Sub topic 10
Choosing a corrective action
This chapter covers what to do once variance analysis shows a project is off plan. It assumes you can compute schedule and cost variance, CPI, SPI, and EAC from earlier chapters. It also assumes you know what a critical path is and have seen a risk register.
Why the choice matters
A variance is a measurement, not a decision. A project that is 10% behind schedule can respond in at least five ways: do nothing, add people, cut scope, move the deadline, or fix a broken process. Each has a different cost and side effects. Picking one by reflex ("add people") is a common way to turn a small variance into a large one.
A corrective action is a documented change to how the work is done. Its purpose is to bring future performance back in line with the existing baseline. That definition separates it from two neighboring responses:
- A change request alters the baseline itself (scope, schedule, or budget). It goes through change control.
- A rebaseline replaces the baseline with a new one. It is a last resort, covered in the next chapter.
The order of preference is usually corrective action first, change request second, rebaseline last. Each step makes the original plan less useful as a yardstick.
Step 1: Decide whether to act at all
Not every variance deserves a response. Small swings are normal, and reacting to noise wastes effort and confuses the team.
Set a threshold before the project starts. Examples are CPI or SPI outside 0.95 to 1.05, or a milestone slipping by more than a set number of working days. Thresholds are written into the plan so that nobody argues about them after the fact.
Check three things before acting:
- Trend, not a single point. A variance that appears in one period and reverses is usually timing. A variance that widens over three periods is a trend.
- Critical path. A task that slips but has float (slack) may not delay the finish date. A slip on the critical path moves the end date day for day.
- Measurement quality. If progress is reported as "90% done" for weeks, the variance may be a reporting artifact. Check the progress rule first (see the chapter on percent complete).
Step 2: Find the cause
A corrective action aimed at the wrong cause does not work. Separate causes into groups, because each group points to different actions.
| Cause | Typical evidence | Where it shows up |
|---|---|---|
| Estimate was too low | Every task of one type overruns by a similar ratio | CPI and SPI both below 1 from early on |
| Productivity is lower than planned | Same hours produce fewer units | Burndown flattens, labor cost is on plan but EV is low |
| Rework and defects | Tasks reopen, test failures rise | Actual cost rises with no EV gain |
| Scope growth | Backlog grows, requirements added informally | Burnup scope line rises |
| Dependency delay | Waiting on a vendor or another team | Critical path tasks idle |
| Resource unavailable | People pulled to other work | SPI drops, AC stays low |
| Price or rate change | Unit costs differ from plan | Cost variance with schedule on plan |
Link the cause to your risk and issue log. If the cause was a known risk that has now occurred, it is an issue and its response plan may already name the action. If it was not in the log, add it and look for related risks that may follow.
Step 3: Pick the lever
Every project has four levers: scope, schedule, cost, and quality. Moving one affects the others. Most corrective actions fall into one of the groups below.
| Lever | Action | Helps | Costs |
|---|---|---|---|
| Schedule | **Fast tracking:** run tasks in parallel that were planned in sequence | Time | Higher rework risk |
| Schedule | **Crashing:** add resources to critical path tasks | Time | Higher cost, diminishing returns |
| Cost | Substitute cheaper resources or materials | Budget | Possible quality or speed loss |
| Scope | Defer or drop low-value items | Time and budget | Needs stakeholder approval, so it is a change request |
| Quality | Add reviews or tests earlier | Reduces rework | Short-term cost and time |
| Process | Remove a blocker, fix handoffs, resolve a dependency | Time and cost | Management attention |
Two rules apply to these levers.
Only the critical path matters for schedule recovery. Crashing or fast tracking a task with float shortens nothing. Spend effort where a day saved is a day saved on the finish date.
Adding people has limits. New team members need onboarding from existing members, and communication paths grow with team size. On knowledge-heavy work, adding people to a late task often slows it further. Crashing works best on work that divides cleanly, such as testing, data entry, or installation.
Step 4: Test whether recovery is realistic
Before committing to recovering within the current budget, check what performance you would need from now on. The To-Complete Performance Index (TCPI) answers this. Against the original budget it is:
TCPI = (BAC - EV) / (BAC - AC)
It is the cost efficiency required on all remaining work to finish within BAC. If TCPI is near 1.0, recovery is plausible. If it is well above your current CPI, the plan assumes a sudden improvement that nothing in the data supports. The team is also unlikely to deliver it.
