Preparing before the event week
The event week is short, so the preparation decides how much of it is spent improving the process. A team that arrives to find no data, a booked-out room, and a missing process owner will spend Monday solving logistics. This chapter covers the pre-work and logistics that sit between the signed charter and the first morning of the event.
This chapter assumes you have already chosen a process and scope, written a charter, picked a team, and collected baseline measures such as lead time and process cycle efficiency. If those are not done, finish them first. Pre-work turns those decisions into a ready room and a ready team.
What pre-work is for
Pre-work has three jobs:
- Remove blockers so the team can observe, trial, and decide during the week.
- Give the team a shared starting point so that Monday's discussion is about the process and not about whose numbers are right.
- Protect the team's time so members are present and fully available, not pulled away by their normal work.
A useful test: if the team needs something from outside the room during the week and cannot get it within an hour, the pre-work missed it.
A timeline for the weeks before
Start about two to three weeks before the event. A first event often needs the longer lead time, because scheduling people and rooms is slower than expected.
Confirming people and their time
The most common preparation failure is a team member who joins "when they can". Treat attendance as a commitment.
- Get the manager's agreement, not only the member's. A member who says yes but whose manager still expects them to answer email will drift away by Tuesday.
- Arrange cover. Decide who handles the member's normal work during the week. For an order-entry event, someone must still confirm orders that arrive while the team is in the room.
- Block full days on calendars. Block the whole event, including the Thursday afternoon report-out, and mark the time as busy.
- Confirm the sponsor's availability for the kickoff, a mid-week check-in, and the report-out. A sponsor who can approve changes quickly is worth more than one who attends every session but cannot decide.
- Invite one or two people from outside the process. A person from a neighboring team often sees steps that insiders no longer notice.
Choosing and preparing the space
Hold the event in or close to the place where the work happens. Observation is the core of Monday and Tuesday, and a conference room across the building makes every observation a trip.
A workable setup has:
- A room with wall space for the current-state map, the fishbone, and the action list.
- Enough chairs for the team, but few enough that people stand and walk during the work.
- Easy access to the work area, so the team can watch the real process and try changes in it.
- Supplies: sticky notes in several colors, markers, flip-chart paper, tape, a stopwatch or timer for each observer, and a camera or phone for photos where policy allows.
If the process is mostly digital, such as the shared-inbox order entry in the sample charter, the "work area" is a screen. Arrange for team members to see the real inbox and the real tools, with any restricted data hidden or handled according to your privacy rules.
Preparing data and the pre-read
The baseline measures you collected earlier are part of the pre-work. Make them usable by the whole team.
Prepare:
- The charter, printed and posted on the wall.
- The baseline numbers with their source and how they were measured. A team that doubts the numbers will argue about them rather than act.
- A draft current-state map or a list of the main steps, labeled as a draft for the team to correct.
- Recent examples of the problem, such as a few orders that took far longer than the median, with identifying details removed.
- A one-page pre-read that explains the event schedule, what the team should bring, and the goals.
Keep the pre-read short. Team members read one page. They skim five.
Check the arithmetic before it goes on the wall
Baseline numbers are often computed by hand, and a mistake on the wall will be repeated all week. A short script is a cheap way to check the numbers and keep a record of how you computed them. This one reads a list of lead times, computes the median and the 90th percentile, and also computes takt time and process cycle efficiency.
import statistics
# Lead times in minutes for a sample of recent orders
lead_times = [95, 120, 140, 180, 210, 240, 250, 300, 360, 480]
median_lead = statistics.median(lead_times)
p90_lead = statistics.quantiles(lead_times, n=10)[-1]
print(f"Median lead time: {median_lead:.0f} minutes")
print(f"90th percentile lead time: {p90_lead:.0f} minutes")
# Takt time: available work time divided by customer demand
available_minutes_per_day = 450 # 480-minute shift minus 30 minutes of breaks
daily_demand_units = 90
takt_minutes = available_minutes_per_day / daily_demand_units
print(f"Takt time: {takt_minutes:.1f} minutes per unit")
# Process cycle efficiency: value-added time divided by total lead time
value_added_minutes = 12
lead_time_minutes = 240
pce = value_added_minutes / lead_time_minutes
print(f"Process cycle efficiency: {pce:.0%}")The median is 225 minutes, which matches the idea of a lead time near 4 hours. The 90th percentile shows how bad the slow cases are, and a team often finds that the slow cases drive the customer complaints. Takt time is 5.0 minutes per unit and process cycle efficiency is 5%.
