Reading variance: planned versus actual
This chapter assumes you know what a baseline is (the approved plan for scope, schedule, and cost) and how progress is measured with a rule such as 0/100 or units completed. It also assumes you are comfortable with percentages and ratios. Here you learn to compute variance, read what it says, and decide what to do with it.
What variance is
Variance is the gap between what the baseline said would happen and what actually happened. It is a measurement, not a verdict. A variance tells you where to look. It does not tell you why the gap exists or whether it matters.
You can measure variance on several dimensions:
- Cost variance: money or effort spent compared with the amount planned.
- Schedule variance: dates or durations compared with the baseline dates.
- Scope variance: work delivered compared with work planned, for example 18 of 24 features.
- Quality variance: defects, rework, or test failures compared with the target.
Cost and schedule variance get the most attention because they are easy to quantify. Scope and quality variance often explain them.
Fix a sign convention first
Teams get confused when one report says "variance: 400" and nobody knows whether that is good news. Pick one convention and state it in every report. This chapter uses:
- Variance = baseline value − actual value, for cost and for duration.
- A positive number is favorable (under budget, early).
- A negative number is unfavorable (over budget, late).
Earned value management, covered in a later chapter, defines cost variance as earned value minus actual cost. The sign meaning is the same: negative is bad. Some spreadsheets define variance as actual minus plan, which flips the sign. Check the definition before you compare numbers from two sources.
| Measure | Formula | Negative means | Positive means |
|---|---|---|---|
| Cost variance (CV) | planned cost − actual cost | Over budget | Under budget |
| Duration variance | planned days − actual days | Took longer | Took less time |
| Finish variance | baseline finish − forecast finish | Finishing late | Finishing early |
| Percent variance | variance ÷ planned × 100 | Same sign as the variance | Same sign as the variance |
Absolute and percent variance
An absolute variance is in the unit you measure: dollars, hours, days. A percent variance divides by the planned value. You need both, because each hides something.
- A 2,000 dollar overrun is trivial on a 2,000,000 dollar project and a crisis on a 5,000 dollar task.
- A 50 percent overrun on a 100 dollar task is noise.
Compare percent variance against a threshold, and apply an absolute floor as well, so small tasks do not flood the report with alerts. A common rule is to investigate when the variance exceeds both 10 percent and some minimum amount that your sponsor cares about.
Compute variance at the right level
Variance computed at the wrong level misleads you. The level should match the level at which the baseline was set.
- Work package level is where you find causes. A package is a small piece of the work breakdown structure with one owner.
- Phase or deliverable level is where managers decide.
- Project level is where sponsors read.
Totals can hide offsetting problems. If one package is 20 percent over and another is 25 percent under, the project total looks healthy while two packages need attention. Always check the packages beneath a quiet total.
The next script computes cost and duration variance per task, flags anything beyond a threshold in either direction, and then reports the total.
THRESHOLD_PCT = 10.0
# name, planned cost, actual cost, planned days, actual days
tasks = [
("Design", 8000, 8400, 10, 12),
("Build", 20000, 24000, 20, 26),
("Test", 6000, 5700, 8, 8),
("Docs", 2000, 1500, 5, 4),
]
total_planned = 0
total_actual = 0
for name, plan_cost, act_cost, plan_days, act_days in tasks:
cv = plan_cost - act_cost
cv_pct = cv / plan_cost * 100
dv = plan_days - act_days
dv_pct = dv / plan_days * 100
beyond = abs(cv_pct) > THRESHOLD_PCT or abs(dv_pct) > THRESHOLD_PCT
status = "investigate" if beyond else "ok"
print(f"{name}: cost {cv:+.0f} ({cv_pct:+.1f}%), "
f"days {dv:+d} ({dv_pct:+.1f}%) -> {status}")
total_planned += plan_cost
total_actual += act_cost
total_cv = total_planned - total_actual
print(f"Total cost variance: {total_cv:+.0f} "
f"({total_cv / total_planned * 100:+.1f}%)")
# Design: cost -400 (-5.0%), days -2 (-20.0%) -> investigate
# Build: cost -4000 (-20.0%), days -6 (-30.0%) -> investigate
# Test: cost +300 (+5.0%), days +0 (+0.0%) -> ok
# Docs: cost +500 (+25.0%), days +1 (+20.0%) -> investigate
# Total cost variance: -3600 (-10.0%)Three things stand out in the output:
- Design has a small cost variance (-5.0 percent) but a large time variance (-20.0 percent). Cost alone would have missed it.
- Docs is favorable but still flagged. Finishing a task early and cheaply can mean work was skipped, so favorable variances also need a look.
- The total cost variance is -10.0 percent, which is not strictly over the threshold. Yet one package, Build, is 20 percent over. The total understates the problem.
Do not add up task durations to get a project duration variance. Durations only add when tasks run in sequence. For the project finish date, use the schedule, which the next section covers.
