Sub topic 14
Following up at 30, 60, and 90 days
This chapter assumes you have run an event week, written a charter with baselines and targets, and documented standard work. It also assumes you know the basic measures from earlier chapters: lead time, takt time, and process cycle efficiency. Here you will plan what happens after the report-out, because most kaizen gains are lost in the weeks after the event, not during it.
Why follow-up is part of the event
A kaizen event ends on Thursday afternoon, but the process keeps running on Friday. The people who were not on the team return to their habits. Old forms reappear, a new work-in-progress limit gets ignored when volume spikes, and the team members go back to their regular jobs. Without a plan, the process drifts back toward its baseline.
Follow-up has three jobs:
- Confirm that the new method is still being used (adherence).
- Confirm that the results still hold (performance).
- Finish the items the team could not complete in the week (open actions).
The charter from earlier chapters already names the follow-up schedule: "Review at 30, 60, and 90 days." This chapter turns that line into a working routine.
Before you leave the room: the 30-day action list
At the end of the event, the team usually has more ideas than it could finish. Record each unfinished item on an action list. Each row needs five fields:
| Field | Example |
|---|---|
| Action | Move the order template into the shared inbox |
| Owner | One named person, not a department |
| Due date | A specific date inside 30 days |
| Evidence of completion | Template visible to all staff |
| Status | Open, in progress, done, or dropped |
Two rules keep this list useful. First, every item has exactly one owner. Shared ownership means no ownership. Second, the list is short. If it has more than about ten items, the team is carrying work that belongs in a separate project. Move the large items to a project backlog and say so openly at the report-out.
What to measure at each checkpoint
Use the same measures you recorded in the baseline. Changing the definition of a measure after the event makes the comparison meaningless. Measure the process the same way, over a comparable period, and record the result next to the baseline and the target.
The following script computes the percentage of the gap closed at each checkpoint. It uses the lead-time goal from the charter (baseline 4 hours, target 2 hours). The checkpoint values are example numbers.
baseline_hours = 4.0
target_hours = 2.0
# Median lead time measured at each follow-up review (example values)
checkpoints = {
"Day 30": 2.4,
"Day 60": 2.2,
"Day 90": 3.1,
}
planned_gain = baseline_hours - target_hours
for label, measured in checkpoints.items():
actual_gain = baseline_hours - measured
closed = actual_gain / planned_gain
status = "on target" if measured <= target_hours else "gap remains"
print(f"{label}: median {measured:.1f} h, "
f"{closed:.0%} of planned gain achieved ({status})")The output is:
Day 30: median 2.4 h, 80% of planned gain achieved (gap remains)
Day 60: median 2.2 h, 90% of planned gain achieved (gap remains)
Day 90: median 3.1 h, 45% of planned gain achieved (gap remains)The Day 90 number shows the pattern you are trying to catch: results improved, then slipped. The number alone does not say why, so each review also needs a look at the process itself.
Measuring adherence, not only results
Results can look good for the wrong reasons, and results can look bad even when the method is followed. For example, a spike in order volume can raise lead time even when everyone follows the standard work. Check both.
An adherence check is a short walk through the process, often called a process audit or a gemba walk, comparing what people do against the standard work document. Keep it simple:
- Observe at least three real cycles of the work, not a staged one.
- Compare each step to the standard work sheet.
- Note any deviation and ask why it happened. Do not blame the person.
- Decide whether the deviation shows that the standard is wrong or that the standard was not followed.
Step 4 matters. If people deviate because the standard does not fit a real situation, the standard needs revision. If they deviate because they were not trained or forgot, the fix is training and reinforcement. Treating every deviation as a discipline problem teaches staff to hide problems.
Reading results and adherence together
| Results | Adherence | Likely meaning | Response |
|---|---|---|---|
| Good | Good | The change is working | Keep monitoring, spread the method |
| Good | Poor | Gain may be luck or a different cause | Investigate before claiming success |
| Poor | Good | The countermeasure is not effective, or demand changed | Return to root cause analysis |
| Poor | Poor | The change was never really adopted | Retrain, remove obstacles, ask why |
The three reviews
Each review is a short meeting, 30 to 45 minutes, with the sponsor, the team leader, and the process owner. The facilitator may attend the first one. Use the same agenda each time so the meetings stay brief.
