Sub topic 3
Writing and Classifying Change Requests
Assume you already know basic project terms such as scope, schedule, cost, quality, risk, and resources. This chapter focuses on the record that starts formal change control: the change request.
What a change request is
A change request is a documented proposal to alter an approved project baseline, plan, deliverable, process, or requirement. A baseline is the approved version used to measure project performance. For example, adding a feature after the scope baseline was approved is a change.
A request is not permission to make the change. It gives decision-makers enough information to assess the request before anyone commits project resources.
A useful request answers these questions:
- What is being requested?
- Who requested it, and when?
- Why is it needed?
- What kind of change is it?
- Which project areas could it affect?
- What is known about the likely impact?
- What information is still unknown?
Classifying the request
Classification helps the project team route and assess requests consistently. A project may use different names, but these categories are common:
| Type | Meaning | Example |
|---|---|---|
| Corrective action | Removes the cause of an existing performance problem | Reconfigure a failed test environment |
| Preventive action | Reduces the chance of a future problem | Add an automated backup before deployment |
| Defect repair | Fixes a deliverable that does not meet its requirement | Correct an incorrect tax calculation |
| Update | Changes an approved feature, requirement, process, or plan | Add single sign-on to a customer portal |
A request can affect more than one category. For example, repairing a security defect may also be corrective action. Choose the primary type and explain the connection in the reason or impact fields.
Do not classify ordinary work as a change simply because it is new to one team. Work already included in the approved scope belongs in the project plan. A request becomes a change when it alters an approved commitment or requires a decision outside the team's existing authority.
Recording the request
Use specific language. “Improve security” is too vague. “Add single sign-on using the approved identity provider” identifies a proposed outcome that can be assessed.
Record the affected areas even when the estimated impact is zero or unknown. Typical areas include:
- Scope and requirements
- Schedule and critical-path activities
- Cost and funding
- Quality and acceptance criteria
- Risks and dependencies
- People, skills, equipment, or other resources
Leave decision fields empty until the authorized decision-maker reviews the request.
id: CR-014
title: Add single sign-on to the customer portal
requested_by: Product owner
date_submitted: 2026-03-02
type: update
reason: Customer contract now requires SSO
areas_affected: [scope, schedule, cost, risk]
impact:
scope: Adds one feature and its test cases
schedule: Three additional weeks on the critical path
cost: 18000
risk: Adds a dependency on the identity provider
status: submitted
decision: null
decided_by: null
decision_date: nullThe id must be unique so that later decisions, messages, and baseline updates can refer to the same request. The title should name the proposed change, not merely its consequence. The reason should explain the business, compliance, technical, or operational need.
A request's path to assessment
The request moves from a clear description to an impact assessment. Classification does not decide the request. It helps reviewers identify the right questions and specialists.
Quality check before submission
Check that the request:
- Names one proposed change.
- States the reason and requested outcome.
- Identifies the requester and submission date.
- Uses an appropriate classification.
- Lists affected areas, including unknown impacts.
- Separates estimates from confirmed facts.
- Has a unique identifier.
- Does not imply approval.
A vague request such as “make the portal compliant” should be returned for clarification. A stronger request names the regulation or contract requirement, the affected feature, the deadline, and the evidence needed to confirm compliance.
Exercise
A developer asks to add an unplanned export format because a customer mentioned it during a meeting. What should the change request record contain before implementation begins?
Show answer
It should identify the requested format, requester, reason, classification, affected scope and acceptance criteria, schedule, cost, quality, risk, and resources. The team should record it as submitted rather than treating the conversation as approval.