Sub topic 1
Baselines: What a Change Is Measured Against
Prerequisites
Assume you know basic project management terms: scope, schedule, cost, quality, risk, resources, project management plan, sponsor, and stakeholder. You should also understand that a project plan can be approved and then used to guide and measure project work.
What a baseline is
A baseline is an approved version of a project plan or measurement used for comparison. It records what the project agreed to deliver, when it should be delivered, and what it should cost.
Common project baselines include:
- The scope baseline: the approved scope statement, work breakdown structure, and work package descriptions.
- The schedule baseline: the approved start dates, finish dates, milestones, and sequence of work.
- The cost baseline: the approved time-phased budget.
- The performance measurement baseline: an integrated view of scope, schedule, and cost used to measure performance.
A baseline is not a prediction that can be silently edited. It is a control point. If the team changes it without formal approval, the project loses a reliable way to identify variance.
A variance is the difference between the approved baseline and actual or forecast results. For example, if a milestone was baselined for 1 June but is forecast for 22 June, the schedule variance is visible because the original commitment remains recorded.
Why changes need baseline control
After a baseline is approved, a requested change may affect several parts of the project. Adding a feature can increase scope, extend the schedule, require more resources, raise cost, introduce new risks, or change quality requirements.
The team should therefore compare the request with the current approved baselines. The question is not only, “Can we do this?” It is also:
- What approved work will be added, removed, or changed?
- Which milestones or dependencies will move?
- How much budget or staff time is needed?
- Will quality criteria or acceptance tests change?
- Which risks will be created or reduced?
- Does the project still support its business case?
This comparison creates a common reference for decision-makers. Without it, a change may appear small because its effects are spread across different plans.
Baselines through the change flow
Integrated change control uses baselines as inputs to impact analysis. A typical flow looks like this:
The baseline remains unchanged while a request is under review. If the request is rejected or deferred, the existing commitments continue to govern the work. If it is approved, the project updates only the affected baselines through the defined control process.
For example, an approved request to add single sign-on might add a feature to the scope baseline, move a release milestone in the schedule baseline, and increase the cost baseline. The update should identify the decision authority, approval date, new values, and reason for each change.
Common baseline errors
Intermediate project teams often make these mistakes:
- Treating an early draft as the baseline before formal approval.
- Updating the baseline to match actual performance instead of recording the variance.
- Changing one plan while ignoring related plans.
- Comparing a request with an outdated baseline.
- Replacing the original baseline so that the project’s history disappears.
- Allowing work to begin because someone gave informal approval in a meeting or message.
A sound process versions the baseline, records who approved the change, and communicates the resulting commitments to affected stakeholders.
Exercise
A sponsor asks the team to add a reporting feature. The team can build it within the existing budget, but the release date will move by two weeks. Which baselines should the team examine before deciding?
Show answer
The team should examine the scope and schedule baselines first, then confirm effects on cost, quality, risk, and resources. The schedule impact may also require changes to milestones, dependencies, and the delivery forecast.