Sub topic 11
Configuration Management and Change Control
Prerequisites and the working model
This chapter assumes you know basic project management terms such as scope, schedule, cost, quality, risk, baseline, stakeholder, and project manager. A baseline is the approved version of a plan or product description used for comparison. Integrated change control decides whether a proposed change may happen. Configuration management keeps the approved project information and deliverables identified, versioned, and consistent.
These practices solve different problems:
- Change control asks, “May we change this?”
- Configuration management asks, “What exactly exists now, which version is approved, and where is it used?”
- Together they provide authorized change and reliable records.
A configuration item is a product, document, requirement, interface, or other component that must be identified and controlled. Examples include a requirements specification, a software release, a test plan, a database schema, or a training manual.
How the two processes connect
Suppose a team wants to add single sign-on to a customer portal. The change request identifies the affected scope, schedule, cost, risk, and requirements. Configuration management identifies the specific items that will change, such as the portal requirements, interface design, security test cases, and release package.
The request should not be implemented merely because someone approves it in a meeting. The team should first record the decision, update the affected configuration items, verify the results, and establish new approved versions where required.
Configuration management usually includes these activities:
- Configuration identification: define which items need control and give each one a unique name or identifier.
- Version control: distinguish one approved state from another and preserve earlier states.
- Status accounting: record the current version, owner, approval status, and relationship to changes.
- Configuration verification and audit: check that the recorded item matches the delivered item and that required approvals exist.
A practical traceability record
A configuration record connects a change request to the items it affects. The record might include the following fields:
| Field | Example |
|---|---|
| Change request | CR-014 |
| Configuration item | Portal requirements specification |
| Current version | 2.1 |
| New version | 2.2 |
| Approval status | Approved for implementation |
| Verification evidence | Security test report ST-09 |
| Owner | Business analyst |
The change log records the decision and overall progress. A configuration record provides more detailed evidence about particular project items. They should reference each other rather than duplicate unrelated information.
A simple registry can expose invalid relationships before implementation:
items = {
"portal-requirements": {"version": "2.1", "status": "approved"},
"security-test-plan": {"version": "1.4", "status": "approved"},
}
approved_changes = {
"CR-014": ["portal-requirements", "security-test-plan"]
}
def register_version(change_id: str, item_id: str, new_version: str) -> None:
if change_id not in approved_changes:
raise ValueError("The change has not been approved")
if item_id not in approved_changes[change_id]:
raise ValueError("The item is outside the approved change scope")
if item_id not in items:
raise KeyError("Unknown configuration item")
items[item_id]["version"] = new_version
items[item_id]["status"] = "pending verification"
register_version("CR-014", "portal-requirements", "2.2")
print(items["portal-requirements"])The example does not replace a configuration management system. It demonstrates an important control: an item cannot be updated under a change that does not authorize it.
Baselines, audits, and common errors
After an approved change is implemented and verified, the project may update a product baseline, a schedule baseline, a cost baseline, or several of them. The old baseline should remain available for traceability. Overwriting it removes evidence of what was approved at the earlier point.
Configuration audits can be conducted before release, at a milestone, or after a significant change. A functional audit checks whether the product satisfies its approved requirements. A physical audit checks whether the delivered components match the approved records and documentation.
Common failures include:
- Editing a controlled document without increasing its version.
- Updating a design but forgetting its test cases or user documentation.
- Treating a file as approved because it is stored in a shared folder.
- Approving a change without identifying the affected configuration items.
- Updating a baseline before the changed deliverable has passed verification.
- Keeping versions but not recording who approved them or why.
Exercise
CR-014 is approved to change the portal requirements and security tests. A developer also edits the training guide because the new login screen looks different. What should the project manager do?
Show answer
Add the training guide to the impact assessment and change records if it is affected, then obtain authorization before treating that edit as part of the approved change. The guide needs its own version update and verification.