Schedule variance is about the critical path
A task that runs 30 percent over its duration does not necessarily move the project end date. What matters is float, the time a task can slip without delaying a successor or the project finish.
- A task on the critical path has zero float. Any slip moves the finish date.
- A task off the critical path can slip by its float before it affects the finish.
So read schedule variance in two steps. First, compute the duration variance for the task. Second, check whether the slip consumed float or pushed the finish. A 6-day slip on a task with 10 days of float is a note. A 2-day slip on a critical task is a delay. Also watch for a slip that consumes float and creates a new critical path through a task that used to be safe.
Percent complete tells you about timing as well. If a task is 50 percent complete at the date the baseline expected 80 percent, the task is behind, whatever its dates say. This is why the measurement rules from the previous chapter matter: a poorly measured percent complete produces a meaningless variance.
Timing variance versus real variance
Not every variance is a problem with the project. Separate these cases before you act:
- Timing variance: the work is on track but the cost is booked in a different period. An invoice arrives a month after the work. A purchase made early shows as overspent until later spending slows. These variances reverse themselves.
- Real variance: the work costs more or takes longer than planned. Without a change, it will remain at the end.
- Baseline error: the plan was wrong, for example an estimate that missed a dependency. The work is fine, and the baseline is what failed.
- Unrecorded change: scope was added informally, so actual work is compared with a baseline that no longer describes it.
Checking for timing variance first avoids false alarms. Checking for baseline error and unrecorded change protects you from blaming the team for a flaw in the plan. The last two cases lead to change control, covered in a later chapter.
Finding the cause
A variance without a cause cannot be fixed. Ask a short series of questions, from cheapest to most expensive:
- Is the measurement right? Check the actuals for missing timesheets, late invoices, and wrong coding.
- Is the baseline right? Compare the estimate with how the work really went.
- Did scope change? Look for added work that never went through a request.
- Is the work harder than expected? This points to an estimate or skill problem.
- Is the work blocked? Waiting on a person, a vendor, or an approval shows up as schedule variance with little cost variance.
The pattern of the two variances is a clue:
| Cost | Schedule | Likely reading |
|---|---|---|
| Over | Late | Work is harder than estimated, or rework |
| Over | On time | Paying more to hold the date, such as overtime or extra staff |
| On budget | Late | Waiting or blocked, with people idle or elsewhere |
| Under | Late | Not enough people on the work, or work not started |
| Under | Early | Good performance, or scope cut quietly |
Treat the table as a list of hypotheses. Confirm each one with the work package owner before you write it in a report.
Trends matter more than snapshots
One period's variance is a point. Three periods are a direction. Compare these two projects, both showing a cost variance of -5 percent today:
- Project A moved from -9 to -7 to -5 percent. It is recovering.
- Project B moved from -1 to -3 to -5 percent. It is worsening, and at that rate it will cross the threshold within two periods.
Record variance at every reporting date and look at the slope. A steady, growing gap usually means a cause that has not been addressed. A single spike usually means an event, such as a purchase, an outage, or a resignation.
Connecting variance to action
Reading variance ends with a decision, and the following chapters build on it:
- A variance with a cause that may recur becomes a risk or an issue (an event that has already happened).
- A variance you can recover inside the plan's tolerance gets a corrective action.
- A variance caused by a baseline error or an approved scope change goes through change control, and may lead to a rebaseline.
- Every variance above threshold appears in the status report with its cause and its next step.
Exercise
A work package has a planned cost of 12,000 dollars and an actual cost of 13,800 dollars. Using the convention in this chapter, what are its cost variance and percent variance, and is it favorable? With a threshold of 10 percent, should you investigate?
Show answer
Cost variance = 12,000 − 13,800 = −1,800 dollars. Percent variance = −1,800 ÷ 12,000 × 100 = −15 percent. The negative sign means it is unfavorable (over budget). Because 15 percent exceeds the 10 percent threshold, investigate. First check whether the overrun is only timing, such as an invoice booked early, before treating it as real.
Exercise
A task has a duration variance of −5 days. The project manager says the project will finish 5 days late. What information do you need before you agree, and what are the two possible outcomes?
Show answer
You need the task's float. If the task has 5 or more days of float, the slip uses up float and the project finish does not move, although the schedule has less protection left. If the task is on the critical path (zero float), or the slip exceeds its float, the finish date moves by the amount of the slip beyond the float. You should also check whether the slip makes another path critical.
Exercise
Project X has cost variances of -2, -4, and -6 percent over three periods. Project Y has -8, -6, and -4 percent. Which one needs more urgent attention, and why?
Show answer
Project X. Its variance is growing by about 2 points each period, so it is worsening and will likely cross a 10 percent threshold in two more periods. Project Y has a larger variance today in the first period but is shrinking, which suggests recovery. The trend, not the single value, sets the urgency.