Sub topic 12
Documenting Standard Work
What this chapter covers
This chapter assumes you have run the trial phase of an event. You already have a countermeasure that met its target in small tests, and you have baseline numbers to compare against. Standard work is how you turn that winning method into the way the process runs every day. Without it, the improvement lasts only as long as the people who were in the room remember it.
You will learn what standard work contains, how to capture it during the event, how to check that someone outside the team can follow it, and where first-time teams go wrong.
What standard work is
Standard work is a written description of the current best-known way to do a task. It states the steps, their order, the time each should take, and the things a person must have on hand to do the work. It is not a rigid rule that freezes the process. It is the baseline that the next improvement starts from. If there is no agreed baseline, nobody can tell whether a change is an improvement.
Standard work has three jobs:
- It lets a new or covering person do the task the same way as an experienced person.
- It makes deviations visible. When a result is bad, you can ask whether the standard was followed and whether the standard itself is wrong.
- It gives the next kaizen team a documented starting point.
The three elements
Classic standard work, as used in lean manufacturing, rests on three elements. They apply to office and service work as well.
| Element | Question it answers | Example from the order-entry event |
|---|---|---|
| Takt time | How often must a unit be completed to meet demand? | 5.0 minutes per order (450 available minutes divided by 90 orders) |
| Work sequence | In what order does one person do the steps? | Open order, check the required fields, enter, send confirmation |
| Standard work-in-process | How much unfinished work may sit between steps? | No more than 5 orders waiting in the inbox |
Takt time sets the pace the work must keep up with. The sequence says what the person does inside that pace. The standard work-in-process limit keeps queues from growing back, which is how lead time quietly returns to its old value.
Capturing standard work during the event
Start writing during the trial phase, not after it. By Thursday morning the team is tired, and a standard written from memory will leave out the details that made the trial work.
Step 1: Observe the new method being done
Have someone who was not in the trial perform the new method while a team member watches and records. Write down what the person actually does, not what the team intended. Gaps between the two show up quickly.
Step 2: Break the work into steps
Write each step as a verb phrase, such as "Check the order against the required-fields list." Keep each step to one action. If a step contains the word "and," it is probably two steps.
For each step, record:
- The time it takes, measured with a stopwatch or timestamps over several repetitions.
- Any key points, which are the things that make the step succeed or fail. A key point for "Enter the order" might be "Copy the customer number from the PO header, never from the email subject."
- The reason for the key point, so the person understands why it matters.
Step 3: Compare total time to takt
Add the step times for one person. If the total is well above takt time, the process cannot keep pace with demand using the current staffing. If it is far below, you may have capacity for other work. Neither result is wrong, but the team should know which one it has.
The following script totals recorded step times and compares them to takt. It uses the same numbers as the baseline chapter, so you can check your own data the same way.
# Compare a documented standard work sequence to takt time
takt_minutes = 450 / 90 # 5.0 minutes per order
steps = [
("Open order from shared inbox", 0.5),
("Check required-fields list", 1.0),
("Enter order in system", 2.0),
("Send confirmation", 0.5),
]
total = sum(minutes for _, minutes in steps)
print(f"Total standard work time: {total:.1f} minutes")
print(f"Takt time: {takt_minutes:.1f} minutes")
if total <= takt_minutes:
margin = takt_minutes - total
print(f"Within takt, with {margin:.1f} minutes of margin")
else:
gap = total - takt_minutes
print(f"Over takt by {gap:.1f} minutes: staffing or the method needs review")With these numbers the total is 4.0 minutes, so the sequence fits within takt with 1.0 minute of margin. That margin is useful. Real work has interruptions, and a standard with zero margin fails on the first bad day.
The standard work documents
Teams usually produce a small set of documents. Use as few as you need.
- A standard work sheet, which lists the steps, times, and key points in order. For office work this is often a one-page table.
- A work instruction or checklist for the steps that need exact detail, such as the required-fields list.
- A layout or flow sketch if the physical or system location of work changed.
- A visual aid at the point of use, such as a laminated checklist next to the workstation or a pinned template in the shared inbox.
