Sub topic 8
Running the event week day by day
This chapter assumes you have read the earlier chapters. You should know the charter format, the team roles, and the baseline measures (lead time, cycle time, takt time, process cycle efficiency). Here you will learn how to run the week itself: what happens each day, what the facilitator watches for, and what usually goes wrong.
The shape of the week
A kaizen event usually runs three to five days. This chapter uses a four-day event with a report-out on Thursday afternoon, matching the sample charter ("Monday to Thursday"). Each day has one job:
| Day | Main job | Output |
|---|---|---|
| Monday | Understand the current state | Observed process map, confirmed baseline, list of problems |
| Tuesday | Find root causes and design countermeasures | Root-cause analysis, ranked countermeasures, trial plan |
| Wednesday | Test changes in small trials | Trial results, the chosen method, draft standard work |
| Thursday | Standardize and report | Standard work, follow-up plan, report-out |
The sequence matters. Teams that skip to solutions on Monday usually fix symptoms. Teams that analyze until Wednesday have no time to test.
The facilitator's job during the week
The facilitator owns the process of the week, not its content. The team members know the work. The facilitator keeps the team on the agenda, asks questions, and protects the scope in the charter. Four habits help:
- Time-box every activity. Say "we have 45 minutes for the fishbone" and keep to it.
- Keep a parking lot. Put good ideas that fall outside the charter on a flip chart, such as credit approval in the sample charter. Give the list to the sponsor on Thursday.
- Make work visible. Use wall charts, sticky notes, and a trial board so everyone sees progress.
- Check the sponsor's availability. Decisions that need approval, such as a small budget or a change to a form, should be answered the same day.
Monday: observe the current state
Start with a 30 to 60 minute kickoff. The sponsor explains why the process was chosen. The facilitator reviews the charter line by line: problem statement, scope start and end, exclusions, and goals with baselines. Ask the team whether anything is unclear. Confirm the ground rules, such as "everyone's observation counts" and "attack the process, not people."
Then go to the place where the work happens, often called the gemba. This is the Japanese word for "the actual place." Watching real work gives better information than describing it from memory in a meeting room.
Walk the process
Split the team into pairs. Each pair follows one item through the process from the start point to the end point in the charter. For the order-entry example, that means from "order received in the shared inbox" to "confirmation sent to the customer." Each pair records:
- Each step, who does it, and how long it takes.
- Waiting time between steps, and the reason for it.
- Rework, errors, and handoffs.
- Any step that is done differently by different people.
Use a stopwatch for cycle times and clock times for queues. Do not average from memory. Compare what the pairs saw. If one person takes 3 minutes on a step and another takes 15, that is a finding, not an error to resolve.
Build the current-state map
By the afternoon, combine the observations into one map on the wall. Mark each step as value-added (the customer would pay for it), non-value-added but necessary, or pure waste. Then check the baseline against what you saw. The check can use the same calculations you used in pre-work:
# Compare the observed process with the charter baseline
available_minutes_per_day = 450
daily_demand_units = 90
takt_minutes = available_minutes_per_day / daily_demand_units
print(f"Takt time: {takt_minutes:.1f} minutes per unit")
value_added_minutes = 12
lead_time_minutes = 240
pce = value_added_minutes / lead_time_minutes
print(f"Process cycle efficiency: {pce:.0%}")
# Observed on Monday: 14 minutes of value-added work in a 250-minute lead time
observed_pce = 14 / 250
print(f"Observed PCE: {observed_pce:.1%}")If the observed numbers differ widely from the baseline, find out why. Perhaps the baseline came from a different week, or the data source was wrong. Agree on one set of numbers before moving on, and note the difference for the report-out.
End Monday by listing problems on sticky notes and grouping them. Do not solve them yet.
Tuesday: find causes and design countermeasures
Open the day with a short review of Monday's map. Then pick the two or three problems that most affect the goals in the charter. For the sample event, those are long waits before confirmation and the status-inquiry calls that follow.
Root cause analysis
For each chosen problem, run two tools together:
- A fishbone diagram (also called a cause-and-effect or Ishikawa diagram) sorts possible causes into categories such as people, method, materials, machines, measurement, and environment. It shows breadth.
