Choosing the right process and scope
This chapter assumes you know the basic types of waste, can read a simple process flow, and can do arithmetic on time and counts. It also assumes you have seen the idea of a kaizen event: a short workshop, usually three to five days, that changes one process and measures the result. The work here happens before the charter. You decide which process to improve and where its edges are.
Why selection decides the outcome
Most first events that fail were doomed before Monday. The team picked a process that was too large, too political, or too poorly understood to improve in a week. A well-chosen process makes the rest of the event much easier. A poorly chosen one cannot be rescued by good facilitation.
Selection answers two questions:
- Which process should get this event?
- Where does that process start and end for this event?
The first is about fit and value. The second is about size. You need both answers before you can write the charter in the next chapter.
What makes a good first-event process
A first event should build trust in the method. Choose a process that is likely to produce a visible, measurable win. These criteria help.
- It is repeatable. The process runs often enough that the team can observe it several times during the week. Order entry that runs 90 times a day is a better candidate than a process that runs twice a month.
- It is observable. People can walk the process, see the work, and time the steps. Work that happens inside one person's head is hard to map.
- It has a clear pain. Customers, staff, or managers already complain about it. Existing pain gives the team energy and gives leaders a reason to support changes.
- It is measurable. Lead time, error counts, or call volume can be collected before the event and again afterward. If you cannot measure it, you cannot show a result.
- It is within the team's control. The people in the room can change most of the steps. If the main cause sits in another department, an outside vendor, or a software release cycle, a one-week event cannot fix it.
- It has a willing owner. A manager who owns the process wants the change and will release staff to attend.
- It is not in crisis. A process that is on fire needs firefighting, not a workshop.
Waste knowledge from the previous chapter helps here. Look for processes with visible waiting, rework, searching, or handoffs. These usually show a large gap between value-added time and total lead time, which means there is room to improve.
Scoring candidates
If you have several candidates, compare them with a simple scoring table instead of choosing by volume of complaint. Rate each criterion from 1 (poor) to 5 (strong). Add the scores.
| Candidate process | Pain | Measurable | Within team control | Observable | Total |
|---|---|---|---|---|---|
| Customer order entry | 5 | 5 | 4 | 5 | 19 |
| Month-end close | 4 | 3 | 2 | 2 | 11 |
| New-vendor onboarding | 3 | 2 | 2 | 3 | 10 |
In this example order entry wins clearly. Month-end close hurts, but it depends on several departments and cannot be seen in a single place. The scores are a conversation aid. If the top two candidates are close, discuss why before you decide.
You can run the same comparison in code if you keep candidates in a spreadsheet export.
candidates = {
"Customer order entry": {"pain": 5, "measurable": 5, "control": 4, "observable": 5},
"Month-end close": {"pain": 4, "measurable": 3, "control": 2, "observable": 2},
"New-vendor onboarding": {"pain": 3, "measurable": 2, "control": 2, "observable": 3},
}
totals = {name: sum(scores.values()) for name, scores in candidates.items()}
for name, total in sorted(totals.items(), key=lambda item: item[1], reverse=True):
print(f"{name}: {total}")The script prints the processes from highest to lowest total.
Event or something else?
A kaizen event is not the right tool for every problem. Use the questions below to check the fit.
| Situation | Better approach |
|---|---|
| The cause is known and the fix is small | Make the change directly, as part of daily improvement |
| The process spans many departments and needs new systems | A larger project with its own plan and budget |
| The cause is unknown and the data is thin | Collect data first, then decide |
| The process is stable but slow, with visible waste, and the fix is within the team's reach | Kaizen event |
If a problem needs a purchase, a software build, or a policy approval that takes weeks, the event cannot finish it. You can still hold an event on the part of the process the team controls. Record the larger issue as a separate follow-up item.
Setting the scope
Scope is the boundary of the event. It says where the process starts, where it ends, and what is excluded. A scope that fits in one week is narrower than most people expect.
Start and end points
Choose a start point and an end point that are events you can observe, not vague phrases. "Order received in the shared inbox" is a clear start. "When the customer first thinks about ordering" is not. The charter example in this tutorial uses "Order received in the shared inbox" to "Confirmation sent to the customer." A reader can tell exactly when a unit of work enters and leaves the scope.
Out of scope
List what is excluded and say so out loud. In the charter example, credit approval and shipping are out of scope. Exclusions protect the team from drifting into neighbouring problems and protect the event from criticism that it ignored something. Each exclusion can become a candidate for a later event.
Sizing to a week
Use these checks to test whether the scope fits.
- Step count. A process with roughly 10 to 30 steps can usually be mapped in a day. Over about 50 steps, the map will eat the week.
- Variants. If the process has many versions (different products, regions, or customer types), pick one family. Mapping all variants multiplies the work.
- Observation volume. The team needs to see enough instances during the week to trust what they find. A daily process works. A process that runs weekly does not.
- Number of handoffs. Many handoffs across many teams mean many people to bring into the room. Aim for a scope the team can cover without waiting on outsiders.
- Trial opportunities. The team will test changes on Wednesday and Thursday. Make sure real work will flow through the process on those days.
Common selection errors
- Choosing the biggest pain. The largest problem is often the least suited to one week. Pick the process where a win is realistic.
- Scope creep before the event. Stakeholders add "just one more step." Each addition lengthens the map. Hold the line and log extra requests for later.
- Scoping by organization chart. A department boundary is not a process boundary. Define scope by the flow of work, not by who reports to whom.
- Starting with a solution. If a leader says "we need to install a new tool," the event is already decided. State the problem and the goal, and let the team find the countermeasures.
- No baseline data. Without numbers, the team cannot judge whether the scope is right or later prove improvement. The next chapters cover baseline measures. Confirm now that the data can be collected.
Confirming with the sponsor
Before you write the charter, review your choice with the sponsor, the manager who will back the event. Bring the scoring table, the proposed start and end points, the exclusions, and the data you expect to collect. Ask the sponsor to confirm three things: the problem matters, staff can be released for the week, and the team may change the steps inside the scope. If the sponsor cannot commit to the third, the event will stall when the team proposes changes.
Exercise
A manager proposes a first kaizen event on "the whole hiring process, from job request to the new employee's first day." The process runs about 15 times a year, involves HR, legal, IT, and facilities, and some steps take weeks because of background checks. Explain two reasons this scope is unsuitable for a one-week event, and propose a narrower scope.
Show answer
First, the process is too large and runs too rarely. With about 15 hires a year, the team cannot observe enough instances in one week, and the flow spans weeks, so trials on Wednesday and Thursday would not see real work. Second, the team does not control the process. Background checks and cross-department steps depend on outside parties, so most causes lie beyond the room. A narrower scope could be "Offer letter approved to signed offer returned" or "Job request received to posting published," whichever runs more often and sits within HR's control. Start and end points should be observable events, the other steps (background check, IT setup, facilities) should be listed as out of scope, and baseline data such as median days for the chosen segment should be confirmed before the charter is written.