Sub topic 11
Change control and when to rebaseline
This chapter covers what happens when a variance cannot be fixed by working harder or by a smaller correction. You decide whether the plan itself must change, and you do it in a controlled way. It assumes you can already compute schedule and cost variance, CPI, SPI, and EAC, and that you know what a performance measurement baseline is. Those topics come from earlier chapters, and this one only applies them.
Why a baseline needs a gatekeeper
A baseline is useful only because it stays still. If anyone can edit the budget or the schedule when work slips, every variance reads zero and the plan can no longer tell you anything. Change control is the process that lets the baseline move only for a documented reason, with someone accountable for the decision.
Two failure modes sit on either side of this process.
- Silent drift. Small changes are absorbed without a record, such as a feature added in a hallway conversation or a deadline nudged a week. Each one is harmless alone. Together they erase the original plan, and you end up reporting against a baseline nobody believes.
- Rigid baseline. Real scope changes are refused or ignored, so the baseline describes a project that no longer exists. Variances then show up as permanent red, and the report stops separating new problems from old ones.
Change control sits between these two. It makes the baseline hard to change casually and possible to change legitimately.
What counts as a change
Not every deviation from the plan is a change request. Separate three things.
| Situation | Is it a change request? | Example |
|---|---|---|
| Work is taking longer or costing more than planned, with the same scope | No. It is a variance. Handle it with corrective action. | A task planned for 5 days takes 8 |
| The deliverable, its acceptance criteria, or its quality target differs from the baseline | Yes. It affects scope. | The client asks for single sign-on, which was not in the requirements |
| The approved budget, end date, or a milestone date must move | Yes, because it changes the baseline itself | A supplier delay moves the delivery milestone by three weeks |
| A fix to a defect in work you already agreed to deliver | Usually no. It is rework inside the baseline. | A report shows wrong totals and must be corrected |
A useful test is to ask whether the baseline would still describe the agreed outcome if you did nothing to it. If the answer is yes, you have a variance to manage. If the answer is no, you have a change.
The change control process
A change request moves through a fixed sequence of steps. The exact names vary between organisations, but the pattern is stable.
- Raise. Anyone can submit a request. It records what is requested, who asked, and why.
- Assess impact. The project team estimates the effect on scope, schedule, cost, quality, and risk. This is the step most often skipped, and it makes the decision informed.
- Decide. An authorised person or group (often a change control board, or CCB) approves, rejects, or defers the request. Authority is set in advance by thresholds, for example the project manager approves changes under 2% of budget and the sponsor approves anything larger.
- Implement. If approved, the baseline is updated and the new work is added to the plan.
- Communicate and log. Stakeholders are told, and the change log is updated.
Rejected and deferred requests belong in the log too. They show how much demand for change the project is absorbing, and they stop the same request from coming back unnoticed.
Incorporating an approved change
When a change is approved, the baseline moves by the amount of the change and no more. If a request adds 12,000 to the budget, the budget at completion (BAC) rises by 12,000. The planned value curve gains the new work at the dates it will be done. Earned value already recorded for existing work does not change, and the actual cost already spent does not change either.
This is the key difference from a rebaseline, covered below. The original baseline is kept as history, and the new baseline is the original plus each approved change.
The following script keeps a small change log, computes the current BAC from approved changes only, and reforecasts. It reuses the project from the earlier earned value chapter: EV of 40,000 and AC of 45,000.
original_bac = 100000
changes = [
("CR-1", 12000, "approved"),
("CR-2", 8000, "rejected"),
("CR-3", 5000, "pending"),
]
ev, ac = 40000, 45000
approved = sum(cost for _, cost, status in changes if status == "approved")
pending = sum(cost for _, cost, status in changes if status == "pending")
current_bac = original_bac + approved
cpi = ev / ac
eac = current_bac / cpi
print(f"Approved changes: {approved}")
print(f"Current BAC: {current_bac}")
print(f"Growth vs original: {approved / original_bac:.0%}")
print(f"CPI: {cpi:.2f}")
print(f"EAC: {eac:.0f}")
print(f"Pending exposure: {pending}")
# Approved changes: 12000
# Current BAC: 112000
# Growth vs original: 12%
# CPI: 0.89
# EAC: 126000
# Pending exposure: 5000Three points about this output matter for reporting.
- Only approved changes enter the budget. The rejected 8,000 never touches it, and the pending 5,000 is reported as exposure, not added.
- EAC of 126,000 is measured against the current BAC of 112,000, so the projected overrun is 14,000. Measured against the original 100,000, the project would look 26,000 over. Good reports show both numbers so the reader can see how much of the gap comes from approved scope growth and how much from poor cost performance.
- The 12% growth figure is a health indicator in its own right. A project whose approved changes keep adding up has a scope-control problem even if every single change was properly approved.
What a rebaseline is
A rebaseline replaces the performance measurement baseline with a new one, so that the new plan becomes the reference for variance. It differs from incorporating a single change in two ways.
- Scale. It resets the whole schedule or cost baseline, not just one piece of it.
- Effect on variance. Past variances are typically cleared and measurement restarts from a new starting point. Cumulative CPI and SPI are either reset or reported from the rebaseline date.
