Forecasting with EAC and ETC
This chapter assumes you know the basic earned value terms from the previous chapter: planned value (PV), earned value (EV), actual cost (AC), cost performance index (CPI), and schedule performance index (SPI). It also assumes you are comfortable with ratios. You will learn to turn those numbers into a forecast of the final cost and the remaining spend.
Why forecast at all
Variance tells you where the project stands today. A forecast tells you where it will finish if nothing changes. Sponsors and finance teams care about the second question, because they approve funding for the whole project, not for the part already done.
Two quantities carry the forecast:
- Estimate at completion (EAC) is the expected total cost of the project when it finishes. It equals the money already spent plus the money still to be spent.
- Estimate to complete (ETC) is the expected cost of the remaining work only.
They are linked by one identity:
EAC = AC + ETC
ETC = EAC - ACA third number compares the forecast with the plan:
- Variance at completion (VAC) is
BAC - EAC. BAC is the budget at completion, the total of the cost baseline. A negative VAC means a forecast overrun.
The central question: will past performance continue?
Every EAC formula answers the same question differently: what do you believe about the future cost efficiency of the remaining work? There are three common beliefs.
- The variance was a one-off. An unusual event caused the overrun, and the rest of the work will cost what the baseline says.
- The current efficiency will continue. The project will keep earning each unit of value at the same cost ratio as so far.
- The original plan is no longer valid. The remaining work needs a fresh, bottom-up estimate.
A fourth belief combines cost and schedule pressure, and is described below.
Formula 1: atypical variance
Use this when the cost variance came from a single event that will not recur, such as a one-time equipment failure.
EAC = AC + (BAC - EV)You keep the overrun already incurred and assume the remaining work, BAC - EV, costs what was budgeted.
Formula 2: typical variance
Use this when the cause is systemic, such as an underestimated unit cost or a team that is slower than assumed.
EAC = BAC / CPIThis assumes that every remaining unit of work costs 1 / CPI times its budget. It is the default formula in most organizations, because overruns tend to persist.
Formula 3: bottom-up re-estimate
Use this when the baseline is clearly wrong, for example after a major change in technology or scope.
EAC = AC + ETC_newHere ETC_new is a fresh estimate of the remaining work, built from the remaining tasks. It is the most accurate method and the most expensive, because someone has to re-estimate the work.
Formula 4: cost and schedule combined
Use this when the deadline is fixed, so a late project must buy back time with extra resources.
EAC = AC + (BAC - EV) / (CPI * SPI)This formula is more pessimistic than Formula 2 whenever SPI is below 1. It assumes the remaining work is hit by both inefficiencies.
Choosing a formula
| Situation | Formula | Typical result |
|---|---|---|
| One-time cause, now resolved | `AC + (BAC - EV)` | Lowest EAC when CPI is below 1 |
| Systemic cause, same team and method | `BAC / CPI` | Middle value, the common default |
| Baseline invalid or scope changed | `AC + new bottom-up ETC` | Depends on the estimate |
| Fixed deadline, behind schedule | `AC + (BAC - EV) / (CPI * SPI)` | Highest EAC when CPI and SPI are below 1 |
When you cannot decide, compute two or three and report them as a range. A range is more honest than one precise-looking number.
A worked example
The following function extends the earned value calculation from the previous chapter. It returns all four EAC methods for the same project data.
def forecast(bac, pv, ev, ac, new_etc=None):
cpi = ev / ac
spi = ev / pv
results = {
"atypical": ac + (bac - ev),
"typical": bac / cpi,
"cost_and_schedule": ac + (bac - ev) / (cpi * spi),
}
if new_etc is not None:
results["bottom_up"] = ac + new_etc
out = {}
for name, eac in results.items():
out[name] = {
"EAC": round(eac),
"ETC": round(eac - ac),
"VAC": round(bac - eac),
}
return out
if __name__ == "__main__":
data = forecast(bac=100000, pv=50000, ev=40000, ac=45000, new_etc=65000)
for method, values in data.items():
print(method, values)The project has a BAC of 100,000. It has earned 40,000 of value, spent 45,000, and planned to have earned 50,000. That gives CPI = 40,000 / 45,000 = 0.89 and SPI = 40,000 / 50,000 = 0.80.
The output is:
atypical {'EAC': 105000, 'ETC': 60000, 'VAC': -5000}
typical {'EAC': 112500, 'ETC': 67500, 'VAC': -12500}
cost_and_schedule {'EAC': 129375, 'ETC': 84375, 'VAC': -29375}
bottom_up {'EAC': 110000, 'ETC': 65000, 'VAC': -10000}Here is how to read the table:
- The atypical forecast, 105,000, only adds the 5,000 overrun to the original budget. It is valid only if you can name the one-time cause and show it is gone.
- The typical forecast, 112,500, matches the 12,500 overrun shown in the previous chapter.
- The combined forecast, 129,375, assumes the project must also recover the schedule slip. It is a worst-case style figure.
- The bottom-up forecast, 110,000, depends entirely on the quality of the new estimate. Here it sits between the optimistic and typical values.
A sensible report to a sponsor might say: "Forecast final cost is 110,000 to 112,500, against a budget of 100,000. The worst case, if we must also recover the schedule, is about 129,000."
Forecasting the finish date
Cost is not the only thing you can forecast. A simple schedule forecast uses SPI the same way:
Estimated duration = planned duration / SPIIf a 10-month project has SPI = 0.80, the naive forecast is 12.5 months. Treat this as a rough guide, not a precise date. The reason is covered in the next section.
