Sub topic 6
Measuring the current state
This chapter assumes you have a written charter (see the previous chapter) and can do basic arithmetic on times and counts. You also need to read a simple flowchart. By the end you will be able to collect baseline measures, build a current-state map, and avoid the errors that make baselines unusable.
Why the baseline matters
A kaizen event claims that a process got better. That claim only holds if you know where the process started. The baseline is the set of measures you record before changes begin. At the report-out and at the 30-60-90 day reviews, you compare new numbers against it.
Without a baseline, the team ends up arguing from memory. Someone says "orders used to take forever," and someone else says "it was never that bad." A baseline replaces that argument with data.
The charter already names the goals and their starting values. The charter's baseline numbers are often estimates. Measuring the current state means checking them against what the process really does.
The core measures
Learn these five measures and their relationships.
| Measure | Definition | Question it answers |
|---|---|---|
| Lead time | Elapsed time from when one item enters the process to when it leaves | How long does the customer wait? |
| Cycle time | Time one person or step spends working on one item | How long does one step take? |
| Takt time | Available work time divided by customer demand | How often must we finish one unit to keep up? |
| Process cycle efficiency (PCE) | Value-added time divided by total lead time | How much of the wait is real work? |
| Quality rate | Share of items finished without rework or correction | How often is the work right the first time? |
Lead time and cycle time are easy to mix up. Lead time includes the waiting between steps. Cycle time covers only the work inside a step. In most office and shop processes, waiting is most of the lead time.
Takt time is a demand number, not a measurement of the process. It tells you the pace the customer requires. You compare each step's cycle time to the takt time. A step slower than takt is a bottleneck.
Worked calculation
Suppose a shift has 480 minutes, with 30 minutes of breaks. Customers order 90 units per day. Takt time is (480 − 30) / 90 = 5.0 minutes per unit. Suppose an order spends 12 minutes in value-added work during a 240-minute lead time. PCE is 12 / 240 = 5%.
A PCE of 5% is not unusual for a process nobody has examined. It means 95% of the elapsed time is waiting, rework, or other non-value-added activity.
import statistics
# Observed lead times in minutes for 10 orders (receipt to confirmation)
lead_times = [180, 210, 240, 95, 600, 225, 250, 230, 300, 205]
# Takt time: available work time divided by customer demand
available_minutes_per_day = 450
daily_demand_units = 90
takt = available_minutes_per_day / daily_demand_units
# Process cycle efficiency, using the median lead time
value_added_minutes = 12
median_lead = statistics.median(lead_times)
pce = value_added_minutes / median_lead
print(f"Orders measured: {len(lead_times)}")
print(f"Mean lead time: {statistics.mean(lead_times):.0f} min")
print(f"Median lead time: {median_lead:.0f} min")
print(f"Slowest order: {max(lead_times)} min")
print(f"Takt time: {takt:.1f} min per unit")
print(f"PCE (median): {pce:.1%}")The output shows a mean of 253 minutes and a median of 227.5 minutes. The one 600-minute order pulls the mean up. This is why the next section recommends reporting the median and the range.
Report a spread, not one number
A single average hides what customers feel. Record at least these for each measure:
- The median, which a few extreme items do not distort.
- The fastest and slowest values, or the 10th and 90th percentiles if you have enough data.
- The sample size, so readers know how much to trust the numbers.
If the median lead time is 4 hours but one order in ten takes two days, the team has two problems: a slow typical case and an unpredictable worst case. A single average would show neither.
Building the current-state map
The current-state map is a diagram of the process as it runs today. It is not the process as the procedure document says it should run. Build it by walking the process, not by asking people to describe it in a meeting. This walk is called going to the gemba, the place where the work happens.
For each step, record:
- The step name and who performs it.
- Cycle time for one item.
- Wait time before the step starts.
- The quality rate, meaning how often the item comes back for correction.
- The queue size, meaning how many items sit waiting.
Then mark each step as value-added or not. A step is value-added when the customer would pay for it, it changes the item toward what the customer wants, and it is done right the first time. Checking, re-keying data, and waiting are not.
In this map the cycle times add up to 12 minutes, and the waits add up to 225 minutes. That is where the 240-minute lead time and the 5% PCE come from. The longest wait, 120 minutes before data entry, is the first place the team will look during root cause analysis.
How to collect the data
Pick a method that matches the size of the process.
- Timestamps from a system. If orders carry a received time and a confirmed time, export them. This gives many items cheaply. Check that the timestamps mean what you think they mean.
- Tally sheet at each step. A simple paper form at each step where people write the item number and the time in and out. Use this when the system does not capture the information.
- Stopwatch observation. A team member watches an item and times each step. Use it for cycle times, and do enough repetitions to see the variation.
- Follow one item. Attach a note to a real item and record its path. This reveals loops and hand-offs that no one mentioned.
Aim for at least 20 to 30 items when you can. If the process is rare or slow, fewer items are fine, but state the sample size next to the result.
Keep the same definitions
Write down the start point and end point exactly as the charter states them. In the order-entry example, lead time starts when the order arrives in the shared inbox and ends when the confirmation is sent. Use the same boundaries before the event, during it, and at every follow-up. Also record whether you measure calendar hours or working hours. An order received Friday at 4 p.m. and confirmed Monday at 9 a.m. looks very different in each unit.
Common errors
Using memory instead of observation. People remember the worst day. Even honest estimates are often wrong by a factor of two. Treat them as hypotheses.
Measuring only touch time. Counting just the work steps gives a cycle time and no lead time. The customer experiences lead time.
Changing definitions midway. If the baseline measures calendar hours and the follow-up measures working hours, the improvement is an illusion.
Treating takt time as a target for individuals. Takt time sets the pace for the process as a whole. It does not tell any one person to work faster.
Measuring on an unusual day. A holiday week, a system outage, or a staff shortage skews the data. Note unusual conditions, and sample across normal days.
Letting the measurement change the work. People work differently when watched. Tell them the measurement is about the process, not about them, and take the data over several days so the effect fades.
Measuring everything. More than a handful of measures overloads the team. Choose the ones in the charter goals, plus the supporting measures needed to explain them.
What to bring out of this step
By the time the baseline is done, the team should have:
- Baseline values, with sample sizes and ranges, for each charter goal.
- A current-state map showing cycle time, wait time, and quality at each step.
- A list of the biggest waits and the steps slower than takt.
- A written definition of each measure, so it can be repeated at the follow-ups.
Exercise
An order-entry process has a shift of 480 minutes with 60 minutes of breaks, and 75 orders arrive per day. Orders have a median lead time of 3 hours, and the value-added work per order totals 9 minutes. Calculate the takt time and the process cycle efficiency. Then explain why the median is a better summary than the mean if one order in the sample took 3 days.
Show answer
Takt time = (480 − 60) / 75 = 5.6 minutes per unit. Lead time is 3 hours = 180 minutes, so PCE = 9 / 180 = 5%. A single order that took 3 days is an extreme value. It pulls the mean far upward and misrepresents the typical experience, while the median stays near the middle of the data. The team should still report the slowest order or a high percentile, because the 3-day case is a real customer problem.
Exercise
A teammate says the baseline for the event is already known because the supervisor says orders "take about four hours." Give two reasons to measure anyway and name one method for doing it.
Show answer
First, estimates from memory are often wrong and tend to reflect the worst days, so they may overstate or understate the problem. Second, a measured baseline with a sample size and a range is needed to prove improvement at the report-out and at the 30-60-90 day reviews. A method: export the received and confirmed timestamps from the system for 20 to 30 orders, or use a tally sheet at each step.