That second effect is the risk. A rebaseline can wipe out evidence of poor performance. If a project is 30% over budget and the budget is simply reset to match, the variance disappears but the money is still gone.
For this reason, a rebaseline needs stricter approval than an ordinary change, and the original baseline must be kept in the record so that you can still report variance to the original if asked.
When to rebaseline
Rebaseline only when the existing baseline can no longer serve as a meaningful measure. Typical triggers are these.
- The baseline is no longer achievable for reasons outside the team's control. A major external event, such as a regulation change, a lost contract input, or a funding cut, makes the original plan irrelevant.
- Accumulated approved changes have altered the project beyond recognition. The change log is so long that the original plan describes a different project.
- The sponsor has formally changed the objective. The goal itself is different.
- The variance is so large that every future report will be red regardless of what the team does. Measuring against an impossible baseline gives managers no signal, so a reset is justified, provided it is approved and the reason is recorded.
Do not rebaseline in these situations.
- To hide a variance. If the only reason is that the project is behind or over budget and nothing about the scope or conditions changed, the right response is corrective action or an escalation.
- Because a milestone was missed once. One slipped milestone is a variance. Move the date through a change request if it is justified.
- Repeatedly. Each rebaseline weakens the credibility of the next one. A project that rebaselines every quarter is not tracking against a plan at all.
Choosing between corrective action, change, and rebaseline
The decision can be structured as a sequence of questions. Start with the least disruptive option and move up only when it cannot work.
| Question | If yes | If no |
|---|---|---|
| Can the team recover within the existing baseline by changing how work is done? | Corrective action. No baseline change. | Next question |
| Does the fix require changing scope, end date, or budget of a specific part of the plan? | Change request, then incorporate it if approved | Next question |
| Is the baseline as a whole no longer a valid measure of the agreed outcome? | Rebaseline, with sponsor approval and the original kept | Escalate. The problem is outside the project's control. |
Corrective action was covered in the previous chapter. The point here is that corrective action always comes first. It costs nothing in credibility, while each change request and rebaseline costs some.
Practical rules for a defensible change process
- Write the thresholds before the first request arrives. Decide who can approve what, by cost, by schedule impact, and by effect on the critical path. Arguments about authority are much harder once a request is on the table.
- Do not start work before approval. Work done on an unapproved change spends actual cost with no matching budget, which produces a cost variance that was created by the process itself.
- Assess schedule impact on the critical path. A change that adds work off the critical path may use float and leave the end date alone. A change on the critical path moves it.
- Track cumulative change as a metric. Report approved changes as a percentage of the original BAC, as in the script above, in every status report.
- Keep versions. Label baselines as Baseline 0 (original), Baseline 1, and so on, with the date and the approving person.
- Update the risk register. Many changes introduce new risks. An approved change with no risk review often becomes next month's issue.
Iterative projects
Teams working in sprints handle change differently, but the logic is the same. The product backlog can be reprioritised freely, so adding and removing items does not need formal approval. What still needs control is the commitment: the scope of the current sprint, and any fixed date or budget promised to the sponsor.
On a burnup chart, an approved scope change appears as a step in the scope line. That is the right way to show it, because the chart then separates the team's delivery rate from growth in the target. If the scope line rises without a recorded decision, you have silent drift, and the chart makes it visible.
Common mistakes
- Treating a variance as a change and moving the baseline to match actual results.
- Approving a change without an impact assessment, then discovering it affects the critical path.
- Adding pending changes into the budget before they are approved.
- Rebaselining without keeping the original, so that the project's true history is lost.
- Letting the same person raise, assess, and approve a change that affects their own deliverable.
Exercise
A project has an original BAC of 200,000. Three change requests exist: CR-1 for 10,000 is approved, CR-2 for 6,000 is pending, and CR-3 for 4,000 is rejected. EV is 80,000 and AC is 100,000. What are the current BAC, the growth of the budget relative to the original, and the EAC using the CPI method?
Show answer
Only approved changes count, so current BAC = 200,000 + 10,000 = 210,000. Growth = 10,000 / 200,000 = 5%. CPI = 80,000 / 100,000 = 0.80. EAC = 210,000 / 0.80 = 262,500. The pending 6,000 is reported as exposure and the rejected 4,000 is ignored.
Exercise
A project is 25% over budget because the team underestimated the work. The scope and the conditions have not changed. The project manager proposes rebaselining so the report turns green. Is this appropriate? What should happen instead?
Show answer
No. Nothing about the scope or external conditions changed, so the overrun is a cost variance, not a baseline problem. Rebaselining would hide the overrun without recovering any money. The right path is to analyse the cause, apply corrective action, update the EAC, and escalate the forecast to the sponsor. If the sponsor decides to fund the gap, that is approved through a change request, and the original baseline stays on record.
Exercise
Name two things that should be kept when a baseline is changed, and explain why each matters.
Show answer
First, the original baseline, so that cumulative variance to the original plan can still be reported and audited. Second, the change log with decisions, approvers, and dates, so that anyone can trace how the current baseline was reached and see how much of the difference comes from approved scope growth.