Sub topic 13
Presenting results at the report-out
The report-out is the closing session of the event week, usually held Thursday afternoon in a three-to-five-day event. The team presents what it found, what it changed, what the numbers show, and what remains open. Leadership, the sponsor, and the people who work in the process attend.
This chapter assumes you have a charter with baselines, trial results from earlier in the week, and a documented standard work. It covers the purpose of the session, how to structure it, how to present data honestly, and the mistakes that weaken it.
What the report-out is for
A report-out does four jobs:
- It shows the sponsor and leadership what the team did against the charter goals.
- It gets decisions and resources for items the team cannot finish alone.
- It recognizes the team's work, which matters for the next event.
- It starts the follow-up clock by naming owners and dates.
It is not a status meeting and not a sales pitch. If the team treats it as a chance to defend its work, the audience will ask hard questions. If the team treats it as a clear account of results, including gaps, the audience trusts it.
Who presents and who attends
The team leader runs the session. Each team member presents one part, ideally the part they worked on. Operators from the process should present, because they own the new method after the event.
The sponsor opens with a short statement of why the event was held and closes with a response. Invite the manager of any area touched by the changes, plus anyone who must approve open items. Keep the audience to people who have a stake. A large audience encourages theater and discourages honest discussion.
A structure that works
Aim for 20 to 30 minutes of presenting and 10 to 15 minutes of discussion. Use the same order the charter used, so listeners can match results to promises.
| Section | Content | Approx. time |
|---|---|---|
| Opening | Sponsor states purpose; leader introduces the team | 2 min |
| Charter recap | Problem statement, scope, goals with baselines | 3 min |
| Current state | What the team observed, key waste found | 4 min |
| Root causes | 5 Whys and fishbone findings | 3 min |
| Changes made | Countermeasures tried, what worked and what did not | 6 min |
| Results | Before and after measures against goals | 4 min |
| Standard work | The new method, shown or demonstrated | 3 min |
| Open items and follow-up | Unfinished actions, owners, dates, 30-60-90 plan | 3 min |
| Sponsor response | Decisions, thanks, next steps | 2 min |
Presenting results honestly
The results section carries the most weight. Show each goal from the charter next to its baseline and its result, in the same units.
For the order-entry example, the table might look like this:
| Measure | Baseline | Target | Result | Status |
|---|---|---|---|---|
| Median lead time | 4 hours | 2 hours | 2.5 hours (trial days) | Partly met |
| Status-inquiry calls per week | 25 | 10 | Not yet measurable | Track at 30 days |
Separate measured results from expectations
An event week is short. Many outcomes, such as weekly call counts, cannot be measured in four days. Label each number as one of three things: measured during trials, estimated from trials, or expected later. Do not present an estimate as a result.
State the sample
A median from 12 orders on Wednesday is a small sample. Say how many cases you measured and over what period. If the trial day was unusually quiet, say so. Listeners who spot an unstated weakness will doubt everything else.
Use the same method before and after
Compare like with like. If the baseline came from timestamps over four weeks, do not compare it with a stopwatch reading from one afternoon. If the method differs, say so and explain the effect.
Compute derived measures the same way
If you report takt time or process cycle efficiency (PCE), use the same formula as the baseline. The script below recalculates both from before and after numbers so the comparison is consistent.
# Takt time: available work time divided by customer demand
available_minutes_per_day = 450 # 480-minute shift minus 30 minutes of breaks
daily_demand_units = 90
takt_minutes = available_minutes_per_day / daily_demand_units
print(f"Takt time: {takt_minutes:.1f} minutes per unit")
# Process cycle efficiency: value-added time divided by total lead time
value_added_minutes = 12
lead_time_before = 240
lead_time_after = 150
pce_before = value_added_minutes / lead_time_before
pce_after = value_added_minutes / lead_time_after
print(f"PCE before: {pce_before:.0%}")
print(f"PCE after: {pce_after:.0%}")The output is a takt time of 5.0 minutes per unit, PCE before of 5%, and PCE after of 8%. Notice that PCE improved only because lead time fell. The value-added time did not change. That is a typical pattern, because most event gains come from removing waiting and rework, not from speeding up the value-added steps.
Show the work, not only the numbers
People remember a demonstration better than a chart. Where possible:
- Show the old and new process maps side by side, with removed steps marked.
- Walk through the new method at the workplace, or play a short recording of a trial.
- Display the standard work document and say where it will be posted.
- Include one or two photos or examples of waste found, such as a pile of orders waiting for a signature.
Keep slides plain. A report-out with ten dense slides loses the room. Use one idea per slide and put detail in an appendix.
Handling open items
Almost every first event ends with unfinished work. Do not hide it. List each open item with an owner, a due date, and any needed approval.
A simple action log works:
open_items:
- action: Move the shared-inbox rule to the new sort order
owner: IT support analyst
due: 14 days
needs_approval_from: Operations manager
- action: Train the second-shift team on the new method
owner: Order-entry supervisor
due: 7 days
needs_approval_from: none
- action: Collect status-inquiry call counts weekly
owner: Customer service lead
due: 30 days
needs_approval_from: none
follow_up_reviews: 30, 60, and 90 daysAsk for decisions during the session. If the team needs a budget item approved, the sponsor can decide in the room. A request deferred to "later" often disappears.
Handling questions and pushback
Expect three kinds of questions.
- Challenges to the data. Answer with the method and sample size. If you do not know, say so and add a follow-up action.
- "Why not do X?" Explain which options were considered and why the team chose differently. The fishbone and trial notes are the evidence.
- Concerns from other departments. Record them as open items. Do not argue the point in front of leadership.
Say plainly what did not work. A countermeasure that failed in a trial and was dropped shows the team tested its ideas.
Common mistakes
- Reporting activity instead of results. "We held five brainstorming sessions" is not a result.
- Overclaiming. A four-day trial does not prove a permanent 50 percent gain.
- Leaving out the baseline. Without it, an "after" number means nothing.
- Presenting only the leader's view. The operators should speak.
- Skipping the owners and dates. Without them, follow-up reviews have nothing to check.
- Running long. Cutting the discussion short ends the commitment-making part of the session.
After the session
Within one or two days, send the sponsor and attendees a short summary containing the results table, the action log, and the dates of the 30-60-90 day reviews. Post the standard work at the workplace. The report-out marks the start of sustaining the change, and the follow-up reviews check whether it lasts.
Exercise
Your team's trial on Wednesday cut median lead time from 4 hours to 2.5 hours across 12 orders. The charter goal was 2 hours, and the weekly call-count goal cannot be measured yet. How should you present these two goals at the report-out, and what should you avoid doing?
Show answer
Show the lead-time goal as partly met: baseline 4 hours, target 2 hours, trial result 2.5 hours, based on 12 orders on one day. Label the number as a trial measurement, not a permanent result, and list an action to keep measuring. Show the call-count goal as "not yet measurable," with a baseline of 25, a target of 10, an owner, and a 30-day check. Avoid changing the 2-hour target to 2.5 hours, avoid presenting the trial number as a lasting gain, and avoid estimating the call count without labeling it as an estimate.
Exercise
A team reports that PCE rose from 5% to 8%, with 12 minutes of value-added time and lead time falling from 240 to 150 minutes. A manager asks whether operators now work faster. What is the correct answer, and why?
Show answer
No. Value-added time stayed at 12 minutes. PCE rose because lead time fell from 240 to 150 minutes (12/240 = 5%, 12/150 = 8%). The gain came from removing waiting, rework, or other non-value-added time, not from faster work on the value-added steps.