- 5 Whys follows one chain of causes downward by asking "why?" until you reach a cause the team can act on. It shows depth.
Use the fishbone first to get a wide list, then run 5 Whys on the most likely branches. For example:
- Why do orders wait so long? Because they sit in the shared inbox.
- Why do they sit there? Because no one is assigned to check it.
- Why is no one assigned? Because checking depends on who is free.
- Why does it depend on who is free? Because there is no schedule or visual signal.
- Why is there no signal? Because the inbox was never treated as a process with an owner.
A good root cause is something the team controls and can verify. "People are careless" is not one. Ask how the process allowed the error.
Design countermeasures
A countermeasure is a change that targets a root cause. Generate many ideas, then rank them by two questions: how much will this move the goal metric, and how easily can we try it this week? Prefer simple changes that cost little. A rotating inbox owner and a color-coded status board often beat a new software tool. Choose a few, write a trial plan for each (what we change, how we measure, what success looks like), and have the sponsor approve anything outside the team's authority before the day ends.
Wednesday: test in small trials
Wednesday is for evidence. Run each countermeasure on a small scale: one shift, a few orders, one workstation. Measure the same things you measured on Monday, using the same method.
A good trial record has the countermeasure, the sample size, the measured result, and what the team learned. Change one thing at a time where you can. If you change three things together and the result improves, you will not know which change helped.
Expect some trials to fail. A failed trial that is understood is a useful result. Return to Tuesday's list, adjust the countermeasure, and test again. Stop when you have a method that meets or approaches the goal and that the people who do the work agree is usable. Do not keep a method only because the team built it.
Start drafting the standard work document in the afternoon, using the method as trialed.
Thursday: standardize and report out
Spend the morning on three tasks:
- Write the standard work. Record the steps in order, who does them, the time for each, and the key points for quality and safety. Use photos or simple diagrams. Have someone who was not on the team read it and try to follow it.
- Plan the follow-up. List open actions with an owner and due date each. Schedule the 30, 60, and 90 day reviews.
- Prepare the report-out. A good presentation covers the problem, the baseline, what the team learned, what changed, the results of the trials, and the remaining actions. Let team members present, not only the leader.
Keep a short rehearsal in the schedule. The report-out itself is covered in a later chapter.
Common problems during the week
| Problem | Sign | Response |
|---|---|---|
| Scope creep | New topics appear each hour | Check the charter; move items to the parking lot |
| Jumping to solutions | Ideas appear on Monday | Ask "what data supports that?" and return to observation |
| One voice dominates | Quiet members stop contributing | Use silent sticky-note writing, then share round-robin |
| Team pulled away | Members leave for their regular work | Get the sponsor to clear schedules before the week |
| Trial skipped | "We know this will work" | Require at least a small test with data |
| Unclear authority | Decisions stall | Settle approvals with the sponsor on Monday |
Exercises
Exercise
On Monday afternoon, your team's observed lead time is 250 minutes. The charter baseline says 240 minutes. Value-added time observed is 14 minutes. What is the observed process cycle efficiency, and what should the team do about the 10-minute difference?
Show answer
Observed PCE is 14 / 250 = 5.6%. The difference from the baseline (12 / 240 = 5%) is small, but the team should find out where each number came from, agree on one set of numbers, and note the difference for the report-out.
Exercise
A team member proposes buying a workflow software tool on Monday morning, before the walk of the process. What should the facilitator do, and why?
Show answer
Put the idea in the parking lot and continue with observation. Monday is for understanding the current state. A solution chosen before observation and root cause analysis may fix a symptom, and it cannot be tested in the time left. The idea can return on Tuesday as a candidate countermeasure if the root cause analysis supports it.
Exercise
On Wednesday, a team tests three changes at once in one trial and lead time drops by 40 minutes. Why is this a weak result, and how would you improve the trial design?
Show answer
The team cannot tell which change caused the improvement, or whether one change hurt while another helped. Test the changes one at a time where possible (or in separate small trials), measure each against the Monday baseline, and keep only those that show a result.