Approving, Rejecting or Deferring a Change
Assume you know basic project terms such as scope, schedule, cost, quality, risk, and baseline. You should also know the roles of the sponsor, project manager, and stakeholders. This chapter focuses on the decision made after a change request has been assessed.
A change decision determines whether the project will alter its approved plan. The decision must be based on evidence, authority, and the project's goals. A request is not approved merely because someone important asks for it.
The three main decisions
A decision-maker normally chooses one of three outcomes.
| Decision | Meaning | Next action |
|---|---|---|
| Approve | The project accepts the change and its effects | Plan and implement the change |
| Reject | The project will not make the change | Record the reason and close the request |
| Defer | The request remains possible but is postponed | Record the condition or date for review |
Approval means more than permission to start work. It also authorizes updates to affected plans, baselines, requirements, resources, and communications. The project team must not implement an approved change until the decision and required updates are recorded.
Rejection does not mean the request was unreasonable. The change may have poor value, excessive risk, insufficient funding, or a conflict with project objectives. Record the reason so that the same request is not repeatedly reconsidered without new information.
Deferral is useful when the decision depends on missing information, a future milestone, available funding, or a related project decision. A deferred request needs a review condition. “Deferred” without an owner or review date is usually a hidden rejection.
Decision authority and evidence
The change management plan defines who may decide. A Change Control Board, or CCB, may decide changes above a defined threshold. A project manager may decide small changes within delegated authority. A sponsor may decide changes that affect the business case, funding, or major commitments.
The decision-maker should review:
- The reason and type of the request.
- Effects on scope, schedule, cost, quality, risk, and resources.
- Dependencies and assumptions.
- Options, including doing nothing.
- Required funding and capacity.
- Effects on contracts, regulations, customers, and other stakeholders.
- The recommendation from the project manager or subject-matter experts.
The decision should state what is authorized, what is not authorized, and any conditions. For example, approval might depend on signing a supplier amendment or completing a security review.
ALLOWED = {
"submitted": {"under_review"},
"under_review": {"approved", "rejected", "deferred"},
"deferred": {"under_review"},
"approved": {"implemented"},
"implemented": {"closed"},
"rejected": {"closed"},
}
def move(current: str, new: str) -> str:
if new not in ALLOWED.get(current, set()):
raise ValueError(f"Cannot move a change request from {current} to {new}")
return new
status = "submitted"
status = move(status, "under_review")
status = move(status, "approved")
print(status)This status model prevents an approved request from being marked closed before implementation. It also prevents work from bypassing review.
Recording and communicating the decision
Update the change log immediately after the decision. At minimum, record:
- Change request identifier and title.
- Decision: approved, rejected, or deferred.
- Decision date and decision-maker.
- Rationale and conditions.
- Required plan or baseline updates.
- Implementation owner and target date.
- Stakeholders who must be informed.
For an approved change, communicate the new commitments before work begins. For a rejected change, explain the outcome to the requester. For a deferred change, state when and how it will return for review.
The project manager then coordinates implementation, monitoring, and closure. If the approved change alters the scope, schedule, or cost baseline, the old baseline remains a record of the previous commitment. The updated baseline becomes the basis for future performance measurement.
Common decision errors
A common error is treating silence as approval. No work should begin until an authorized decision is recorded. Another error is approving a request without identifying its effect on the baseline. This creates conflicting commitments and makes performance difficult to measure.
A further error is using deferral to avoid an uncomfortable decision. If the request has no realistic review condition, reject it or return it for more analysis.
Exercise
A change adds a customer-required feature but increases the schedule by three weeks and has no funding source. What should the decision record contain before approval?
Show answer
It should contain the impact assessment, funding decision, schedule effect, risks, approval authority, conditions, implementation owner, and communication plan. Approval should wait if the required funding or authority is missing.