Pitfalls: Scope Creep, Informal Approvals and Stale Baselines
Assume you know the basic project management terms scope, schedule, cost, quality, risk, and baseline. You should also understand the roles of the project manager, sponsor, and stakeholders. This chapter focuses on failures that weaken integrated change control after the project plan and baselines have been approved.
Scope creep: work enters without a decision
Scope creep is the gradual addition of work without a documented review and approval. Each addition may look small, but the combined effect can change the delivery date, budget, quality targets, or project risks.
Common sources include:
- A stakeholder asks a team member for “one quick addition.”
- A developer fixes or improves something outside the approved requirements.
- A customer comment is treated as an instruction rather than feedback.
- A project team accepts extra work to avoid a difficult conversation.
- A defect repair is confused with a new feature.
A useful test is: “Does this request change an approved requirement, deliverable, acceptance criterion, constraint, or assumption?” If yes, record it as a change request or use the project’s defined process for handling it.
A change request does not need to be approved. It needs to be visible and assessed. Rejecting or deferring a request is a controlled result. Hiding it is not.
flowchart TD
A[New request appears] --> B{Changes approved scope or constraint?}
B -- No --> C[Handle as routine project work]
B -- Yes --> D[Record change request]
D --> E[Assess impact]
E --> F{Authorized decision}
F -- Approve --> G[Update plan and baseline]
F -- Reject or defer --> H[Record decision and communicate]Informal approvals: agreement is not authorization
An informal approval is a verbal, chat-based, or implied agreement that bypasses the authority defined in the change management plan. For example, a sponsor might say, “That sounds fine,” during a meeting. The team then starts work without recording the decision or checking whether the sponsor has authority over the affected baseline.
This creates several problems:
- The team cannot prove what was approved.
- Different stakeholders may remember different conditions.
- The budget or schedule may be changed without authority.
- The project manager may discover the change after resources are committed.
- The same request may be reviewed more than once.
The project manager should convert significant decisions into a durable record. The record should identify the request, decision, decision maker, date, conditions, and affected baselines. A meeting minute, approved workflow entry, or change log entry can provide this evidence if it follows the project’s rules.
| Weak practice | Controlled practice |
|---|---|
| “The client agreed in the meeting.” | Record the decision, authority, conditions, and date. |
| Start work while approval is pending. | Wait, unless the emergency process applies. |
| Treat silence as approval. | Require an explicit decision. |
Stale baselines: measuring against yesterday’s plan
A baseline is an approved version of scope, schedule, or cost used for comparison. A baseline becomes stale when an approved change is implemented but the affected plans and baselines are not updated.
For example, a board approves a three-week feature addition. The team adds the feature, but the schedule baseline still shows the original completion date. Later reports show a delay that was already authorized. This makes performance reporting misleading and encourages unnecessary corrective action.
After approval, the project manager should:
- Update the project management plan and affected subsidiary plans.
- Update the relevant scope, schedule, and cost baselines according to governance rules.
- Update requirements, estimates, risks, assumptions, and resource assignments.
- Link the implementation work to the change request.
- Communicate the new approved targets.
- Preserve the previous baseline for historical traceability.
Do not rewrite a baseline to hide poor performance. A baseline changes because an authorized change alters the approved target. Normal variance remains visible against the current approved baseline.
def baseline_action(decision: str) -> str:
actions = {
"approved": "update affected plans and baselines before implementation",
"rejected": "keep baselines unchanged and close the request",
"deferred": "keep baselines unchanged and schedule a future review",
}
try:
return actions[decision]
except KeyError:
raise ValueError("Decision must be approved, rejected, or deferred")
print(baseline_action("approved"))Good practice: maintain traceability
A change log should connect the request to its assessment, decision, implementation, and closure. Use identifiers such as CR-014 in planning records, work items, meeting minutes, and status reports. This connection helps an auditor or team member answer:
- What changed?
- Who requested it?
- Who decided?
- Why was it decided?
- Which deliverables and baselines changed?
- Was the result verified and communicated?
Exercise
Exercise
A sponsor verbally asks a team to add a dashboard. The team starts building it, but the schedule and cost baselines remain unchanged. Identify two control failures and the next action.
Show answer
The team accepted an informal approval and began scope work without a recorded decision. The baseline is stale because the approved target was not updated. Record and assess the request, confirm the authorized decision, then update affected plans and baselines if it is approved.