Sub topic 6
Burndown and Burnup Charts for Iterative Work
This chapter assumes you know what a sprint, a backlog, and a story point are. It also assumes you have read the earlier chapters on baselines and progress measurement rules. Here you learn to build burndown and burnup charts, read them, and avoid the mistakes that make them misleading.
What these charts are for
In iterative work, the plan is a set of time boxes (sprints or iterations) and a pool of work (the backlog). Each iteration is short. The scope can change between iterations. A Gantt chart with a fixed baseline fits this poorly, so teams track the amount of work against elapsed time.
Both charts answer the same question: how much work is left, and will it be done by the deadline? They differ in what they make visible.
- A burndown chart plots remaining work against time. The line falls toward zero.
- A burnup chart plots completed work and total scope against time. The completed line rises toward the scope line.
Both use the same data: the work completed each day and the total scope each day. Remaining work is the scope minus the completed work.
Building a burndown chart
You need three things:
- A unit of work. Story points are common. Task counts or hours also work if used consistently.
- A start value, usually the total committed work at the start of the iteration.
- A daily reading of the work remaining.
The ideal line is a straight line from the start value on day 0 to zero on the last day. It is a reference, not a forecast. Real work is lumpy because stories finish in whole pieces, so the actual line usually looks like stairs.
The gap is actual remaining minus ideal remaining. A positive gap means behind the ideal line. A negative gap means ahead of it. The script below computes the gap for a 40-point, 10-day sprint.
total_points = 40
sprint_days = 10
actual_remaining = [40, 38, 35, 33, 30]
for day, remaining in enumerate(actual_remaining):
ideal = total_points - (total_points / sprint_days) * day
gap = remaining - ideal
print(f"day {day}: remaining={remaining}, ideal={ideal:.0f}, gap={gap:+.0f}")
# day 0: remaining=40, ideal=40, gap=+0
# day 1: remaining=38, ideal=36, gap=+2
# day 2: remaining=35, ideal=32, gap=+3
# day 3: remaining=33, ideal=28, gap=+5
# day 4: remaining=30, ideal=24, gap=+6The team burns 2 to 3 points a day, but the plan needs 4. The gap grows every day, so the team is not catching up. This is the same idea as schedule variance, shown over time instead of at one date.
Reading a burndown chart
Look at the slope and the gap, not at one day's value.
| Pattern | Likely meaning | Question to ask |
|---|---|---|
| Actual stays above ideal, gap widening | Delivery is slower than planned | Is the estimate wrong, or is something blocking the team? |
| Flat line for several days, then a sharp drop | Work is started but not finished, or finished stories are not marked done | Is work-in-progress too high? Is the board updated daily? |
| Line below ideal early, then flattens | Easy work was done first, or stories were over-estimated | What is left, and is it harder? |
| Line rises on one day | Scope was added, or work was re-estimated upward | Was the change agreed, and who approved it? |
| Line hits zero well before the end | Under-commitment, or work was completed with a lower definition of done | Should more be pulled in? Was quality skipped? |
The flat-then-drop pattern is a measurement problem as well as a delivery problem. It is the iterative version of the 0/100 rule: a story counts only when it is done. That makes the chart hard to inflate, but it also means the line only moves when whole stories finish.
The weakness of burndown: hidden scope change
Suppose the team finishes 3 points on a day and the product owner adds 3 points of new work. Remaining work does not change, so the burndown line stays flat. A reader sees "no progress" when the team actually delivered. A reader who is not told about the added scope may blame the team.
The opposite also happens. If scope is cut, the line drops without anything being delivered, and the sprint looks healthier than it is.
The burndown merges two different events, delivery and scope change, into one line. The burnup chart keeps them apart.
Building a burnup chart
A burnup chart has two lines:
- The scope line shows the total work agreed so far. It steps up when scope is added and down when it is removed.
- The done line shows cumulative completed work. It only goes up.
The gap between the lines is the remaining work. Progress is the done line rising. Scope change is the scope line moving. A flat done line means the team delivered nothing that day, and a step in the scope line shows when new work arrived.
The script below uses the same sprint but adds 8 points of scope on day 3. It also projects a finish date from the average rate so far.
done = [0, 2, 5, 7, 10]
scope = [40, 40, 40, 48, 48]
for day, (d, s) in enumerate(zip(done, scope)):
print(f"day {day}: done={d}, scope={s}, remaining={s - d}")
days_elapsed = len(done) - 1
velocity = done[-1] / days_elapsed
days_left = (scope[-1] - done[-1]) / velocity
print(f"velocity={velocity:.1f} points/day, "
f"projected finish at day {days_elapsed + days_left:.1f}")
# day 0: done=0, scope=40, remaining=40
# day 1: done=2, scope=40, remaining=38
# day 2: done=5, scope=40, remaining=35
# day 3: done=7, scope=48, remaining=41
# day 4: done=10, scope=48, remaining=38
# velocity=2.5 points/day, projected finish at day 19.2On day 3 the burndown would show remaining work going up from 35 to 41. The burnup shows the true cause: the team delivered 2 points, and 8 points of scope arrived. The projection says work will end at about day 19, not day 10. To finish by day 10 the team needs 38 points in 6 days, about 6.3 points per day, which is more than double its pace so far.
