Fix a baseline to measure against
This chapter assumes you know basic project vocabulary (scope, schedule, budget, task), can read a task list or Gantt chart, and are comfortable with simple ratios. It also assumes you have seen a work breakdown structure (WBS), the hierarchy of deliverables and work packages that the previous chapter built. Here you turn that breakdown into numbers and dates that you can hold the project against.
What a baseline is
A baseline is the approved version of the plan, frozen at a point in time. You compare actual results with it. Without one, "behind schedule" and "over budget" have no meaning, because the plan keeps moving to match what happened.
A baseline is not the same as a current plan:
- The baseline is the approved reference. It changes only through formal change control.
- The current plan, or forecast, is your latest best estimate of how the work will go. It changes whenever you learn something.
Variance is the gap between the two. If you edit the baseline every time reality drifts, the gap disappears and so does your early warning.
The three baselines
A project baseline has three parts, one per constraint you track.
| Baseline | What it fixes | Typical contents |
|---|---|---|
| Scope baseline | What is in and out of the project | Approved scope statement, WBS, WBS dictionary |
| Schedule baseline | When the work happens | Approved start and finish dates for work packages, milestones, dependencies |
| Cost baseline | How much it is allowed to cost, and when the money is spent | Time-phased budget for each work package, plus contingency reserve |
The WBS dictionary is the document that describes each work package. It records the deliverable, the acceptance criteria, the owner, the assumptions, and the budget. The scope baseline needs it because a bare WBS names the work but does not say what "done" means. Acceptance criteria written here are what the progress rules in the next chapter depend on.
The performance measurement baseline
When you use earned value, you combine the three baselines into one integrated reference, called the performance measurement baseline (PMB). Each work package in it has a defined scope, a schedule window, and a budget spread over that window. Later chapters compute planned value (PV) from this baseline, so any error in it carries into every variance, index, and forecast you produce.
Build the time-phased budget
A budget total alone is not enough. You need to know how much work and money you expect in each period. That is the time-phased budget, and its running total is the PV curve (sometimes called the S-curve).
The steps are:
- List the work packages, the lowest level of the WBS.
- Give each one a budget and a start and finish period.
- Spread each budget across its window. An even spread is the simplest rule. Use a different spread only if the work really is front-loaded or back-loaded.
- Sum the periods, then take a running total.
- Check that the final running total equals the sum of the work package budgets. That total is the budget at completion (BAC).
The script below does this for a ten-month project with four work packages.
packages = [
{"id": "1.1", "name": "Requirements", "budget": 12000, "start": 1, "finish": 2},
{"id": "1.2", "name": "Design", "budget": 18000, "start": 2, "finish": 4},
{"id": "1.3", "name": "Build", "budget": 50000, "start": 4, "finish": 8},
{"id": "1.4", "name": "Test and release", "budget": 20000, "start": 9, "finish": 10},
]
def monthly_plan(packages, months):
"""Spread each work package budget evenly over its start..finish months."""
plan = [0.0] * months
for p in packages:
length = p["finish"] - p["start"] + 1
per_month = p["budget"] / length
for month in range(p["start"], p["finish"] + 1):
plan[month - 1] += per_month
return plan
months = 10
plan = monthly_plan(packages, months)
bac = sum(p["budget"] for p in packages)
cumulative = 0.0
for month, amount in enumerate(plan, start=1):
cumulative += amount
print(f"month {month}: planned={amount:.0f}, cumulative PV={cumulative:.0f}")
assert round(cumulative) == bac, "time-phased plan does not add up to BAC"
print(f"BAC = {bac}")
# month 1: planned=6000, cumulative PV=6000
# month 2: planned=12000, cumulative PV=18000
# month 3: planned=6000, cumulative PV=24000
# month 4: planned=16000, cumulative PV=40000
# month 5: planned=10000, cumulative PV=50000
# month 6: planned=10000, cumulative PV=60000
# month 7: planned=10000, cumulative PV=70000
# month 8: planned=10000, cumulative PV=80000
# month 9: planned=10000, cumulative PV=90000
# month 10: planned=10000, cumulative PV=100000
# BAC = 100000Notice that month 2 and month 4 are peaks. Two work packages overlap in each, so the plan asks the team for more effort in those months. The time-phased view makes overlap and resource spikes visible before work starts. If the peaks are unrealistic, fix them now, because after approval every change is a formal baseline change.
The assert is a small integrity check. A baseline whose periods do not sum to its total is a common defect, usually caused by editing one work package without updating the schedule or the reverse.
Reserves: what belongs inside the baseline
Reserves are budget held back for uncertainty. They come in two kinds, and they are treated differently.
- Contingency reserve covers identified risks, the "known unknowns". It is part of the cost baseline, so the team can plan against it.
- Management reserve covers unidentified problems, the "unknown unknowns". It sits outside the cost baseline. Using it needs sponsor or management approval and then a baseline change.