A sample of ten is too small for real decisions. Use it here to show the method and collect a larger sample, ideally a few weeks of records, for the actual baseline.
Getting permission to try things
Events fail quietly when the team finds a good idea on Wednesday and learns it needs approval from someone who is away. During pre-work, agree on the boundaries of what the team may change.
- List what is allowed, such as moving equipment, changing the order of steps, creating a checklist, or changing a form.
- List what needs approval and name the person who can give it quickly.
- List what is off limits, such as the items in the charter's out-of-scope list (credit approval and shipping in the sample).
- Tell neighbors. Upstream and downstream teams should know that the process may change and who to call if a trial affects them.
Also check safety, quality, and compliance rules. A change to a regulated step may need review that cannot happen in the week. Learn this before Monday.
Pre-work checklist
The checklist below can be adapted. Keep it as a shared document and mark each item with an owner and a date.
| Item | Owner | Done when |
|---|---|---|
| Charter signed | Sponsor | Signed copy on file |
| Team confirmed with managers | Facilitator | Each manager has agreed in writing |
| Cover arranged for normal work | Team leader | Cover named for each member |
| Room and supplies booked | Facilitator | Room reserved for all days, supplies on hand |
| Baseline data checked | Team leader | Numbers and sources written on one page |
| Pre-read sent | Facilitator | All members acknowledged receipt |
| Neighbors informed | Team leader | Upstream and downstream leads notified |
| Trial permissions agreed | Sponsor | Allowed, approval-needed, and off-limits lists written |
| Report-out invitations sent | Sponsor | Leaders have the Thursday slot |
Common preparation errors
- Over-preparing the answer. Pre-work should supply data and access, not conclusions. If the leader arrives with a finished solution, the team will feel their analysis is for show, and the root cause work will be shallow.
- Collecting baseline data too late. Data gathered during Monday takes the team away from observation. Collect it earlier.
- Booking the room but not the work area. The team needs to see the actual process.
- Skipping the neighbors. A trial that surprises another team can end with the trial being stopped.
- Letting members carry a full workload. Partial attendance causes lost context. The team spends time repeating what was said while someone was away.
Exercise
Your event is two weeks away. You find that two team members' managers have not agreed to release them for the full week, and the baseline data comes from one person's memory of "about four hours". List the actions you take, in order, and name who owns each.
Show answer
First, the facilitator contacts the two managers with the sponsor's support and gets written agreement to release each member for the full week, with cover named by the team leader. This comes first because the team cannot be formed without it, and it has the longest lead time. Second, the team leader replaces the remembered number with measured data by pulling a few weeks of order timestamps from the shared inbox and computing the median and 90th percentile, checking the arithmetic with a script or spreadsheet. Third, the team leader records the source and method on the one-page baseline sheet. Fourth, the facilitator includes the checked numbers in the pre-read. If a manager will not release a member, the sponsor decides whether to replace the member or move the event date.
Exercise
A team member suggests that, to save time, the team leader should arrive with a finished design for the new order-entry process so the week can be spent on implementation. What is the risk, and what should the pre-work supply instead?
Show answer
The risk is that the team stops analyzing and starts defending or merely approving a design they did not create. Root cause analysis becomes shallow, the team has less ownership, and the leader's design may be built on assumptions that the observation would have contradicted. The pre-work should supply the charter, checked baseline data, recent examples of the problem, a draft map labeled as a draft, trial permissions, and access to the real work area, so the team can find causes and design countermeasures themselves.