Choosing between them
Use a burndown when the scope is fixed or nearly fixed, such as one sprint with a committed goal. It is simple, and most teams already know how to read it.
Use a burnup when the scope can change, such as a release or a long project. Stakeholders can see the scope line move and so link the delay to the change. This supports the change control process described later in this tutorial.
Many teams draw both: a burndown for each sprint and a burnup for the release.
Edge cases and gotchas
The unit of work
Points measure relative size, and teams estimate them differently. Use the chart only for one team, and do not compare teams by their lines. Task counts are easier to audit but treat a one-hour task like a three-day task. If you use counts, keep the stories a similar size.
Re-estimating work
If a story is re-estimated from 5 points to 8, remaining work rises by 3 although nothing was added. Decide on one rule and apply it every time. A common choice is to leave the estimate of started or finished stories alone, and to record only re-estimates of work not yet started. When you re-estimate, note it on the chart so the bump is not read as lost progress.
Partial credit
If you count a story as 50% done when it is half-coded, the line looks smooth, but the progress is hard to verify. The 0/100 rule makes the line jumpy but trustworthy. For an iteration a few days long, 0/100 is usually the right choice.
Weekends and holidays
The ideal line should span working days only. If you plot calendar days, the ideal line declines over the weekend when nobody works, and every Monday shows a false gap. Also lower the ideal line on days when people are away, if capacity matters.
Stories finishing on the last day
If most stories close on the last day, the chart tells you nothing until it is too late. This usually points to large stories or a late testing phase. Split stories so they can finish in one or two days, and the daily line becomes useful.
Straight ideal lines are not forecasts
The ideal line assumes constant delivery. Real teams ramp up, hit blockers, and finish with a tail of testing. A better forecast uses actual velocity, as the burnup script did. Treat any projection as a range, since a few days of data can mislead. Use more history, such as the average of the last three sprints, once it exists.
Gaming the chart
When a chart becomes a target, people adjust the data. Examples include closing stories before testing, splitting a story to count more done items, or leaving out new work. Agree on a definition of done, and review scope changes openly.
Linking to variance and corrective action
A growing gap on a burndown is a schedule variance in other units. When the gap grows, work through these questions in order:
- Is the done line rising at the expected rate? If not, the problem is delivery. Look for blockers, too much work in progress, or estimates that were too low.
- Did the scope line move? If so, the cause is scope change. Raise it through change control instead of treating it as a team failure.
- Is the projected finish after the deadline? If so, choose an action: cut scope, add capacity, extend the date, or accept a lower quality. Each has a cost, which later chapters cover.
The burnup answers questions 1 and 2 at a glance, which is why it is often the better chart for a status report.
Exercise
A team starts a 10-day sprint with 30 points. After 5 days it has completed 12 points and 6 points of new work were added to the sprint. Calculate the remaining work, the ideal remaining work on day 5, and the gap. Then say what a burndown line would show compared with a burnup.
Show answer
Scope is 30 + 6 = 36 points. Remaining is 36 - 12 = 24 points. The ideal remaining on day 5 is 30 - (30/10) x 5 = 15 points, measured against the original commitment. The gap is 24 - 15 = +9 points, behind plan. The burndown would show a line that fell only from 30 to 24 and would hide that the team delivered 12 points and the other 6 points came from added scope. The burnup would show the done line at 12 and the scope line stepped up from 30 to 36, so the cause is clear.
Exercise
Using the burnup script, the done line is [0, 3, 6, 9] over days 0 to 3 and the scope is constant at 30. What velocity and projected finish day does the method give? Does the sprint finish by day 10?
Show answer
Velocity is 9 / 3 = 3 points per day. Remaining is 30 - 9 = 21 points, so 21 / 3 = 7 more days. The projected finish is day 3 + 7 = day 10, so the sprint finishes on time if the pace holds, with no margin.
Exercise
A burndown line stays flat for four days and then drops by 15 points on day 5. Give two possible causes and one change to the process that would make the line more useful.
Show answer
Possible causes are that several stories were in progress at the same time and all closed together, or that the board was not updated during the four days. A useful change is to limit work in progress and split stories so each can finish in one or two days, and to update the board daily after stand-up.