The script below turns the earlier metrics into a first-pass triage. The thresholds are examples. Set yours in the plan.
def tcpi(bac, ev, ac):
return (bac - ev) / (bac - ac)
def triage(cpi, spi, tcpi_bac, tolerance=0.05, tcpi_limit=1.10):
actions = []
if cpi < 1 - tolerance:
actions.append("cost: find the cause, then cut cost or scope")
if spi < 1 - tolerance:
actions.append("schedule: check the critical path, then fast track or crash")
if tcpi_bac > tcpi_limit:
actions.append("budget recovery unlikely: raise a change request or rebaseline")
if not actions:
actions.append("within tolerance: keep monitoring")
return actions
scenarios = {
"A": dict(bac=100000, pv=50000, ev=40000, ac=45000),
"B": dict(bac=100000, pv=45000, ev=30000, ac=50000),
}
for name, s in scenarios.items():
cpi = s["ev"] / s["ac"]
spi = s["ev"] / s["pv"]
t = tcpi(s["bac"], s["ev"], s["ac"])
print(f"{name}: CPI={cpi:.2f} SPI={spi:.2f} TCPI={t:.2f}")
for action in triage(cpi, spi, t):
print(" -", action)
# A: CPI=0.89 SPI=0.80 TCPI=1.09
# - cost: find the cause, then cut cost or scope
# - schedule: check the critical path, then fast track or crash
# B: CPI=0.60 SPI=0.67 TCPI=1.40
# - cost: find the cause, then cut cost or scope
# - schedule: check the critical path, then fast track or crash
# - budget recovery unlikely: raise a change request or rebaselineScenario A is the project from the earlier earned value example. It needs about 9% better cost efficiency than the plan assumed, which is demanding but within reach of a corrective action. Scenario B needs 40% better than plan while currently running at 60% efficiency. No process fix will close that gap, so the honest options are a change request (more budget, less scope) or a rebaseline.
The script only sorts variances into starting points. It does not read the cause, the critical path, or the stakeholders' priorities, and a person still has to weigh those.
Step 5: Route the decision
Use the authority and the effect on the baseline to decide where the action goes.
In practice:
- A corrective action within the team's authority (for example, reassigning two testers) needs only a log entry and a mention in the status report.
- An action that changes cost, schedule, or scope beyond the agreed tolerances needs a change request and sponsor approval.
- A rebaseline needs approval and a written reason. After it, variance restarts from zero, so keep the old baseline's history in the record to avoid hiding past performance.
Step 6: Record, assign, and verify
A corrective action without an owner and a date is a hope. For each action record:
- the variance and cause it targets
- the action and its expected effect, stated as a number ("raise SPI from 0.80 to 0.95 within three weeks")
- one named owner
- a review date
- any new risk it creates
At the next period, compare the metric with the expectation. There are three outcomes:
- It worked. The metric moved as expected. Close the action.
- It partly worked. Keep it and add a second action, or revise the target.
- It did not work. Reopen the cause analysis. The first diagnosis was probably wrong.
Remember that SPI and CPI are cumulative. A good month barely moves a ratio built on ten months of history. To judge a recent action, also look at the period's own numbers (period EV divided by period PV, for example), not only the project total.
Common errors
- Treating the symptom. Adding overtime to a team that is blocked on a vendor produces cost with no schedule gain.
- Recovering float-rich tasks. Effort goes to tasks that were never going to delay the end date.
- Chaining quick fixes. Several unrecorded fixes make it impossible to know which one helped.
- Hiding scope cuts. Dropping features silently turns a schedule recovery into a quality problem. Scope reductions need approval and a mention in the status report.
- Averaging away a trend. Cumulative indices can look acceptable while the last three periods trend badly. Check both.
- Skipping the follow-up. An action never reviewed is an action never learned from.
Linking to the next chapters
Corrective actions that stay inside the baseline are reported but do not change it. Those that cannot stay inside it feed change control, covered next. In both cases the action, its owner, and its measured effect belong in the status report. That report also states progress, variance, forecast, risks, and decisions needed.
Exercise
A project has BAC = 200,000, EV = 80,000, AC = 100,000, and PV = 90,000. (a) Compute CPI, SPI, and TCPI against BAC. (b) With a threshold of 1.10 for TCPI, should you plan on recovering within budget through a corrective action alone? (c) One late task has 6 days of float. Should you crash it to recover the schedule?
Show answer
(a) CPI = 80,000 / 100,000 = 0.80. SPI = 80,000 / 90,000 = 0.89. TCPI = (200,000 - 80,000) / (200,000 - 100,000) = 120,000 / 100,000 = 1.20. (b) No. TCPI of 1.20 exceeds the 1.10 limit and is far above the current CPI of 0.80, so the remaining work would need 50% better cost efficiency than the project is delivering. Raise a change request (more budget or less scope) or plan for a rebaseline. (c) No. A task with float does not control the end date, so crashing it spends money without shortening the schedule. Apply schedule actions to critical path tasks.
Exercise
Your team applied a corrective action three weeks ago expecting SPI to rise from 0.80 to 0.95. Cumulative SPI is now 0.83, but the last three periods each show a period SPI of about 1.0. Did the action work?
Show answer
Probably yes, at least in part. Cumulative SPI moves slowly because it includes all earlier months of poor performance, so it understates a recent recovery. Period SPI of about 1.0 shows the team now earns value at the planned rate. The action has stopped the slide but has not recovered the earlier shortfall. If the end date must still be met, a further action is needed to earn the lost value back. Report both numbers and explain the gap.