac),
"VAC": round(bac - eac),
}
print(evm(bac=100000, pv=50000, ev=40000, ac=45000))
# {'CV': -5000, 'SV': -10000, 'CPI': 0.89, 'SPI': 0.8, 'EAC': 112500, 'ETC': 67500, 'VAC': -12500}Walk through the results:
- CV = 40,000 − 45,000 = −5,000. The project is $5,000 over cost for the work done.
- SV = 40,000 − 50,000 = −10,000. The project is $10,000 of planned work behind.
- CPI = 40,000 / 45,000 ≈ 0.89. Cost efficiency is poor.
- SPI = 40,000 / 50,000 = 0.80. Schedule efficiency is worse.
- EAC = 100,000 / 0.89 = 112,500. If the current cost efficiency continues, the project will finish about $12,500 over budget.
Both indices are below 1.0, so the project is behind and over cost. That is the signal to move to variance causes and corrective action.
How the pieces relate
The three base values are compared pairwise. The diagram shows which comparison produces which result.
EV sits in every comparison. It is the shared yardstick, which is why a weak progress measurement rule damages every EVM output at once.
Reading the two indices together
Looking at CPI and SPI together tells you more than either one alone.
| CPI | SPI | Typical reading |
|---|---|---|
| Above 1 | Above 1 | Ahead and under budget. Check that scope was not cut or quality skipped. |
| Above 1 | Below 1 | Under budget but late. Spending may be low because people are missing or work is blocked. |
| Below 1 | Above 1 | Fast but expensive. Possibly overtime, extra staff, or rework. |
| Below 1 | Below 1 | Late and over budget. Needs prompt analysis and usually corrective action. |
These readings are starting hypotheses. The numbers show that something is happening, not why. You still have to ask the team.
Common errors and edge cases
Treating SPI as a true schedule measure
SV and SPI are measured in money, not time. Near the end of a project, all planned work has a PV equal to BAC. If the project finishes late, EV eventually reaches BAC too, so SV and SPI both drift to 0 and 1.0. A project that finished months late can show a perfect SPI at the end. Because of this, SPI is most reliable in the early and middle phases. Pair it with milestone and critical path tracking to see whether the dates actually hold.
Confusing SPI with work on the critical path
SPI sums all work. A team can complete many non-critical tasks and raise SPI while the critical path slips. A healthy-looking SPI does not guarantee the finish date. Check milestones as well.
Mismatched status dates
PV, EV, and AC must all be as of the same date. If accounting costs lag by two weeks, AC is understated, and CPI looks better than it is. Either accrue costs to the status date or choose a status date the accounting data can support.
Using the wrong AC
AC must cover only the work in the baseline scope, in the same cost categories the baseline included. If the baseline excluded internal labor and AC includes it, CPI is distorted. Likewise, AC for work that is not yet started, such as a down payment on equipment, does not belong against the completed work unless the baseline treated it the same way.
Dividing by zero
At the start of a project, AC or PV can be zero. CPI and SPI are undefined in that case. A real tool should handle it. The function above does not, which is acceptable for a teaching example, but a status script should guard against it.
def safe_indices(pv, ev, ac):
cpi = ev / ac if ac else None
spi = ev / pv if pv else None
return cpi, spi
print(safe_indices(pv=0, ev=0, ac=0))
# (None, None)
print(safe_indices(pv=50000, ev=40000, ac=45000))
# (0.8888888888888888, 0.8)Reading EV from a stale baseline
If approved changes have been added to scope but the baseline was not updated, PV and BAC no longer describe the real project. Variances then mix real performance problems with unrecorded scope changes. Update the baseline through change control, then measure.
Overreading small differences
A CPI of 0.98 is not a crisis. Choose thresholds ahead of time, such as investigating when an index falls below 0.9 or above 1.1, and apply them consistently. Many organizations set the thresholds by project risk.
Mixing percent-complete rules without noticing
If one package uses 0/100 and another uses subjective estimates, EV is partly strict and partly optimistic. Document the rule for each package so the numbers can be interpreted.
Trends matter more than a single reading
One status date gives you a snapshot. Calculate CPI and SPI every reporting period and plot them. A project with a CPI of 0.90 that has held steady for six periods is behaving predictably, and the forecast based on it is reliable. A project whose CPI fell from 1.05 to 0.95 to 0.88 is deteriorating, and that direction is itself a finding. As a rule of thumb, a CPI that has been stable for a good fraction of the project tends to persist, which is why it is used for forecasting in the next chapter.
Summary of formulas
| Metric | Formula | Good direction |
|---|---|---|
| CV | EV − AC | Positive |
| SV | EV − PV | Positive |
| CPI | EV / AC | Above 1.0 |
| SPI | EV / PV | Above 1.0 |
Exercise
A project has BAC = $200,000. At the status date, PV = $80,000, EV = $60,000, and AC = $75,000. Calculate CV, SV, CPI, and SPI, and describe the project's state in one sentence. Then explain why a high SPI at the very end of a late project would be misleading.
Show answer
CV = 60,000 − 75,000 = −15,000. SV = 60,000 − 80,000 = −20,000. CPI = 60,000 / 75,000 = 0.80. SPI = 60,000 / 80,000 = 0.75. The project is over cost and behind schedule: each dollar spent returns 80 cents of planned work, and only 75% of the planned work is done. A high SPI near the end is misleading because PV reaches BAC at the planned finish date and EV eventually reaches BAC when the work is done, so SPI converges to 1.0 even if the project finished months late. SPI is measured in money, not time, so it cannot show lateness once the planned end date has passed.
Exercise
A team reports a design package with a $30,000 budget as "80% done" for the fourth week in a row, and AC on the package is $28,000. What EV would the team report, what is the resulting CPI for this package, and what would you change about the measurement rule?
Show answer
EV = 30,000 × 0.80 = 24,000, so CPI = 24,000 / 28,000 ≈ 0.86. The repeated "80% done" suggests the figure is a subjective estimate that is not moving, so EV and CPI may be overstated. Switch to a stricter rule such as 0/100 or weighted milestones with objective completion criteria (for example, "design reviewed and approved"). Then EV only rises when a verifiable milestone is met.