Sub topic 8
Keeping a Change Log
This chapter assumes you know basic project management terms such as scope, schedule, cost, quality, risk, and baseline. You should also recognize the roles of the project manager, sponsor, stakeholders, and Change Control Board (CCB).
Why a change log matters
A change log is the project’s controlled record of requested changes and the decisions made about them. It creates traceability, which means you can follow a change from its original request through assessment, decision, implementation, and closure.
The log prevents a common failure: someone remembers that a change was “approved,” but nobody can show who approved it, what was approved, or which project documents were updated.
A change log is not a task list. A task list tracks work. A change log tracks decisions about whether the project should change.
What to record
Each entry should have a unique identifier and enough information for another person to understand its history. The exact fields depend on the change management plan, but a useful log includes:
| Field | Purpose |
|---|---|
| ID and title | Identifies the request and gives it a short description |
| Requester and date | Shows who submitted it and when |
| Type and reason | Explains what kind of change it is and why it is needed |
| Affected areas | Identifies effects on scope, schedule, cost, quality, risk, or resources |
| Status | Shows where the request is in its lifecycle |
| Decision and authority | Records the outcome, decision-maker, and decision date |
| Implementation and closure | Shows what changed and when the request was completed |
Use the same status vocabulary throughout the project. For example, a request might move from submitted to under_review, then to approved, rejected, or deferred. An approved request can move to implemented and finally closed.
The log should link to supporting information, such as the impact assessment, meeting record, revised requirements, or updated schedule. Do not place every detail in the log. Store the evidence in the appropriate project document and record its location.
Recording decisions clearly
A decision must be specific. “Approved” is incomplete unless the entry identifies the approved scope, conditions, authority, and follow-up work. If the CCB approves a request only when the sponsor accepts an additional budget, record that condition.
A rejected request also needs a reason. For example, the team might reject a feature because its benefit does not justify a four-week schedule delay. A deferred request remains visible, but it is not part of the current approved work.
Update the log promptly after the decision. Then notify affected stakeholders and update the relevant plans, baselines, requirements, and work items. The log is useful only when it matches the current project state.
from dataclasses import dataclass
from datetime import date
@dataclass
class Change:
change_id: str
title: str
status: str
decision: str | None = None
decided_by: str | None = None
decision_date: str | None = None
def record_decision(change: Change, decision: str, approver: str) -> None:
allowed = {"approved", "rejected", "deferred"}
if change.status != "under_review":
raise ValueError("Only changes under review can receive a decision")
if decision not in allowed:
raise ValueError(f"Unknown decision: {decision}")
change.status = decision
change.decision = decision
change.decided_by = approver
change.decision_date = date.today().isoformat()
request = Change("CR-014", "Add customer portal SSO", "under_review")
record_decision(request, "approved", "Change Control Board")
print(request)The example enforces one useful control: only a request under review can receive a decision. A real system would also record the impact assessment, approval conditions, implementation owner, and links to updated baselines.
A traceable change flow
Good operating practice
Assign one person, often the project manager or change coordinator, to maintain the log. The CCB makes decisions when authority is delegated to it, but the log owner records and communicates those decisions.
Review open requests during project status meetings. Check for duplicate requests, overdue decisions, requests with missing impact information, and approved changes that were never implemented. Protect the log from casual editing by using access controls or a versioned repository.
Exercise
A stakeholder says that CR-014 was approved in a meeting, but the change log still shows it as under review. What should the project manager do first?
Show answer
Verify the meeting decision and its authority, obtain the decision record or confirmation, then update the log and communicate the result before implementation begins.