Sub topic 9
Implementing Approved Changes and Updating Baselines
This chapter assumes you know basic project management terms such as scope, schedule, cost, quality, risk, and resources. It also assumes that a change request has completed impact assessment and received a formal approval.
From approval to controlled implementation
Approval gives the project permission to make a defined change. It does not mean the team should immediately start work. First, the project manager translates the decision into updated plans, assignments, dates, budgets, and acceptance criteria.
A controlled implementation usually follows this sequence:
- Confirm the approved decision, conditions, funding, and decision authority.
- Update the affected project management plan and subsidiary plans.
- Update the relevant baselines.
- Communicate the authorized change to people who will perform or support the work.
- Implement and monitor the change.
- Verify the result against the updated requirements.
- Record completion and close the change request.
A baseline is an approved version of a plan used for comparison. The scope baseline defines the approved work. The schedule baseline defines approved timing. The cost baseline defines approved time-phased spending. A change may affect one baseline or several.
Do not rewrite a baseline merely because actual performance differs from the plan. A baseline changes only when an approved change alters the planned work, timing, or spending. Actual results remain actual results.
Updating plans and baselines
The project manager should identify every controlled document affected by the decision. For example, adding single sign-on might require updates to the scope statement, requirements documentation, work breakdown structure, schedule, cost baseline, risk register, resource plan, quality approach, and procurement documents.
The updates must remain traceable. Link the new work package, activities, budget, risks, and acceptance tests to the change request identifier. This allows an auditor or team member to answer three questions:
- What was approved?
- Which project artifacts changed?
- What evidence shows that the change was implemented?
| Area | Possible update after approval | Verification evidence |
|---|---|---|
| Scope | New feature, requirement, or work package | Accepted requirement and deliverable |
| Schedule | New activities and revised milestone dates | Updated schedule and status data |
| Cost | Authorized budget and funding period | Approved cost baseline |
| Risk | New or changed threats and responses | Updated risk register |
| Quality | New tests or acceptance criteria | Test results and acceptance record |
Record the old and new values where practical. Do not delete the earlier version. Version history preserves the project’s decision trail.
Implementing and communicating the change
Assign an owner for implementation. The owner coordinates the work, confirms dependencies, and reports progress. Team members should receive the approved requirements, revised dates, budget limits, and quality criteria. People affected by the change should also know what has changed and when it takes effect.
A simple implementation record can enforce the required order:
def implement_change(status: str, plan_updated: bool, communicated: bool) -> str:
if status != "approved":
raise ValueError("Only an approved change can be implemented")
if not plan_updated:
raise ValueError("Update the affected plans and baselines first")
if not communicated:
raise ValueError("Communicate the authorized change first")
return "implemented"
result = implement_change(
status="approved",
plan_updated=True,
communicated=True,
)
print(result)The implementation is not complete when the team finishes the task. The project must verify that the delivered result meets the approved change and that related scope, schedule, cost, quality, risk, and resource effects are understood.
Closing the change request
After verification, update the change log with the implementation date, responsible owner, affected baselines, evidence, and final status. A request can move to closed only when its decision has been recorded, approved work has been completed or formally cancelled, and the result has been communicated.
A stale baseline creates confusion because reports compare performance with a plan that no longer represents approved work. A properly updated baseline preserves meaningful performance measurement while the change log preserves why the plan changed.
Exercise
The board approves a change that adds two weeks and $12,000 to the project. What should happen before the team begins the new work?
Show answer
The project manager should update the affected plans and baselines, record the decision and new values, communicate the authorized work, and then authorize implementation.