Sub topic 6
The Change Control Board and Who May Decide
Assume you know basic project management terms such as scope, schedule, cost, quality, risk, sponsor, and stakeholder. You should also know that a baseline is an approved version of the project plan used for comparison. Once a baseline exists, a proposed change needs a decision by the person or group with the right authority.
What the Change Control Board does
A Change Control Board (CCB) is a group that reviews proposed changes and decides what happens to them. The CCB does not create every change request. It evaluates requests after the project team has described the likely effects.
The CCB has four main responsibilities:
- Confirm that the request is clear enough to review.
- Check the impact assessment.
- Compare the change with project goals, constraints, contracts, and priorities.
- Record a decision and any conditions attached to it.
A CCB may approve, reject, or defer a change. To defer means to postpone the decision until more information, funding, or a business decision is available. The board should not approve a change simply because a stakeholder has asked for it.
The board also protects the project from fragmented decisions. For example, a product owner may understand customer value, while a technical lead understands system risk. Reviewing the change together helps the project consider both.
Membership and decision authority
CCB membership depends on the project. A typical board includes:
- The project manager, who explains the effect on delivery and coordinates the decision.
- The project sponsor, who represents business ownership and can resolve major priority or funding issues.
- A customer or product representative, who explains value and acceptance needs.
- A technical or engineering representative, who evaluates feasibility, architecture, and technical risk.
- A quality or compliance representative, when the change affects standards, testing, safety, or regulation.
- A finance, procurement, or operations representative, when the change affects contracts, suppliers, or running costs.
Membership should be small enough for timely decisions. A person may be a permanent member or invited only when the request affects that person's area.
The CCB's authority must be defined in the change management plan. The plan should state which decisions the project manager may make, which require the CCB, and which must go to the sponsor, customer, steering committee, or another governing body.
| Change condition | Likely decision authority |
|---|---|
| No effect on an approved baseline and within team authority | Project manager or delegated lead |
| Material effect on scope, schedule, cost, quality, or risk | Change Control Board |
| Effect on contract, legal obligation, or organizational funding | Sponsor, customer, or authorized governance body |
A threshold is a limit that triggers escalation. Examples include more than two weeks of schedule impact, a cost increase above a stated amount, or a change to a contractual requirement. Thresholds prevent both excessive bureaucracy for small changes and unauthorized approval of major ones.
How the board makes a decision
The board should use the same criteria for every request. It can ask:
- Does the change support the business case or project objectives?
- What value does it add, and what work or benefits must be delayed?
- Are the schedule and cost estimates credible?
- Does it introduce unacceptable technical, security, quality, or compliance risk?
- Are people, skills, suppliers, and funding available?
- Which baselines, requirements, deliverables, or contracts would change?
The decision record should identify the decision, its date, the authority that made it, and any conditions. An approval might require a revised estimate, a risk response, or customer acceptance before implementation. The project manager then communicates the decision and ensures that the approved work follows the normal implementation and tracking process.
Exercise
Exercise
A proposed feature adds three weeks to the schedule and requires new compliance testing. The product owner supports it, but the project manager has authority only for changes under one week. Who should decide, and why?
Show answer
The Change Control Board should review it because the change exceeds the project manager's delegated threshold and affects both schedule and compliance. The board may approve, reject, or defer it, and must record its decision.