The project budget is the cost baseline plus management reserve. This distinction matters because reserve placement changes your numbers. If you bury contingency in each work package, every task looks over-budgeted and padding goes unnoticed. If you hide all uncertainty in management reserve, the baseline looks tight and the first risk event creates a "variance" that was in fact anticipated. Keep contingency visible and tied to named risks.
Organizations differ in how they handle this, and some include schedule contingency as a separate buffer in the schedule baseline. Whichever convention you use, write it down in the baseline document so every reader interprets variances the same way.
What makes a baseline usable
Check a draft baseline against these criteria before you approve it.
- Complete. The WBS covers 100 percent of the scope. Work missing from the WBS is work missing from the budget.
- Measurable. Every work package has a deliverable and acceptance criteria, so you can decide when it is done.
- Right-sized. Work packages are small enough to track. A common guideline is that a package should take about a reporting period or a few reporting periods, not half the project. Large packages hide trouble until it is too late.
- Owned. Each package has one accountable person who agreed to the estimate.
- Integrated. Schedule dates and budget periods come from the same work packages, not from separate spreadsheets.
- Realistic. Estimates have a stated basis, such as past projects, vendor quotes, or a three-point estimate. Padding for politics and optimism for approval both distort the later variance.
- Approved. The sponsor and key stakeholders signed it.
Freeze it: version, approve, protect
Approval turns a plan into a baseline. After that:
- Record the baseline with an identifier and date, for example "Baseline v1, approved 2026-03-02".
- Store it where everyone reads the same copy. Keep the working plan in a separate file so people can edit the forecast freely.
- Allow changes only through change control. A change request states the reason, the impact on scope, schedule, and cost, and who approved it.
- Keep every previous version. A history of baselines shows how much the project has moved from the original commitment, even when each single change looked small.
Common errors
- No baseline until trouble appears. A baseline drawn after work has started already contains the slippage. It cannot show it.
- Baseline equals the optimistic target. A plan built to win approval, with no basis of estimate, produces permanent negative variance. People then stop trusting the numbers.
- Cost and schedule baselined separately. If the budget is spread by one rule and the dates by another, PV does not match the work the schedule describes. Variances then reflect modeling mismatch, not project performance.
- Too coarse. With only five work packages for a year-long project, nothing is measurable until a package finishes. Progress then appears as jumps.
- Forgetting reserves. If contingency is spent without being recorded, the project looks on budget until it suddenly is not.
- Never rebaselining after a large approved change. If the sponsor adds a major feature and the baseline is untouched, every report afterward shows a large unexplained variance. The next chapters cover when a rebaseline is the right response.
Edge cases
Iterative and agile work. Detailed scope is not known up front, so you baseline at a coarser level. A common approach is to fix the budget, the target dates, and the release scope as a prioritized backlog. You then let the scope inside each release flex. Scope changes are tracked against that agreed boundary rather than prevented. Burndown and burnup charts, covered later, take over the role of fine-grained tracking.
Joining a project in progress. If you inherit a project with no baseline, do not invent one from the original idea. Baseline the remaining work from today: estimate what is left, set a new baseline date, and state clearly that variance is measured only from that date. Note the work already done as the starting point.
Rolling-wave planning. When far-future work is uncertain, you detail the near term and keep later work in planning packages, which are summary-level placeholders with a budget but without a task breakdown. As the horizon approaches, you split a planning package into work packages. This splitting is not a baseline change as long as the total budget and dates for the package stay the same.
Non-even spreads. A purchase of equipment is spent when the invoice is due, not evenly across the delivery period. Spread each budget according to when value is earned or cost is incurred, and say which rule you used.
Exercises
Exercise
Your Build work package slips two weeks because a supplier was late. Should you move its dates in the baseline? Explain what you should do instead.
Show answer
No. Changing the baseline hides the slip and removes the schedule variance you want to report. Leave the baseline dates unchanged, update the forecast dates, record the variance, and log a risk or issue for the supplier delay. Move the baseline only if a change request is approved through change control.
Exercise
A project has four work packages with budgets of 8,000 (months 1-2), 12,000 (months 2-4), 30,000 (months 3-6), and 10,000 (month 7). Using an even spread, what is the cumulative PV at the end of month 4, and what is BAC?
Show answer
Month 1: 4,000. Month 2: 4,000 + 4,000 = 8,000. Month 3: 4,000 + 10,000... check each package: package 2 spends 4,000 per month for months 2-4, and package 3 spends 7,500 per month for months 3-6. Cumulative through month 4 is package 1 at 8,000, package 2 at 12,000, and package 3 at two months of 7,500, which is 15,000. The total is 35,000. BAC is 8,000 + 12,000 + 30,000 + 10,000 = 60,000.
Exercise
Why is a baseline built from the optimistic target a problem even when the team works well?
Show answer
The plan assumes less effort, time, or cost than the work needs, so the team shows negative variance from the start. The variance reflects a flawed baseline rather than poor performance, so it hides real problems and erodes trust in the reports.