The test for each document is whether the person doing the work will actually look at it. A 12-page procedure stored in a shared folder fails that test. A one-page sheet at the desk passes it.
Testing the standard
A standard is not finished when the team agrees on it. It is finished when someone who was not on the team can follow it and get the same result.
Pick a person who does this work but did not take part in the event. Give them only the sheet. Do not coach them. Watch where they hesitate, ask a question, or do something different from the sheet. Each of those points is a defect in the document, not in the person.
Revise and repeat until the outside person completes the work correctly within the expected time. One or two rounds is typical.
Training and approval
Once the standard passes the test, three things need to happen before the event ends or very soon after.
- The sponsor or process owner reviews and approves the standard. Approval matters because it gives the document authority. Without it, a supervisor can ignore it.
- Everyone who does the work is trained, including people on other shifts and anyone who covers absences. Training means showing the method and watching the person do it, not emailing the sheet.
- The old method is retired. Remove old templates, old forms, and old instructions. If both versions remain available, people drift back to the familiar one.
Record the training in a simple log with the name, date, and trainer. That log becomes useful at the 30-day follow-up, when you ask who actually uses the standard.
Version control and change rules
A standard needs a version number, a date, and an owner. Put these in the footer of the sheet. Tell people how to propose a change, and make it easy.
A good rule is that anyone can propose a change, but the change is tried as a small trial first and approved by the owner before the sheet is updated. That keeps the standard stable without making it untouchable. The standard should change when someone finds a better way, and that is the same idea behind kaizen.
standard_work_sheet:
process: Customer order entry
version: 1.0
date: Thursday of event week
owner: Order-entry supervisor
takt_minutes: 5.0
wip_limit_orders: 5
steps:
- step: Open order from shared inbox
minutes: 0.5
key_point: Take the oldest order first
- step: Check required-fields list
minutes: 1.0
key_point: Return incomplete orders the same hour
- step: Enter order in system
minutes: 2.0
key_point: Copy the customer number from the PO header
- step: Send confirmation
minutes: 0.5
key_point: Use the confirmation template
review: Confirm at 30, 60, and 90 daysCommon errors
- Writing the standard as the team wishes the work were done. Document what was tested. Untested ideas added at the last minute have no evidence behind them.
- Using vague steps. "Process the order correctly" cannot be followed. Name the action and the key point.
- Skipping the outside test. Team members fill gaps without noticing. Only a new reader finds them.
- Writing too much. If the sheet is long, people will not read it. Move detail into a checklist and keep the sheet to one page.
- Leaving the old method available. Retire it explicitly.
- No owner. An unowned standard decays. Name one person.
- Treating the standard as final. A standard with no route for improvement turns into a rule people resent.
Connecting to the rest of the event
The standard work sheet feeds directly into the report-out, where you show the before and after measures and the new method. It also becomes the checklist for the 30-60-90 day follow-up. At each review you ask two questions: is the standard still being followed, and is the result still holding? If the standard is followed and the result slips, the standard needs revision. If the standard is not followed, the problem is training, ownership, or fit, and the team should find out which.
Exercise
A team documents a four-step order-entry method with step times of 0.5, 1.0, 2.0, and 0.5 minutes. Daily demand is 90 orders and available time is 450 minutes. Another person on the team adds a fifth step of 1.5 minutes after the outside test. What is the new total, how does it compare to takt time, and what should the team do?
Show answer
The takt time is 450 / 90 = 5.0 minutes. The original total is 4.0 minutes. Adding 1.5 minutes gives 5.5 minutes, which is 0.5 minutes over takt, so one person cannot keep pace with demand. The team should first ask why the step was added and whether the outside test showed it is needed. If it is needed, they should look for time to remove from another step or consider a staffing change. They should not leave the sheet over takt without deciding how to handle the gap.
Exercise
Name three things that must happen after the standard work sheet is written before the event can be considered done with this step, and explain why the third matters.
Show answer
The sheet must pass a test with someone outside the team, the sponsor or process owner must approve it, and all affected staff must be trained. Retiring the old method also belongs on this list. It matters because if old templates or instructions stay available, people drift back to the familiar way, and the new standard is quietly replaced.