Day 30: stabilize
At 30 days the main question is whether the new method is in daily use. Expect problems here. The new method has met real conditions the event week never produced, such as a holiday, an absent employee, or an unusual customer order.
Cover these points:
- Close or reassign every item on the action list.
- Check that the standard work is posted where the work happens.
- Confirm that new or substitute staff have been trained on it.
- Compare the first month of data with the baseline and the target.
Day 60: confirm the trend
At 60 days one month of data exists after the stabilization period. Look at the trend, not a single point. Plot the weekly values on a run chart, which is a simple line chart of a measure over time. A single good week proves little. Several weeks in a row near the target is better evidence.
Ask whether the gain is holding without extra attention from the team. If the team must remind people every day, the change depends on effort and is fragile. Look for ways to build the method into the process itself, such as a form that cannot be submitted without a required field, or a visual signal at the workstation.
Day 90: decide and hand over
At 90 days, make a decision. There are three outcomes:
- Goal met and stable. Close the event. Hand ongoing monitoring to the process owner as part of a normal routine, such as a weekly metric board.
- Goal partly met. Decide whether a small second event or a few focused changes can close the gap, or whether the original target was unrealistic. Record the reasoning.
- Gain lost. Find out why before trying again. Repeating the same event without understanding the cause wastes the team's time.
Closing the event does not end measurement. It moves measurement from the event team to the process owner.
Tracking the follow-up in a file
A simple structured record keeps the three reviews consistent. This example extends the charter format used earlier in this tutorial.
follow_up:
event_name: Reduce order-entry lead time
reviews:
- day: 30
date: 2026-12-28
attendees: [Operations manager, Order-entry supervisor]
lead_time_median_hours: 2.4
status_calls_per_week: 14
adherence_audit: "3 of 3 observed cycles followed standard work"
open_actions: 2
decision: Continue; close remaining actions
- day: 60
date: 2027-01-27
lead_time_median_hours: null
status_calls_per_week: null
adherence_audit: null
open_actions: null
decision: null
- day: 90
date: 2027-02-26
lead_time_median_hours: null
status_calls_per_week: null
adherence_audit: null
open_actions: null
decision: nullEmpty fields are left as null until the review happens. This makes it obvious which reviews are still pending and prevents a review from being skipped quietly.
Sustaining the gain after day 90
Three practices help a result outlast the formal follow-up.
- Make the standard visible. Post the standard work and the metric at the place of work. People cannot follow a standard they cannot see.
- Build in a trigger. Assign a recurring check, such as a weekly five-minute review of the metric, to a named role. When the person changes, the role keeps the duty.
- Train every new person on the standard. Include it in onboarding. Many gains disappear when staff turn over.
Share what you learned with the sponsor too. If the event produced a better way to do something that other teams also do, note it. Spreading a proven method to similar processes is often worth more than a second event on the same process.
Common follow-up errors
- Cancelling reviews when things look fine. A good Day 30 result does not predict Day 90. Hold all three reviews.
- Changing the measure. Switching from median to average, or changing the time window, hides drift.
- Reporting only results. Without an adherence check, you cannot tell why a number moved.
- No owner for the review. If nobody is named, nobody schedules it. Put the dates in calendars at the report-out.
- Blaming people for deviations. This stops honest reporting, and honest reporting is what follow-up depends on.
- Letting the action list grow. Move large items to a project backlog.
Exercise
At the Day 60 review, the median lead time is 2.1 hours (target 2.0, baseline 4.0). The adherence audit finds that only one of three observed cycles followed the standard work, and the supervisor says she reminds staff every morning. What do you conclude, and what do you do next?
Show answer
The result is close to target, but adherence is poor and the gain depends on daily reminders, so it is fragile. This is the "Good results, poor adherence" case. Do not claim success. Ask why staff deviate: if the standard does not fit real situations, revise it; if people forget or were not trained, add training and build the method into the process (for example a required field or a visual signal) so it does not rely on reminders. Keep measuring through Day 90.
Exercise
Using the formula in this chapter, what percentage of the planned gain is achieved if the baseline is 25 status-inquiry calls per week, the target is 10, and the Day 30 measurement is 16?
Show answer
Planned gain is 25 - 10 = 15. Actual gain is 25 - 16 = 9. The share achieved is 9 / 15 = 60%.