Gotchas and failure modes
CPI is stable early, so use it with care
Studies of large projects have found that CPI rarely improves much after the project is about 20% complete. That supports Formula 2 as a default in the middle and late stages. In the first few weeks, though, CPI swings widely because EV and AC are both small. Do not extrapolate from a CPI measured on 5% of the work.
SPI converges to 1.0 at the end
SPI is computed in money terms, so when a project finishes, EV equals PV and SPI becomes exactly 1.0, even if the project finished months late. A late project can show a healthy SPI near the end. For this reason, forecast the finish date with a critical path analysis or with milestone slippage, and use SPI only as an early signal.
A weak EV rule corrupts the forecast
Forecasts inherit the quality of the progress measurement. If tasks are reported as "90% done" for weeks, EV is overstated, CPI looks better than it is, and EAC is too low. This is why the earlier chapter on progress measurement rules matters. A 0/100 rule or weighted milestones give a more trustworthy EV than subjective percentages.
Unrecorded costs make AC too low
Invoices that have not arrived, accrued labor, and committed purchases are real costs. If AC includes only paid bills, CPI looks good and EAC is understated. Include accruals.
Division by zero and tiny denominators
CPI is undefined if AC is zero, and SPI is undefined if PV is zero. Guard against this in any spreadsheet or script. In the first reporting period, report "not enough data" instead of a number.
Mixing a changed baseline with old actuals
If a change request raised BAC, use the new BAC in the formulas and make sure EV was recomputed against the new baseline. Using the old EV with the new BAC gives a false forecast.
Forecasting a project that is ahead
A CPI above 1 does not mean the project will finish under budget. A team may be early on easy work and have the hard work left. Treat a good CPI with the same skepticism as a bad one, and check the remaining work.
The To-Complete Performance Index
The to-complete performance index (TCPI) tests whether a target is realistic. It tells you the cost efficiency the remaining work must achieve to hit a goal.
TCPI (to BAC) = (BAC - EV) / (BAC - AC)
TCPI (to EAC) = (BAC - EV) / (EAC - AC)For the example project, TCPI to BAC is (100,000 - 40,000) / (100,000 - 45,000) = 60,000 / 55,000 = 1.09. The team must now earn 1.09 units of value per unit of cost for the rest of the project, while so far it has managed 0.89. That is a large jump, and it is a strong sign the original budget is no longer credible.
def tcpi(bac, ev, ac, target=None):
target = bac if target is None else target
return (bac - ev) / (target - ac)
print(round(tcpi(100000, 40000, 45000), 2))
print(round(tcpi(100000, 40000, 45000, target=112500), 2))The first call prints 1.09. The second prints 0.89, because the 112,500 forecast assumes the team keeps its current efficiency.
How the forecast feeds the next steps
The forecast is not the end of the analysis. It sets up the decisions that follow.
If VAC is inside the agreed tolerance, you report it and keep monitoring. If not, the next chapters cover how to respond: link the variance to risks and issues, choose a corrective action, and decide whether to rebaseline.
Practical habits
- Recompute every reporting period. A forecast made once at the start is only a plan. Use the same formulas each time so the trend is comparable.
- Record which formula you used and why. Switching formulas without saying so makes a forecast improve on paper.
- Show a range. Report the typical forecast as the headline, with the best and worst cases beside it.
- Update the bottom-up ETC when the work changes. A bottom-up estimate goes stale as fast as any other.
- Keep management reserve separate. BAC does not include management reserve, so an EAC above BAC does not automatically mean the reserve should be spent. Releasing it needs a decision.
- Flag the confidence level. A forecast at 15% complete is much less reliable than at 60%.
Summary table
| Term | Meaning | Formula |
|---|---|---|
| EAC | Forecast total cost | Depends on the assumption |
| ETC | Forecast cost of remaining work | `EAC - AC` |
| VAC | Forecast over or under budget | `BAC - EAC` |
| TCPI | Efficiency needed on remaining work | `(BAC - EV) / (target - AC)` |
Exercise
A project has BAC = 200,000, EV = 80,000, AC = 100,000, and PV = 90,000. The overrun was caused by a supplier price error that has been corrected, so the remaining work should cost what was budgeted. (a) Which EAC formula applies, and what are EAC, ETC, and VAC? (b) What would EAC be if the cause were systemic instead?
Show answer
(a) Use the atypical formula: EAC = AC + (BAC - EV) = 100,000 + (200,000 - 80,000) = 220,000. ETC = EAC - AC = 120,000. VAC = BAC - EAC = -20,000. (b) CPI = 80,000 / 100,000 = 0.80, so EAC = BAC / CPI = 200,000 / 0.80 = 250,000, which gives ETC = 150,000 and VAC = -50,000.
Exercise
A project reports SPI = 1.0 in its final month, yet the delivery date was missed by three months. Explain why SPI is misleading here, and name a better way to forecast the finish date.
Show answer
SPI is a ratio of earned value to planned value in money terms. When all the work is complete, EV equals PV (both equal BAC), so SPI becomes 1.0 regardless of how late the work finished. The metric loses its power as the project nears its end. A better forecast uses the critical path or milestone slippage, which measures the delay in time instead of in money.
Exercise
For the project in the first exercise, compute the TCPI needed to finish within the original BAC, and say what it implies.
Show answer
TCPI = (BAC - EV) / (BAC - AC) = (200,000 - 80,000) / (200,000 - 100,000) = 120,000 / 100,000 = 1.20. The team has so far achieved CPI = 0.80, so it would need to be 50% more efficient than its past performance (1.20 against 0.80) on all the remaining work. That is unlikely, so the original budget is probably not achievable without a change in scope, resources, or method.